November 2026
Who we areEstablished in 1992 as a privately owned company, Central Puerto (CEPU) is today the largest electricity generation company in Argentina, with 6,933 MW of installed capacity diversified across thermal and renewable technologies. We own and operate 16 generation plants strategically located throughout the country.
100% of our shares are publicly listed, both on the Buenos Aires Stock Exchange (BYMA), under the regulatory framework of the Argentine Securities and Exchange Commission (CNV), and on the New York Stock Exchange (NYSE), under U.S. SEC regulations, since February 2018. Our ticker is "CEPU".¹
Our key differentiator is our long-standing track record as Argentina's leading pure-play power generation company, combining unmatched scale, the country's largest generation market share, strong corporate governance as a dual-listed public company, and a robust capital structure. These strengths are reflected in our financial policies and underpin our strong credit profile and overall financial quality.
In 2026, we further strengthened and diversified our platform. We secured an additional 30-year concession for the Piedra del Águila hydroelectric asset, added the Brigadier López combined-cycle plant, and advanced the development of 205 MW of battery energy storage systems (BESS). We also expanded into Oil & Gas, securing a franchise to potentially develop resources in Vaca Muerta following a disciplined de-risking program, with development expected to commence in 2027.
Our strong operating performance, disciplined execution and robust financial position are the foundation of our competitive advantage. Together, they reinforce our long-term leadership in Argentina's energy market while providing a platform for sustainable growth and attractive risk-adjusted returns for our shareholders.
Our value propositionAssess strategic optionality with flexibility, low exposure and potential high return.
Leadership
Sustain market leadership and seize the evolving economic landscape by adding
value-generating projects.
Disciplined growth
Maintain liquidity, strong free cash flow generation, and a net leverage ratio that allows us to grow while upholding resiliency.
Financial strength
Drive balanced return in a sustainable business model.
Investor return
3
(1) Our common shares are listed on the BYMA under the symbol "CEPU". During 2025, the volume traded on the BYMA amounted to 308,113,408 shares. The total number of shares subscribed and integrated on December 31, 2025, was 1,513,770,222, of which 100% were listed and available to trade on the Buenos Ares Stock Exchange. Since February 2018, our ADSs representing our common shares began to trade on the NYSE under the symbol "CEPU". In 2025, the volume of ADRs traded on the NYSE amounted to 85,605,051, equivalent to 856,050,510 common shares. Consequently, the total trading volume of our common shares during 2025 was 1,164,163,459.
Photo: Corporate headquarters.
Central Puerto at a glanceGeneration 2025
18,603
GWh
Generation 3Q26 LTM
18,994
GWh
Revenues 2025
US$ 752 MM
Revenues 3Q26 LTM
US$ 1,412 MM
Includes Spot self-procured fuel.
Adj. EBITDA 2025
Adj. EBITDA 3Q26 LTM
US$ 323.7 US$ 480.3 MM MM
Capex 2025
Capex 3Q26 LTM
US$ 202.0 US$ 458.6 MM MM
Net financial leverage ratio 2025
0.30x
Net financial leverage ratio 3Q26 LTM
0.72x
Other business
Forestal Argentina
+160,000 ha in 8 fields
Interest in
FONINVEMEM
assets +2,500 MW CCs.
3C Lithium Pte. Ltd
We hold 35% stake
3
4
Piedra del Águila: 30-year concession retained
Awarded with a US$ 245 MM bid (fee paid in January 2026) and US$-denominated revenues.
Recent developmentsBESS: 205 MW nearing commercial operation
Construction at 87% (Costanera) and 81% (Nuevo Puerto); 82% of project CAPEX executed. COD before year-end (Costanera) and January 2027 (Puerto), adding US$ 25-27 MM to 2027 Adj. EBITDA.
Oil & Gas: expanding in Vaca Muerta
Aguada del Chivato-Aguada Bocarey blocks acquired in April 2026. Corralera Noroeste block awarded in Neuquén's tender, with a US$ 78.7 MM exploratory investment commitment.
AbraSilver: minority stake sold
Sold for C$ 228.4 MM vs. a C$ 35.7 MM cost basis, a C$ 192.7 MM gain. Extraordinary cash dividend of AR$ 164.00 per share approved (payment date: Sept. 2026).
Pluspetrol: direct natural gas supply
First non-integrated companies in the sector to withdraw Plan Gas volumes from the centralized CAMMESA framework.
