Quarterly Production Report – Q1 2026 (Operating Tables in... (Report)

· Issued by Antofagasta plc

Summary by 6ix AI

Antofagasta plc's copper production was 143.0 kt (thousand tonnes) for the first quarter of 2026, down 19.2% from the fourth quarter of 2025 and down 7.6% from the first quarter of 2025, according to its production report dated 15 April 2026.

Key details

  • Copper sales were 137.0 kt for the first quarter of 2026, down 31.8% from the fourth quarter of 2025 and down 19.5% year to date. Gold production was 46.5 koz (thousand ounces) and molybdenum production was 3.0 kt.
  • Group cash costs before by-product credits (the cost per pound of copper before subtracting revenue from other metals produced) were $2.77/lb, and net cash costs (after that revenue) were $1.08/lb for the first quarter of 2026.
  • Copper production by mine for the first quarter of 2026: Los Pelambres 66.3 kt, Centinela 48.7 kt, Antucoya 19.6 kt and Zaldívar 8.3 kt.
  • The realised copper price was $5.83/lb and the realised gold price was $5,264/oz for the first quarter of 2026, against market prices of $5.83/lb and $4,875/oz.
  • Total tonnage moved by the transport division was 1,320 kt for the first quarter of 2026, down 21.4% from the fourth quarter of 2025.

6ix AI wrote this summary from the release below and checked it against the release.

