Vivek Gadodia, Chief Executive Officer of the Company, commented:
"The first quarter of the Year has been a truly challenging time for the
Company, with the market remaining weak, the S189A process at Cullinan Mine and
the rest of Group, and the implementation of the Business Rescue process at
Finsch, all of which have been managed against a very tight balance sheet. Of
note, despite these headwinds, production from underground areas at Cullinan
Mine was down only 3% quarter on quarter, notwithstanding productivity impacted
by the S189A process, maintenance related downtime, as well as the broader
uncertainty surrounding the Company and the diamond sector. Overall production
was down 5% quarter on quarter as a result of tailings processed during Q1 FY
2027 being 14% lower quarter on quarter.
The Company announced the commencement of a Strategic Review at the beginning of
October, which is underway. The Strategic Review can be summarised as
concurrently progressing three distinct workstreams - short-term liquidity
support, a consensual refinancing, and/or a sale of the Company's assets, with a
view to maximising the possible outcomes for the Company's stakeholders.
The Company has reached several important milestones in recent weeks The S189A
process has concluded, which is expected to result in sustainable annualised
savings of c. US$3 million. As part of the first workstream of the Strategic
Review, a binding Advance Payment Agreement has been agreed for future run-of
-mine production to provide immediate short-term liquidity support as well as a
Forbearance Period being agreed with our Senior Secured Lender, which provides
the Company with the platform to progress the other workstreams within the
Strategic Review process.
Overall, the diamond sector remains at historic low levels, but with robust
demand for high value stones. There appeared to be a cautious but uneven
bottoming of the overall market towards the end of September, with prices on
smaller goods also seeing some improvement against prices from June/July. The
Company realised average prices of US$63/ct (compared to US$76/ct for the
previous quarter). Management consider this to be largely attributable to a
weaker product mix.
The Company will continue to focus on mining areas of the Cullinan Mine that
have the maximum potential for high value stones. Management expect improvements
to both product mix and grade from November onwards following conclusion of the
S189A process, completion of scheduled maintenance during Q1 FY 2027 within the
C-Cut as well as sourcing of some critical mining equipment that began to arrive
at the Cullinan Mine from October onwards.
The Company also announced on 22 October that due to delays in auditing the
Group's financial statements for the financial year ended 30 June 2026, it was
unable to publish its results before the 31 October 2026, which has resulted in
the suspension of the listing of and trading in the Company's shares. In
addition, Euronext Dublin has confirmed by announcement on 2 November 2026 a
temporary suspension of listing and trading of the second lien notes due 2030
issued by Petra Diamonds US$ Treasury plc, which is an automatic consequence of
such delays. The Company intends to seek restoration of listing and resumption
of trading of its shares and second lien notes, following publication of the
Group's audited financial statements for the financial year ended 30 June
2026.The audit work remains ongoing in order to complete the publication of the
financial results as soon as possible, alongside the Company's continuing
discussions with potential finance providers.
The Company would like to thank its employees for the tremendous resilience and
fortitude displayed during perhaps the most challenging time experienced both by
the Company and the diamond sector as a whole, especially in South Africa. In
addition, the Company would also like to thank all its stakeholders, including
its shareholders and lenders for the on-going support in helping the Company as
it seeks to navigate through these challenges."
Q1 FY 2027 Salient Points
· LTIFR increased to 0.69 and LTIs to 3 (Q4 FY 2026: 0.43 and 2 respectively)
· Underground ore processed decreased by 3% at Cullinan Mine compared to Q4 FY
2026, mainly attributed to the S189A process which impacted shift patterns, as
well as availability of mining equipment and planned maintenance, which was
completed during the quarter. Tailings processed was lower by 14% quarter on
quarter, largely due to increased tailings processed during Q4 FY 2026
· Total revenue amounted to US$21 million (Q4 FY 2026: US$30 million) from
329,948 carats sold (Q4 FY 2026: 395,005 carats), with an average price of
US$63/ct (Q4 FY 2026: US$76/ct). Average diamond prices for the period decreased
c. 18% compared to Q4 FY 2026 due to a weaker product mix and lower occurrence
of Type II diamonds
· The South African Rand strengthened during the quarter, averaging
ZAR16.20:US$1 (Q4 FY 2026: ZAR16.47:US$1)
· Bank loans and borrowings, including accrued interest and deferred
transaction costs, represent the Company's ZAR1.75 billion (US$107 million)
revolving credit facility (RCF). As at 30 September 2026, the RCF had been fully
drawn
· In July 2026, the Group secured an additional R300 million (approximately
US$18 million) working capital facility from Absa Bank under its existing
banking arrangements. The facility has an 18-month term, maturing in January
2028. This additional facility of R300 million is currently fully drawn
· Consolidated net debt increased to US$348 million as at 30 September 2026
(30 June 2026: US$322 million). Unrestricted cash on hand of US$7 million as at
30 September 2026 (30 June 2026: US$9 million)
· The Business Rescue practitioners continue to implement the Business Rescue
Plan at Finsch
· Litigation against the Company's former Head of Sales & Marketing is
ongoing, with a first instance decision in Dubai finding in favour of the
Company's claim of breach of contract and making an award of c. US$2.1 million.