5
Power Generation & Operating Performance13.6%
of total SADI generation in 3Q26
Generation volume
+5.6%
y/y
-5.2%
q/q
(in GWh)
409
578
4,453
5,056
4,791
469
3Q26
1,973
1,231
1,118
CEPU installed capacity remained stable in 3Q26
(in MW)
432
1,067
2,000
1,466
2,372
1,185
Spot thermal 51.0%
Contracted thermal
Hydro
Renewables
20.0%
20.8%
8.2%
3Q25 2Q26
Thermal availability
Renewables Hydro
Contracted thermal
Spot thermal
Total thermal* 85.3%
Combined cycles* 93.0%
ST / GT 72.0%
q/q generation volume drivers:
(-)
Central Puerto -32.0%
Central Costanera -14.4%
due to scheduled maintenance
at some plants' assets.
(+)
Piedra del Águila +4.8% Brigadier López +21.5%
San Lorenzo +20.5%
*Excludes Luján de Cuyo maintenance
3
6
Source: CAMMESA
Thermal availability is calculated as a weighted average of the declared availability to CAMMESA in the period. Market share excludes FONI plants volumes. Market share was 15.9% including FONI plants at WI.
Volumes refer to energy generated by all of the company's operating assets are based on CAMMESA's "Síntesis Mensual" publicly available files, which may be revised by CAMMESA in subsequent monthly reports. Accordingly, Central Puerto volumes originally reported for 1Q26 as 5,420 GWh and 2Q26 as 5,250 GWh have been restated to 5,185 GWh and 5,055 GWh, respectively. 3Q26 volumes may likewise be restated in future reports.
Delivering results through the yearsCentral Puerto's historical performance
Revenues (US$ MM)
(Revenue mix by type of sale)
Adjusted EBITDA (US$ MM)
and annual outstanding FONI credit collections
271.0
211.0
301.0
224.0
223.0
267.0
271.0
324.0
392.6
319.7
541.2
636.3
73.0
316.9
69.0
376.3
66.0
276.8
74.0
288.0
54.2
337.2
4433..44
451.0
1,620
5,174
2021 2022 2023 2024 2025 9M26
2021 2022 2023 2024 2025 9M26
Annual capex (US$ MM) Generation volumes (GWh/year)
1,568
2,565
463
4,849
458.6
14,419
1,610
3,283
1,775
17,484
20,773 21,605
4,348 |
2,359 |
9,284 |
3,839 |
18,598
1,926
2,683
7,040
3,468
2,646
1,422
15,280
67.4
176.4
78.6
159.7
202.4
4,979
5,525
2,087
3,185
8,690
2,105
2,900
7,825
3,264
4,973
2021 2022 2023 2024 2025 9M26
2021 2022 2023 2024 2025 9M26
Spot thermal ST/GT Spot thermal CC Thermal PPA
Hydro
Renewables
Adjusted EBITDA = Net income + Income tax expenses + Financial results, net + Depreciation and amortization − Non-recurring operating results.
(1) FONINVEMEM collections are monthly proceeds from an outstanding commercial credit with CAMMESA. 7
Availability rates of thermal units(1)Combined Cycles (%)
91%
88%
92%
68%
79%
92%
58%
86% 86%
96%
93%
79%
90%
100%
94%
84%
91%
99% 99% 96%
90%
44%
Since 2023
Central Puerto complex Central Costanera complex Lujan de Cuyo San Lorenzo
2021 | |
2022 | |
2023 | |
2024 | |
2025 | |
2026 9M |
Steam & Gas turbines (%)
86%
70%
75% 76% 72%
67%
Since 2023
29%
44%
58%
65%
96% 95% 93% 97%
Central Puerto complex
Central Costanera complex
Brigadier Lopez
Availability reported by CAMMESA, based on the total installed capacity of each power
plant. 8
Consistent growth of insta led capacityInstalled capacity growth (in MW)
(1992-2000)
Central Puerto & Puerto Nuevo ⁽¹⁾
(1994) Piedra del Águila ⁽²⁾
(2017)
Luján de Cuyo thermal facility + mini hydro.
3,948
(2018)
Luján de Cuyo CC (+95 MW)
(2019)
Brigadier Lopez (291 MW)
Wind farms: La Castellana I, La Castellana II, La Genoveva II, Achiras (206 MW).
4,250
(2020)
Wind farms: La Genoveva I, Manque, Los Olivos (total 168 MW).