Q1 2026 PR
ANTOFAGASTA PLC - Q1 2026 PRODUCTION REPORT
Operating Tables in Excel Format
15 April 2026
ANTO Operating Data
Antofagasta Operating Data
GROUP PRODUCTION AND CASH COSTSQuarterYTD% Change
20212022202320242025202620252026Q1 26 vs Q4 25YTD 26 vs YTD 25
Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1YTDYTD
Copper productionkt183.0178.4181.1178.9138.8129.8181.9195.7145.9149.6173.6191.5129.4155.3179.0200.3154.7160.1161.8177.0143.0154.7143.0(19.2)(7.6)
Copper saleskt182.8163.4182.3197.2115.9147.1178.0201.5149.0146.4158.4213.4115.7161.5176.5191.8170.2153.8141.3201.0137.0170.2137.0(31.8)(19.5)
Gold productionkoz59.161.466.864.938.435.446.956.142.244.057.465.533.333.651.868.242.948.353.966.346.542.946.5(29.9)8.4
Molybdenum productionkt3.02.82.62.12.02.02.63.12.52.43.22.92.72.52.72.83.14.43.94.43.03.13.0(31.8)(3.2)
Cash costs before by-product credits$/lb1.681.771.791.922.342.402.122.002.492.472.272.072.672.632.332.012.372.272.422.442.772.372.7713.516.9
Net cash costs$/lb1.161.131.161.351.751.901.661.271.541.961.471.501.931.941.621.231.541.121.071.051.081.541.082.9(29.9)
LOS PELAMBRESQuarterYTD% Change
20212022202320242025202620252026Q1 26 vs Q4 25YTD 26 vs YTD 25
Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1YTDYTD
Daily ore throughputkt164.5163.3158.0136.698.8110.1160.7176.7115.5143.4164.1185.5177.1196.2183.0186.0173.5171.2164.1181.1165.5173.5165.5(8.6)(4.6)
Copper grade%0.670.650.640.670.680.640.610.640.660.640.610.610.560.520.550.570.530.540.560.530.520.530.52(1.9)(1.9)
Copper recovery%89.190.290.391.892.389.388.488.389.289.289.289.788.289.088.489.588.389.890.991.190.488.390.4(0.8)2.4
Copper productionkt84.984.481.174.354.144.387.888.859.369.281.190.755.377.292.095.269.973.373.079.266.369.966.3(16.3)(5.2)
Copper saleskt80.784.969.189.941.954.480.494.656.872.369.1100.850.782.788.393.673.072.657.295.165.273.065.2(31.4)(10.7)
Molybdenum grade%0.0210.0210.0180.0180.0160.0180.0160.0170.0190.0180.0170.0160.0160.0150.0150.0160.0190.0260.0250.0260.0190.0190.019(26.9)-
Molybdenum recovery%85.383.983.985.186.583.984.887.187.385.584.685.084.984.980.981.475.883.781.984.481.475.881.4(3.6)7.4
Molybdenum productionkt2.62.42.41.81.41.42.12.41.81.72.42.32.22.02.12.02.33.53.03.72.32.32.3(37.8)-
Molybdenum saleskt2.62.32.12.21.21.51.82.21.81.92.12.32.52.11.82.22.03.63.13.12.72.02.7(12.9)35.0
Gold gradeg/t0.0480.0480.0370.0430.0440.0420.0400.0420.0460.0380.0410.0300.0340.0290.0320.0370.0350.0440.0430.0420.0380.0350.038(9.5)8.6
Gold recovery%68.164.983.074.573.572.467.269.070.067.063.776.469.669.670.170.671.270.170.972.570.371.270.3(3.0)(1.3)
Gold productionkoz14.313.813.411.88.66.813.913.89.99.711.911.88.410.413.014.711.614.313.815.012.111.612.1(19.3)4.3
Gold saleskoz12.912.911.114.26.48.812.814.39.810.89.312.46.810.312.514.211.313.89.817.610.511.310.5(40.3)(7.1)
Cash costs before by-product credits$/lb1.461.561.601.741.982.061.751.732.171.941.881.792.192.142.071.992.302.192.202.172.612.302.6120.313.5
Net cash costs$/lb0.840.810.811.121.271.371.190.780.841.450.951.271.141.261.361.241.360.710.590.660.721.360.729.1(47.1)
CENTINELAQuarterYTD% Change
20212022202320242025202620252026Q1 26 vs Q4 25YTD 26 vs YTD 25
Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1YTDYTD
CONCENTRATES
Daily ore throughputkt106.4102.9100.3110.8104.0110.6105.1115.9103.2105.1109.5111.790.1101.0105.9117.2100.6106.0107.7113.897.5100.697.5(14.3)(3.1)
Copper grade%0.600.590.620.590.440.450.520.540.510.480.530.550.350.320.420.530.510.580.560.580.500.510.50(13.8)(2.0)
Copper recovery%84.285.284.984.981.478.879.781.783.382.582.884.181.575.479.183.281.483.484.983.483.181.483.1(0.4)2.1
Copper productionkt45.345.147.647.432.933.337.645.538.236.042.845.72320.631.646.635.944.545.148.835.735.935.7(26.8)(0.6)
Copper saleskt45.135.756.350.622.542.039.045.141.030.543.152.315.325.029.544.841.939.344.453.031.441.931.4(40.8)(25.1)
Molybdenum grade%0.0100.0090.0080.0100.0130.0130.0120.0140.0160.0130.0110.0110.0110.0100.0110.0140.0170.0190.0160.0130.0160.0170.01623.1(5.9)
Molybdenum recovery%39.553.843.846.259.761.758.149.371.068.667.758.46768.764.262.767.264.257.052.381.867.281.856.421.7
Molybdenum productionkt0.40.30.20.40.60.60.50.70.80.70.80.60.50.50.60.70.80.90.90.70.70.80.7-(12.5)
Molybdenum saleskt0.40.30.20.20.40.70.70.60.80.70.90.60.50.50.60.70.71.01.10.70.70.70.7--
Gold gradeg/t0.220.230.260.250.150.150.170.190.170.180.220.260.140.140.190.230.170.170.190.230.190.170.19(17.4)11.8
Gold recovery%71.972.869.170.466.764.064.065.565.166.867.266.864.461.967.569.466.868.067.567.264.766.864.7(3.7)(3.1)
Gold productionkoz44.947.653.453.129.828.633.042.332.334.445.553.624.923.138.853.531.334.040.051.234.531.334.5(32.6)10.2