The Company intends to take steps to obtain final judgement, enforce this award
and pursue available claims
Post Period
· A strategic review commenced on 1 October to address liquidity needs of the
business: binding Advance Payment Agreement executed and Senior Secured Lender
Forbearance Period agreed
· Following a hearing on 14 October, a UK court made a winding-up order in
respect of Petra Diamonds UK Treasury Limited, a wholly owned, indirect
subsidiary of the Company regarding £5,647,811.32 for FY2025 due to HMRC in
relation to corporation tax. Further updates will be provided as and when
appropriate
Amre Youness, who had the right to attend meetings of the Board of the Company,
has informed the Chair that he will not attend any future meetings. The Board
wishes to express its gratitude to Amre for his longstanding and continued
support for the Company.
Updates on Strategic Review
A strategic review was announced on 1 October 2026 which includes the
consideration of all potential paths to address liquidity needs of the business,
continue discussions for a refinancing of the Company, while also assessing any
potential sale of the Company's assets with a view to maximising the possible
outcomes for the Company's stakeholders.
This process continues to progress, with the immediate objective being injection
of further working capital liquidity in order to continue operations at the
Cullinan Mine which has been secured as detailed below.
Advance Payment Agreement and Senior Secured Lender Forbearance
The Company announces that its subsidiary, Cullinan Diamond Mine Proprietary
Limited ("Cullinan Mine"), has entered a binding Advance Payment Agreement with
a mid-stream diamantaire group ("Offtaker"). The Offtaker will make available at
least US$20 million through revolving advance payments for all future run-of
-mine production. The conditions and commercials attached with this facility are
in line with other agreements of this type. Cullinan Mine may terminate this
agreement at any time without penalty, provided that any outstanding amounts are
settled in full.
Concurrently, and as a condition to the Advance Payment Agreement, Petra has
also agreed a forbearance and consent letter with its Senior Secured Lender
("Forbearance"), pursuant to which the Senior Secured Lender will not take
enforcement action on specified defaults until the earlier of 12 months from the
date of the letter or full repayment of any outstanding amounts under the
Advance Payment Agreement, subject to certain ongoing conditions being met.
Together, the Advance Payment Agreement and the Forbearance provide near-term
liquidity and stability for Petra and Cullinan Mine whilst it continues to
progress its strategic review to find a long-term financing solution.
S189A at Cullinan Mine and rest of Group
As previously announced, on 28 July 2026, the Company launched a Section 189A
labour restructuring process during Q4 FY 2026. This process resulted in
extensive engagements over the past 3-4 months, resulting in a conclusion
achieved during October 2026. As a result of the process, regrettably, 25
positions have been made redundant and certain variable cost reductions have
been implemented. The outcome of the S189A process is expected to result in c.
US$3m in annualised sustainable savings.
The Company is now focused on moving on from the challenges of the S189A
process, and re-orientating the workforce towards improving production and
safety performance achieved during Q1 FY 2027.
Litigation against the Company's former Head of Sales & Marketing
Earlier this year, the Company commenced claims, including in South Africa and
Dubai, against its former Head of Sales & Marketing on the basis that, while
employed, he was believed to have established and operated a competing business
using knowledge, contacts and opportunities acquired through his employment
within the Company's group.
In September of this year, in Dubai, a Court of first instance found in favour
of the Company, against its former Head of Sales & Marketing ("the First
Defendant") and a company established by him, Noble Star DMCC ("the Second
Defendant", and together "the Defendants"), finding that the Defendants
committed acts of unlawful competition through the First Defendant's
establishment of the Second Defendant, which carried on similar business
activity and operated in a similar market during the period of his employment
within the Company's group.
The Court found that this constituted a contractual breach by the First
Defendant and a tortious wrongful act by the Second Defendant and made an award
of AED 7,764,544 in favour of the Company, being worth approximately US$2.1
million as at today's date. The Company intends to take steps to obtain final
judgement, enforce this award and pursue available claims. Further updates will
be shared, as appropriate.