(2021)
San Lorenzo (391 MW)
4,809
(2023)
Central Costanera (1,789 MW)
Guañizuil II solar farm (100 MW)
6,698
374
1,440
967
1,926
1,891
100
(2025)
Closing of B. Lopez CC (140 MW)
San Carlos (15 MW)
Cafayate (80 MW)
6,933
2025
Installed capacity breakdown by
technology mix and revenue model:
6,933 MW
21%
8%
20%
23%
28%
7 wind &
3 solar farms
71% thermal
in 5 plants
Spot ST/GT Thermal Spot CC Thermal
195 |
374 |
1,440 |
545 |
2,769 |
1,610 |
374 |
1,440 |
576 |
798 |
1,621 |
206 |
1,440 |
576 |
798 |
1,230 |
1,440 |
480 |
798 |
1,230 |
PPA Thermal
Spot Hydro
PPA Renewables
Thermal spot ST/GT
Thermal spot CC Thermal PPA Hydro spot
Wind PPA
Solar PPA
9
Our Nuevo Puerto and Puerto Nuevo thermal generation plants are equipped with five steam turbine-generator units in the aggregate and have an installed capacity of 360 MW and 589 MW, respectively. The third plant, the Puerto combined cycle plant has two gas turbines, two heat recovery steam generators and a steam turbine, and it has a total installed capacity of 798 MW. Total installed capacity of 1,747 MW.
In January 2026, Central Puerto was awarded Piedra del Aguila concession extension, until 2056.
# Plant Technology MW Location (province) CEPU op. date Spot, contracts & PPA exp. date
Asset overview · geographic footprint
15 · 16
11
5 · 6
4
12-14
1 · 2
7-10
3
Thermal Hydro Wind
Solar
1 | Central Costanera | Thermal (2 CC + 4 ST) | 1,789 | City of Buenos Aires | Feb. 23 | Spot Res. 400/25 / Contracts |
2 | Central Puerto | Thermal (1 CC + 5 ST) | 1,747 | City of Buenos Aires | 1992 & 2000 | Spot Res. 400/25 / Contracts |
3 | Piedra del Águila | Hydro | 1,440 | Río Negro | 1994 | Spot Comahue terms / Contracts |
4 | Luján de Cuyo | Thermal | 576 | Mendoza | 2019 | PPA 2034 / Spot |
5 | San Lorenzo | Thermal | 391 | Santa Fe | 2021 | PPA 2035 |
6 | Brigadier López | Thermal CC | 421 | Santa Fe | 2019 & 2026 | PPA 2035 / Spot |
7 | Genoveva I | Wind | 88.2 | Buenos Aires | 2020 | PPA RenovAr |
8 | Genoveva II | Wind | 41.8 | Buenos Aires | 2020 | MATER contracts |
9 | La Castellana I | Wind | 100.8 | Buenos Aires | 2019 | PPA RenovAr |
10 | La Castellana II | Wind | 15.2 | Buenos Aires | 2020 | MATER contracts |
11 | Guañizuil II | Solar | 100 | San Juan | Oct. 23 | PPA RenovAr |
12 | Manque | Wind | 57 | Córdoba | 2020 | MATER contracts |
13 | Achiras I | Wind | 48 | Córdoba | 2020 | PPA RenovAr |
14 | Los Olivos | Wind | 22.8 | Córdoba | 2020 | MATER contracts |
15 | San Carlos | Solar | 15 | Salta | 2025 | MATER contracts |
16 | Cafayate | Solar | 80 | Salta | Aug. 25 | PPA RenovAr |
16 plants | 6,933 | MW installed |
10
(1) Nuevo Puerto and Puerto Nuevo thermal plants have five steam turbine-generator units in the aggregate (360 MW and 589 MW, respectively). The third plant, Puerto combined cycle, has two gas turbines, two heat recovery steam generators and a steam turbine (798 MW). Total installed capacity of 1,747 MW. (2) In January 2026, Central Puerto was awarded the Piedra del Águila concession extension, until 2056. (3) Regime by plant per the portfolio table: PPA includes RenovAr and thermal PPAs (some with spot exposure); MATER = renewables under MATER contracts; MAT = thermal spot plants under Res. 400/25 with term-contract optionality; Spot = hydro (Comahue terms).
