China State Construction Engineering (CSCEC) said the main bridge of the Saribas Bridge project in Malaysia, which it is building, has been connected. CSCEC says the Saribas Bridge is its first bridge project in Malaysia.

Key details

  • The Saribas Bridge has a total length of 2.43 kilometers.
  • The main bridge is a six-span prestressed concrete continuous rigid structure, a design using concrete reinforced with tensioned steel, with a maximum span of 220 meters. CSCEC says this makes it one of the longest bridges of its kind in Southeast Asia.
  • Using skeleton reinforced concrete and pouring concrete during low-temperature periods, CSCEC says the closure deviation, the misalignment where the spans joined, was kept within the millimeter range. It says drilled holes for the ultra-long foundation piles were less than 1 percent off vertical and integrity tests rated all piles as Class I.
  • During construction the project received the silver award of the MOSHPA OSH Excellence Award and CSTR HSE Performance (Gold) in Malaysia, given in recognition of its performance in safety and environmental management.

What’s still pending

  • The project still has to be completed before it opens to traffic.

6ix AI wrote this summary from the release below and checked it against the release.

Recently, the main bridge of the Saribas Bridge project in Malaysia, built by CSCEC, was connected, marking a major construction milestone and paving the way for the project's completion.

The Saribas Bridge is CSCEC's first bridge project in Malaysia, with a total length of 2.43 kilometers. Its main bridge features a six-span prestressed concrete continuous rigid structure with a maximum span of 220 meters, making it one of the longest bridges of its kind in Southeast Asia.

Once completed and opened to traffic, the project will serve as a major transportation artery for the local area, significantly improving regional connectivity and contributing to a more efficient modern transportation network.

The main bridge adopts a variable cross-section prestressed concrete continuous girder design and features ultra-long pile foundations in water, large pile caps, high piers and extra-long spans. The project team innovatively adopted skeleton reinforced concrete combined with concrete pouring during low-temperature periods, keeping the closure deviation within the millimeter range.

The project also achieved a borehole verticality deviation of less than 1 percent for its ultra-long pile foundations, while integrity tests rated all piles as Class I, ensuring the safety and stability of the bridge's foundation structure.

During construction, the project received the silver award of the MOSHPA OSH Excellence Award and CSTR HSE Performance (Gold) in Malaysia in recognition of its outstanding performance in safety and environmental management.

Related news
  • CSCEC completes handover of Baniyas North Phase 3 Project in Abu Dhabi
  • Starry Hill residential project tops out in Belgrade
  • CSCEC projects shine at UIA World Congress of Architects 2026
  • Delegates of CSCEC's first C-star Workshop attend World Youth Development Forum 2026 in Wuhan
  • CSCEC-built new bridge to Dubai Harbour opens
  • CSCEC-built National Stadium of El Salvador passes first interim inspection

China State Construction Engineering Corp. Ltd. on 6ix

Earlier from China State Construction Engineering

Later from China State Construction Engineering

All China State Construction Engineering news releases