Updates on the Business Rescue Process at Finsch
As previously announced, on 7 August 2026, the Business Plan presented by the
Business Rescue Practitioners was adopted. Progress has been made since then,
with the following main elements to note:
1. Recovery of underground movable assets nearly complete, with a view to
completing all underground operations as soon as possible.
2. Asset sales have commenced, with over 3000 lots catalogued for disposal
largely through the auction route, with these auctions underway with the speed
of auctions governed by the applicable Mine Health and Safety Act.
3. A skeleton crew continues to work under the custodianship of the Business
Rescue Practitioners to implement the Business Plan.
4. A S189A process was initiated and completed, with a retrenchment agreement
signed on 14 of October 2026, which resulted in the retrenchment of all
employees at Finsch, with the skeleton crew continuing to help implement the
approved Business Plan, and who will also exit once the work is completed.
The Business Rescue Practitioners continue to progress the Business Plan, with
the immediate focus on completing the underground activities and progressing the
asset sales. Further updates will be provided on material developments going
forward.
Operating Summary
Unit FY 2027 FY 20261
Q1 Q4 Var. Q1 Var. 12 months
Safety
LTIFR Rate 0.69 0.43 +60% 0.23 +200% 0.35
LTIs Number 3 2 +50% 1 +200% 6
Sales
Diamonds sold Carats 329,948 396,398 -16% 278,968 +18% 1,399,474
Revenue2 US$m 21 30 -31% 36 -43% 149
Production
ROM tonnes Mt 866,978 894,762 -3% 959,257 -10% 3,814,819
Tailings and Mt 195,135 227,535 -14% 154,756 +26% 778,455
other tonnes
Total tonnes Mt 1,062,133 1,122,297 -5% 1,114,013 -5% 4,539,274
treated
ROM diamonds Carats 230,680 271,628 -15% 286,897 -20% 1,174,433
Tailings and Carats 60,837 67,622 -10% 43,586 +40% 224,171
other
diamonds
Total Carats 291,517 339,250 -9% 330,483 -12% 1,398,604
diamonds
1 FY26 numbers exclude Finsch
2Revenue reflects proceeds from the sale of rough diamonds and excludes revenue
from profit share arrangements
LTIFR and LTIs increased to 0.69 and 3 respectively, from 0.43 and 2 in Q4 FY
2026. The increase is associated with recent organisational restructuring
initiatives, with approximately 66% of LTIs linked to behavioural factors,
specifically inadequate risk awareness and hazard recognition. This highlights
the need for strengthened safety leadership, engagement, and risk awareness
interventions during periods of organisational change.
Production at Cullinan Mine during the quarter was down compared to the previous
quarter. This was largely as a result of scheduled maintenance and a breakdown,
which resulted in non-availability of two crushers servicing the C-Cut during
September and into October, which impacted both the product mix as well as the
grade. Availability of critical mining equipment also played a role in delaying
planned ramp-up production from the CC1E. The delays in procuring critical
mining equipment were as a direct result of cash management steps, which
resulted in deferring procurement of critical mining equipment. Despite these
challenges, as well as the morale and productivity dips related to the S189A
process for the entirety of the quarter, underground ROM production was down
only 3% quarter on quarter. Tailings production was down by 14% quarter on
quarter, largely because Q4 FY2026 saw enhanced tailings processing.
We expect improvements in both product mix and grade, which should improve the
carats produced from underground from November onwards, with critical mining
equipment arriving at Cullinan Mine from October, with continued deliveries in
November, as well as the completion and re-operationalisation of the C-Cut
crushers.
Q1 FY 2027 sales results
Diamond sales for Q1 FY 2027 was US$21 million from 329,948 carats. Average
prices decreased c. 18% compared to Q4 FY 2026. Rough diamond sales results for
the respective periods are shown below.