2026 Capex plan& 205 MW BESS projects progress
3Q26 total CAPEX US$ 36.7 MM
BESS execution milestones achieved
YTD 2026 total CAPEX US$ 458.6 MM(1)
YTD 2026 total CAPEX
9 months (in US$ MM)
245.0
55.3
108.9
49.4
Piedra del Aguila concession Oil & Gas BESS Maintenance & other
(1) Total CAPEX excludes the impact of the Abra Silver divestment
Central Costanera BESS project
55 MW. Lithium (LFP). Contemporary Amperex Technology Co., Limited (CATL)
Offtaker: Edesur
Revenues:
10,161 US$/MW-month per hour (RTE up to 5 hours).
10 US$/MWh variable (energy discharged). Energy fuel cost 20 US$/MWh (approx. 15%).
Central Puerto BESS project
150 MW. Lithium (LFP). Contemporary Amperex Technology Co., Limited (CATL)
Offtaker: Edenor
Revenues:
11,147 US$/MW-month per hour (RTE up to 5 hours).
10 US$/MWh variable (energy discharged). Energy fuel cost 20 US$/MWh (approx. 15%)
Contract details:
Contract term: 15 years.
Estimated capex: US$ 130-140 MM (both projects).
Energy nominated and supplied by CAMMESA (at no additional cost and with no energy price arbitrage).
BESS project update
Construction progress: 81% (Nuevo Puerto) and 87% (Central Costanera).
82% of project CAPEX executed.
Commercial operation expected before year end for BESS Costanera and January 2027 for BESS Puerto.
Expected total contribution to consolidated Adj. EBITDA 2027 US$ 25-27 MM.
11
Strong balance sheet and financial flexibility3Q26 Financing Developments
Financial debt maturity profile and ratios
337.8
Financial debt maturity profile As of September 30, 2026
Category/ Instrument | Action/ Event | Amount (USD) | Execution / Maturity date | Comments |
Class E | New Issuance | US$94.3 MM | July 27, 2026 | 3-yr bullet, 5.5% p.a., semi-annual |
IFC Loan | 2nd Disbursement | US$117.0 MM | August 12, 2026 | Funding for debt prepayments |
Achiras (IFC & IADB) | Full prepayment | US$22.8 MM | August 18, 2026 | Project Finance debt |
La Castellana (IFC & IADB) | Full prepayment | US$43.3 MM | August 18, 2026 | Project Finance debt |
La Genoveva I (IFC) | Full prepayment | US$52.9 MM | August 18, 2026 | Project Finance debt |
Class F | New Issuance | US$50.0 MM | October 6, 2026 | 3-yr bullet (2029), 6.00% p.a., semi-annual |
Galicia Bridge Loan | Extension | US$69.9 MM | October 27, 2026 | Extended to Nov25, 2026. |
(in US$ MM)
220.2 219.0
82.8
14.3
36.9
62.2
46.2
Cash & eq. 4Q2026 2027 2028 2029 2030 2031 >2032
Local Notes
Corporate Loan
Project finance
Financial ratios as of September 30, 2026 (US$ MM) | |
Total outstanding financial debt | 681.5 |
Cash & cash equivalent and financial current assets | 337.8 |
Financial debt net from cash (Net debt) | 343.7 |
3Q 2026 LTM Adj. EBITDA | 480.3 |
Net Leverage ratio | 0.72 x |
FONINVEMEM 3Q26 collections from CAMMESA
In 3Q26 were US$ 11.4 MM & credit outstanding balance of US$ 85.7 MM.
3
12
Power market normalization initiatedResolution 400/25 (Oct 21, 2025) outlined a gradual roadmap liberalizing Argentina's Wholesale Electricity Market (WEM), and progressively reintroduced value creation, contracts and competitive dynamics.
ENERGY FORMULA
Hourly remuneration = CVP + RMA
RMA = CVP + (CMOh × node loss factor - CVP) × FRA × FRC · CVP published by CAMMESA biweekly RMA (US$/MWh): 2 if CVP < 60; 7 if CVP ≥ 60 · FRA = 0 without own fuel management
P50 2026 hourly marginal cost (CMOh) averages ~US$55.5/MWh vs. ~68.7 (2025), 67.1 (2024)
CAPACITY FORMULA
PPAD × KP × capacity remuneration hours + reliability reserve
KP: gas-only 1.1 winter/summer, 0.9 other · dual-fuel 1.5 winter/summer, 1.0 other
Theoretical average (US$/MW-month): gas-only 5,680 · dual-fuel 6,850 · new dual-fuel 14,850 · dual-fuel + Res. 294/94 (ST, GT) 8,100
Resolution 400/25 key aspects
Contract market optionality for spot thermal: Thermal generators gain significant flexibility to add contracts in the new Thermal Term Market (MAT) for up to 20% of their production to Large Users (GUDIs) and the remaining up to 100% to Distribution Companies (Distcos) or the spot market.