Gold saleskoz42.635.461.454.222.236.134.139.933.524.945.459.016.427.434.954.537.231.235.954.729.637.229.6(45.9)(20.4)
CATHODES
Daily ore throughputkt56.955.760.757.855.457.355.052.549.453.565.664.354.760.264.061.457.852.354.850.159.857.859.819.43.5
Copper grade%0.590.620.610.640.650.620.730.760.560.500.510.560.60.670.630.650.500.450.430.440.460.500.464.5(8.0)
Copper recovery%66.463.764.967.467.864.564.068.569.263.264.071.071.672.870.271.270.671.867.262.461.970.661.9(0.8)(12.3)
Copper production - heap leachkt20.419.322.223.322.121.323.827.018.214.720.222.521.327.125.626.019.115.415.313.612.519.112.5(8.1)(34.6)
Copper production - totalkt21.520.223.224.022.922.224.928.219.515.521.123.22227.426.126.519.816.116.014.313.019.813.0(9.1)(34.3)
Copper saleskt21.816.825.024.822.620.026.728.221.515.620.923.121.225.927.723.124.716.014.616.512.624.712.6(23.6)(49.0)
Total copper productionkt66.865.270.771.455.855.662.573.757.751.563.868.94548.057.773.155.660.661.163.148.755.648.7(22.8)(12.4)
Cash costs before by-product credits$/lb1.781.821.862.002.702.662.472.042.663.012.542.193.233.382.481.802.312.112.292.352.732.312.7316.218.2
Net cash costs$/lb1.121.041.141.231.932.031.921.241.602.191.551.302.392.571.400.641.180.840.660.360.341.180.34(5.6)(71.2)
ANTUCOYAQuarterYTD% Change
20212022202320242025202620252026Q1 26 vs Q4 25YTD 26 vs YTD 25
Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1YTDYTD
Daily ore throughputkt80.687.382.991.182.292.189.893.484.894.781.593.590.599.985.295.392.593.291.9100.994.492.594.4(6.4)2.1
Copper grade%0.350.340.330.350.310.320.360.350.330.330.340.340.330.320.320.310.310.310.300.350.310.310.31(11.4)-
Copper recovery%69.167.967.971.369.468.669.468.766.868.067.868.966.269.470.271.871.970.870.269.868.071.968.0(2.6)(5.4)
Copper productionkt20.219.218.320.917.418.921.021.818.819.118.321.619.620.719.320.820.219.318.623.019.620.219.6(14.8)(3.0)
Copper saleskt22.917.220.319.917.419.721.122.619.118.315.725.319.219.221.319.520.818.617.423.819.520.819.5(18.1)(6.3)
Cash costs$/lb1.962.122.062.022.402.592.402.582.802.642.652.442.612.552.742.232.472.703.053.043.032.473.03(0.3)22.7
ZALDÍVARQuarterYTD% Change
20212022202320242025202620252026Q1 26 vs Q4 25YTD 26 vs YTD 25
Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1YTDYTD
Daily ore throughputkt42.238.648.048.639.539.044.338.633.631.736.538.135.240.742.451.540.732.039.346.929.140.729.1(38.0)(28.5)
Copper grade%0.880.660.650.770.840.780.770.760.700.800.820.820.780.630.640.640.590.670.620.810.740.590.74(8.6)25.4
Copper recovery%48.850.352.953.556.454.249.659.660.662.057.752.156.156.958.757.454.453.655.453.558.154.458.18.66.8
Copper production - heap leachkt9.06.27.79.18.27.67.88.37.06.87.27.57.06.26.77.96.04.36.58.96.16.06.1(31.5)1.7
Copper production - totalkt11.19.611.012.411.511.010.611.310.09.810.410.39.59.410.011.29.07.09.011.78.39.08.3(29.1)(7.8)
Copper saleskt12.48.711.612.011.611.110.810.910.69.79.711.99.38.69.710.89.87.47.612.68.39.88.3(34.1)(15.3)
Cash costs$/lb2.302.652.342.312.102.182.552.752.893.032.982.912.972.973.053.093.093.383.743.533.613.093.612.316.8
TRANSPORTQuarterYTD% Change
20212022202320242025202620252026Q1 26 vs Q4 25YTD 26 vs YTD 25
Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1YTDYTD
Railkt1,2161,2971,3701,3381,3101,3981,3101,3501,3091,3651,3741,3331,3461,4211,3961,4501,2131,2051,2611,3331,0691,2131,069(19.8)(11.9)
Roadkt309369381422410451418461442436453398376362396360344376329346251344251(27.5)(27.0)
Total tonnage transportedkt1,5261,6661,7511,7601,7201,8491,7281,8111,7511,8001,8281,7311,7221,7831,7921,8101,5571,5821,5901,6791,3201,5571,320(21.4)(15.2)
COMMODITY PRICES AND EXCHANGE RATESQuarterYTD% Change
20212022202320242025202620252026Q1 26 vs Q4 25YTD 26 vs YTD 25
Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1YTDYTD
Copper
Market price$/lb3.854.404.254.404.534.323.513.634.053.853.793.703.834.424.184.174.244.324.445.035.834.245.8315.937.5
Realised price$/lb4.264.593.994.655.053.423.283.974.483.493.773.843.974.694.303.754.694.404.605.785.834.695.830.924.3
Gold
Market price$/oz1,8001,8151,7901,7951,8771,8731,7301,7281,8901,9761,9291,9742,0702,3382,4742,6642,8593,2813,4544,1454,8752,8594,87517.670.5
Realised price$/oz1,7081,8551,7811,8122,0211,8211,6331,8132,0291,9411,8982,0602,1762,3992,6002,6693,0983,4423,7054,3635,2643,0985,26420.769.9
Molybdenum
Market price$/lb11.314.219.018.919.118.416.121.432.820.923.7518.619.921.821.821.720.520.724.422.925.720.525.712.225.4
Realised price$/lb13.319.220.218.119.916.416.028.937.012.725.313.121.124.919.721.519.322.128.018.331.019.331.069.460.6
Exchange rates
Chilean pesoper $724716773826808843927913810801853896947934931963963947960935886963886(5.2)(8.0)