+-------------+------+-------+-------+-------+-------+-------+---------+
|Cullinan Mine|Unit |FY 2027|FY 2026|Var |FY 2026 |FY 2026 |
+-------------+------+-------+-------+-------+-------+-------+---------+
| |Q1 |Q4 |Q1 |Var | |
+-------------+------+-------+-------+-------+-------+-------+---------+
|Revenue, US$m|US$m |21 |30 |(31.4%)|36 |(42.6%)|149 |
+-------------+------+-------+-------+-------+-------+-------+---------+
|Diamonds Sold|cts |329,948|396,398|(16.8%)|278,968|18.3% |1,399,474|
+-------------+------+-------+-------+-------+-------+-------+---------+
|Average $/ct |US$/ct|63 |76 |(17.7%)|130 |(51.6%)|106 |
+-------------+------+-------+-------+-------+-------+-------+---------+
Overall, the markets showed some signs of bottoming out in August and September,
with good demand for the coarser higher valued goods. The Cullinan Mine,
experienced a period of depressed product mix through the quarter, largely due
to the challenges noted above, where Cullinan Mine was not able to maximise
production from the intended production areas as a result of unavailability of
two crushers and a delay in delivery of critical mining equipment.
FURTHER INFORMATION
There is no certainty as to the outcome of the Strategic Review. The Board will
make further announcements in due course.
The person responsible for releasing this announcement is Tumi Dakada, General
Counsel and Company Secretary of the Company.
For further information please contact:
Investor Relations, London
Julia Stone Telephone: +44 (0)7988 702005
Kelsey Traynor
[email protected]
Notes:
The following definitions have been used in this announcement:
a. cpht: carats per hundred tonnes
b. LTIs: lost time injuries
c. LTIFR: lost time injury frequency rate, calculated as the number of LTIs
multiplied by 200,000 and divided by the number of hours worked
d. FY: financial year ending 30 June
e. CY: calendar year ending 31 December
f. Q: quarter of the financial year
g. ROM: run-of-mine (i.e. production from the primary orebody)
h. m: million
i. Mt: million tonnes
j. Mcts: million carats
k. period: the first quarter of FY 2026
l. Preceding Period: Q4 FY 2025
m. Prior Period: Q1 FY 2025
About Petra Diamonds Limited
Petra Diamonds is a leading independent diamond mining group and a supplier of
gem quality rough diamonds to the international market. The Company's portfolio
incorporates interests in two underground mines in South Africa (Cullinan Mine
and Finsch). The Group's principal operating asset is Cullinan Mine. Finsch
entered business rescue on 29 May 2026.
Petra strives to conduct all operations according to the highest ethical
standards and only operates in countries which are members of the Kimberley
Process. The Company aims to generate tangible value for each of its
stakeholders, thereby contributing to the socio-economic development of its host
countries and supporting long-term sustainable operations to the benefit of its
employees, partners and communities.
Petra is quoted on the Main Market of the London Stock Exchange under the ticker
'PDL'. The Company's loan notes, due in 2030, are listed on EuroNext Dublin
(Irish Stock Exchange). For more information, visit www.petradiamonds.com.
Corporate and financial summary as at 30 September 2026
Unit As at 30 As at As at 31 As at As
Sept 2026 30 June March 31 at
2026 30
2026 Dec Sept
2025 2025
Total cash at 26 28 34 55 46
bank1,2 US$m
Diamond debtors US$m 1 3 21 - 2
Diamond US$m 9 14 29 46 44
inventories3
Carats 160,110 207,646 434,182 608,217 468,733
2030 Loan Notes4 US$m 249 243 251 246 n/a
2026 Loan Notes4 US$m n/a n/a n/a n/a 233
Bank loans and US$m 126 109 102 92 102
borrowings5
Consolidated Net US$m 348 322 298 284 287
Debt6
Bank facilities US$m - - - 11 -
undrawn and
available5
Notes:
1. The following exchange rates have been used for this announcement: average
for Q1 FY 2027 US$1: ZAR16.20 (FY 2026: US$1: ZAR18.15); closing rate as at 30
September 2026 US$1: ZAR16.42.
2. The Group's cash balances comprise unrestricted balances of US$7 million,
and restricted balances of US$19 million.
3. Recorded at the lower of cost and net realisable value.
4. The 2030 Loan Notes have a carrying value of US$249 million
which represents the nominal value of US$228 million, plus fair value
adjustments at modification date in terms of IFRS 9 and net of any unamortised
transaction costs capitalised which were incurred during the Refinancing
completed during November 2025. The 2026 Loan Notes represent the gross capital
of US$228 million (including PIK), plus accrued and unpaid interest for the
relevant periods, up to the refinancing date.
5. Bank loans and borrowings represent the Group's ZAR1.75 billion (US$107
million) revolving credit facility and ZAR300 million (US$18 million) additional
facility granted in July 2026, including accrued interest of US$6 million, less
repayments of US$5 million. As at 30 September 2026, both the revolving credit
facility and the additional facility were fully drawn.
6. Consolidated Net Debt is bank loans and borrowings plus loan notes, less
cash and diamond debtors.