Spot remuneration restored: The new spot remuneration mechanism establishes a margin on top of Variable Production Costs (CVP), supporting long-term value creation for generators.
US$-denominated revenues, reducing currency and inflation risk.
Fuel management: The responsibility for fuel management is transferred from CAMMESA to generators. In the transition, existing Plan Gas remains until 2028.
Phased Implementation: The transition will be managed through a phased approach. Importantly, all existing power contracts will remain in force until their natural expiration, ensuring market continuity and stability during the shift.
CEPU Check list
Allowed capacity and energy for B2B nearly fully contracted plus Distcos sales, positioned CEPU as top MAT player.
Added natural gas transportation firm capacity from TGS
Procured LNG and liquids in 1H 2Q26.
ENERGY (SPOT)
Nov 2025
2026
15%
2025-2026
2027
25%
2027
2028
2029
35%
from 2028
2030
New generation (commercial operation from 1/1/2025)
or existing thermal with new firm gas transport · no RMA floor or cap
0.8 0.6 0.5
first two years 2027 from 2028
No cap
from 1/1/2030
80%
of PPAD in non-dispatched HRP
40%
2027
Plan Gas ends (Dec 2028)
0%
only if dispatched
USD 12/MW per remuneration hour (HRP)
90 HRP per week · KP factor by fuel and season
USD 1,000/MW-month
with or without own fuel management
USD 9,000/MW-month for up to 10 years
Thermal, hydro, nuclear or storage (from 1/1/2025) · SE approval and CAMMESA-assigned node
100% with Distcos, up to 20% with GUDIs
New generation: free contracting since 2025
Own management
mandatory from 1/1/2029
Plan Gas (CAMMESA) or own management
CAMMESA as supplier of last resort
USD 16/MW per HRP × KP
KP 1.1 in winter and summer · 0.9 rest of year
FRA
Existing thermal
FRA = 1
Uncapped margin
FRC
With Plan Gas
Fuel
Gas management
MAT energy
Existing thermal
CAPACITY PAYMENT
Capacity
No own fuel mgmt.
PPAD
Own fuel mgmt.
SRC Base
Existing thermal
SRC Additional
New generation
Demand charge
Capacity price
Theoretical capacity prices: internal estimates based on 390 capacity-payment hours in a typical month; self-managed fuel supply. 13
Concession extensionPiedra del Águila hydro plant
Central Puerto was awarded the Piedra del Águila concession for 30 years, with a bid of US$ 245 million.
New energy and capacity prices: 1,733 US$/MW-month affected by maintenance hours and available capacity. Energy: 3.5 US$/MWh (when dispatched), 1.39 US$/MWh (available). The price doubles between 18:00 and 23:00 hours in December, January, February, June, July, and August.
Optionality for sales under contract: Gradual increase in the capacity allowed for sales under contracts: 5% in 2026/2027, increasing by 5% every two years (10% in 2028/2029, etc.).
Revenues denominated in U.S. dollars, reducing FX and inflation risk.
US Inflation indexes adjustment: Annual revisions.
Maintenance plan: Asset preservation plan
14
Concession Fee of US$ 245 MM paid in January 2026
Central Puerto will operate the plant for an additional 30 years, after having operated it for 32 years.
Appendix
Argentina Power Market ESG & Sustainability data Non-core asset details
2025 Argentina power market summary30,257 MW
Historic peak capacity in 2025
142,789 GWh
Total electricity generation, 2025
+16.5%
Renewable generation y/y, aprox. 19% of total demand
38.6%
Renewable share incl. hydro in the energy mix
Generation by source
Total 2025: 142,789 GWh
Thermal
75,225 · 52.7%
Hydro
30,144 · 21.1%
Renewable
26,659 · 18.7%
Nuclear
10,761 · 7.5%
Renewable mix
Wind 70%
Solar 19%
Small hydro 5%
Biomass 4%
Biogas 2%
Thermal fuel consumption
2025 volume and change vs 2024
Natural gas
42.2 Mm³/d
▲ 1.1%
Gas oil
439.3 Mil m³
▼ 53.5%
Fuel oil
91.4 Mil Ton
▼ 60.9%
Coal
266.0 Mil Ton
▲ 5.2%
Total fuel consumption fell 2.6% y/y: liquid fuels were partially replaced by natural gas.
Balance | GWh | vs 2024 |
Local demand | 141,249 | ▲ 0.7% |
Generation | 147,093 | ▲ 0.2% |
Exports | 509 | ▼ 47.6% |
Imports | 4,304 | ▼ 7.5% |
Electricity demand
Local demand breakdown, GWh
Residential
66,388 · 47%
Commercial
38,498 · 27%
Industrial
36,363 · 26%
Source: CAMMESA
16
25.4%
74.6%
Ownership composition (Sept. 2026)
100% of our shares are publicly listed in BYMA (Arg) and NYSE (US).
ESG & Sustainability dataStrong corporate governance
Corporate governance framework
Our corporate governance framework is built on internationally recognized best practices and guided by strict standards of transparency, efficiency, ethics, investor protection, and equal treatment of shareholders.
Our Corporate Governance Code aligns with the principles set forth by the CNV (Comisión Nacional de Valores).
We have implemented a robust Code of Ethics and an Internal Code of Conduct, which define clear expectations for professional conduct, integrity, and employee performance. These frameworks support a culture of accountability across all levels of the organization.
Corporate Management & Board highlights
According to our bylaws, the Board of Directors consists of nine members, appointed for three-year terms, with one-third of its composition renewed periodically.
Our common shares are listed on the BYMA under the symbol "CEPU". During 2025, the volume traded on the BYMA amounted to 308,113,408 shares. The total number of shares subscribed and integrated on September 30, 2026, was 1,513,770,222, of which 100% were listed and available to trade on the Buenos Ares Stock Exchange. Since February 2018, our ADSs representing our common shares began to trade on the NYSE under the symbol "CEPU". As of September 30 2026, the volume of ADRs outstanding in the NYSE amounted to 38,463,856, equivalent to 384,638,560 common shares.
45% (4 members) of our Board of Directors qualifies as independent, based on CNV criteria (may differ from those defined by the NYSE and NASDAQ standard of independence), 1 member (11% of total Board members) is a woman.
No controlling shareholder group, supporting fair and transparent decision-making.
Internal Oversight Committees: Audit Committee and Supervisory Commission.
Experienced management with extensive industry expertise and strongly aligned with Central Puerto's corporate governance principles.
17
Sustainability is present in every stage of our activities and, together with environmental management, constitutes one of the pillars of our business.
Biodiversity protection
Conservation of Pampas Meadowlark
(leistes defilippii)
Site | Quality ISO 9001:2015 | Environmental ISO 14001:2015 | Health & Safety ISO 45001:2018 |
Piedra del Águila (hydro) | |||
Brigadier Lopez (thermal) | |||
Achiras (wind) | |||
Manque (wind) | |||
Los Olivos (wind) | |||
La Genoveva I (wind) | |||
La Genoveva II (wind) | |||
La Castellana I (wind) | |||
La Castellana II (wind) | |||
Luján de Cuyo (thermal) | |||
C. Puerto complex (thermal) | |||
C. Costanera complex (thermal) |
Sustainable grassland management practice
Avoid natural grazing from turning into grain crops or winter grass pasture. | Dispense with the use of herbicide and, above all, insecticide. | Handle the livestock load depending on the season. | Conduct controlled grazing fires, except during the reproduction period. |
Minimizing emissions: Next-to-zero GHG intensity in thermal generation and steam production
Absolute emissiones (Tn CO2e)
Scope 1 & 2 Emissions intensity (Tn CO2e/Thermal MWh)
0.46
0.33
0.47
0.52
7,037,022
0.51
5,160,925
6,450,681 6,395,399
6,056,014
35,171 | 58,243 | 64,562 | 64,392 | 63,616 | |
2021 | 2022 | 2023 | 2024 | 2025 | 18 |
ESG & Sustainability data
ESG in the center of our business
Environment, Quality, Health & Safety Integrated Management System
We have an Integrated Management System (SIG) that identifies sustainable and participatory processes, which allows us to implement, in our daily activities, the principles established by the Board in the Integrated Policy of Environment, Quality, Health & Safety. Our SIG is ISO 9001, 14001 and 45001 certified.
Non-core asset details Non-contro ling interest in 3 thermal plantsWe hold interest in three ENARSA's combined cycle plants.
The plants total 2,554 MW and total annual generation of 10,514 GWh in 2025.
San Martín
Manuel Belgrano
Vuelta de Obligado
Company
Termoeléctrica José de San Martín S.A. (TJSM)
Installed capacity: 865 MW
Termoeléctrica Manuel Belgrano S.A. (TMB)
Company
Installed capacity: 873 MW
Central Vuelta de Obligado
Company
S.A. (CVOSA)
Installed capacity: 816 MW
Technology Location
Commercial
Thermal Combined Cycle located in Timbúes, Santa Fé province
Technology Location:
Commercial
Thermal Combined Cycle located in Campana, Buenos Aires province
2010
Technology: Commercial
Thermal Combined Cycle located in Timbúes, Santa Fé province
2018
operation year: 2010
Ownership transfer: 2020 to ENARSA
operation year:
Ownership transfer: 2020 to ENARSA
operation year:
Ownership transfer year: 2028
Operator: Central Puerto
44%
56%
Ownership structure | % |
Energía Argentina S.A. | 68.83 |
Central Puerto S.A. | 9.63 |
AES Argentina Generación S.A. | 6.37 |
ENEL Generación El Chocón S.A. | 5.60 |
Pampa Energía S.A. | 2.84 |
Central Costanera S.A. | 1.68 |
Orazul Energy Cerros Colorados S.A. | 2.01 |
Hidroeléctrica los Nihuiles S.A. | 1.42 |
Hidroeléctrica Diamante S.A. | 0.76 |
Hidroeléctrica Ameghino S.A. | 0.43 |
Central Dock Sud S.A. | 0.42 |
Generación Mediterránea S.A. | 0.01 |
Ownership structure | % |
Energía Argentina S.A. | 65.00 |
Central Puerto S.A. | 10.83 |
AES Argentina Generación S.A. | 7.17 |
ENEL Generación El Chocón S.A. | 6.23 |
Pampa Energía S.A. | 3.19 |
Central Costanera S.A. | 1.89 |
Orazul Energy Cerros Colorados S.A. | 2.26 |
Hidroeléctrica los Nihuiles S.A. | 1.60 |
Hidroeléctrica Diamante S.A. | 0.85 |
Hidroeléctrica Ameghino S.A. | 0.48 |
Central Dock Sud S.A. | 0.47 |
Generación Mediterránea S.A. | 0.01 |
Outstanding credit for CEPU:
Other
19
FONINVEMEM is a 2004 financing scheme, created by Argentina's Secretariat of Energy and administered by CAMMESA, under which private generators' investments in new power plants are recognized and repaid through future energy-dispatch payments, adjusted by an agreed interest rate (e.g., SOFR + spread).
TJSM and TMB Ownership structure according to companies' websites Sept. 2026. https://www.tmbsa.com.ar/empresa/ and https://www.tsm.com.ar/autoridades/ .
As of Sept 30, 2026, US$ 85.7 MM.
Non-core asset detailsForestry assets across +160,000 hectares.
Lithium project located at the core of Argentina
Our forestry platform is held via Proener S.A.U., wholly controlled by Central Puerto, and spans approximately 160,400 hectares in total, anchored by two key subsidiaries:
Forestal Argentina S.A., with a land base of
~141,000 hectares across Entre Ríos and
Saladas
San Miguel Concepción
Catamarca (Lithium)
The "3 Cruces" lithium project is located in Catamarca, Argentina, within the Lithium Triangle, a region recognized for its world-class lithium deposits, favorable geology and business environment.
Central Puerto participates in the project
Corrientes, including ~67,000 hectares of established eucalyptus and pine plantations, within a total plantable capacity of ~77,500 hectares.
Loma Alta Forestal S.A., adding a further
~19,400 hectares in Corrientes, with ~10,400 hectares already under pine.
Together, these assets position the Group among the leading forestry landholders in the region, with a diversified plantation base and substantial untapped growth potential.
Annual production capacity covers 1.8 million m3 for over 50 customers through 4 forest-industrial regional hubs. The business delivered US$ 13.1 MM in revenue in 2025 and US$ 9.4 in the first six months of 2026. Ongoing expansion includes planting over 3,000 hectares annually, entirely financed by own operating cash flow.
San Roque Virasoro
La Cruz
Paso de los Libres
Concordia
through Minera Cordillera S.A., the leading partner of the venture, and currently holds a 35% interest. The investment is consolidated in the Company's FFSS under the "share of profit of an associate" line.
The project remains in the exploratory phase, providing exposure to the long-term development potential of one of the world's most prospective lithium regions.
Additional resources: Website: Forestal Argentina and section "Foray into the Forestry Business" of our 2025 20-F report.
(1)Through the acquisition of share capital and voting rights of 3C Lithium Pte. Ltd. ("3C"), (a company incorporated under the laws of Singapore), which holds 100% of the share capital of MCSA..
20
Terms and abbreviationsAbbreviation / Term
1Q26 / 2Q26 / 3Q26 / 4Q26
1H26 /6M26 FY25 / FY26 LTM
q/q y/y
Adj. EBITDA
Art. 9 BCRA BESS BYMA CAMMESA CAPEX CENCH CMO
COD CVP
FONINVEMEM
Gas Acuerdo GNL / LNG
Gross Income GT
IAS 29 IFRS MAT MATER
MEM / WEM MM
MW
MWh GWh NYSE ON
Piedra del Águila concession PPA
R400 RMA
Resolution No. 400/2025 SADI
SEC SE
Self-procured fuel SG&A
Spot Market ST
US$ WI
Definition
First, second, third and fourth quarters of 2026, respectively Six-month period ended June 30, 2026
Fiscal year ended December 31, 2025 and 2026, respectively Last Twelve Months
Quarter-over-quarter comparison Year-over-year comparison
Adj. Earnings Before Interest, Taxes, Depreciation and Amortization (Non-IFRS measure). New Adjusted EBITDA formula: Gross Income - Administrative & Selling Expenses + Depreciation & Amortization - Non-recurring operating results
Article 9 of the Piedra del Águila Concession Terms, establishing the remuneration mechanism applicable to the hydroelectric complex. Central Bank of Argentina (Banco Central de la República Argentina)
Battery Energy Storage System
Bolsas y Mercados Argentinos S.A., Argentina´s stock exchange
Wholesale Electricity Market Administrator (Compañía Administradora del Mercado Mayorista Eléctrico S.A.) Capital Expenditures
Non-Conventional Hydrocarbon Concession granted by the Province of Neuquén for the exploration and exploitation of unconventional hydrocarbon resources Marginal Operating Cost (Costo marginal Operativo)
Commercial Operating Date
Variable Production Cost (Costo Variable de Producción)
Fund for Investments Required to Increase Electricity Supply in the Wholesale Electricity Market (Fondo para inversiones necesarias que permitan incrementar la oferta de eléctrica en el MEM) Natural gas supply program under which CAMMESA procures and allocates natural gas to eligible thermal generating units under regulated conditions
Liquefied Natural Gas Gross profit
Gas Turbine
International Accounting Standard 29 - Financial Reporting in Hyperinflationary Economies International Financial Reporting Standards
Term Electricity Market (Mercado a Término)
Renewable Energy Term Market established under SE Resolution No. 281-E/2017 Argentine Wholesale Electricity Market (Mercado Eléctrico Mayorista)
Million Megawatt Megawatt-hour Gigawatt-hour
New York Stock Exchange
Corporate Bonds (Obligaciones Negociables)
Concession agreement governing the operation and remuneration framework of the Piedra del Águila hydroelectric complex since 2026, following the expiration of the original concession. Power Purchase Agreement
Secretariat of Energy Resolution No. 400/2025 Spot Market Remuneration Adjustment Factor
Resolution issued by Argentina´s SE establishing the remuneration framework for conventional generation, including seasonal capacity remuneration and energy pricing mechanism applicable in the MEM Argentine Interconnection System (Sistema Argentino de Interconexión)
U.S. Securities and Exchange Commission Argentina´s Secretariat of Energy
Fuel purchased directly by the Company for spot generation and subsequently reimbursed by CAMMESA under the applicable regulatory framework Selling, General and Administrative Expenses
Electricity sold into the Argentine Wholesale Electricity Market and remunerated under the applicable regulatory framework Steam turbine
U.S. Dollar Working Interest
21
ContactContact us or to subscribe to our Distribution List:
Investor Presentation
November 2026
Central Puerto
Web
https://www.centralpuerto.com
Phone
+ 54 11 4317 5000
Headquarters
Av. Tomas Alva Edison 2701, Dock E, City of Buenos Aires Port.