CIMIC Group's CPB Contractors has been selected by Main Roads WA to deliver the Kwinana Freeway Upgrade between Roe Highway and Safety Bay Road, working with partners McConnell Dowell, Jacobs and Arup.

Key details

  • CIMIC says the contract will generate revenue of approximately $250 million to CPB Contractors.
  • The work covers design and construction, including a new 2.5km southbound lane and bridge widening between Roe Highway and Berrigan Drive (four lanes to five) and a new 3.3km northbound lane from Russell Road to Beeliar Drive (three lanes to four).
  • It also includes a new 11km lane in each direction between Russell Road and Mortimer Road (two lanes to three), plus improvements to noisewalls, safety barriers, surfacing and drainage.
  • The work includes new coordinated ramp signals on the northbound side between Safety Bay Road and Roe Highway, with civil and Intelligent Transport System (technology for managing traffic) works for eleven new coordinated ramp signals there.
  • CIMIC says the project will reduce congestion, improve travel time reliability and support more efficient freight and commuter movements across the Perth metropolitan area.

6ix AI wrote this summary from the release below and checked it against the release.

CIMIC Group's CPB Contractors has been selected by Main Roads WA to deliver the Kwinana Freeway Upgrade, between Roe Highway and Safety Bay Road, alongside partners McConnell Dowell, Jacobs and Arup.

The Kwinana Freeway Upgrade will deliver a significant increase in capacity, safety and network efficiency across one of Western Australia's most critical transport corridors, ensuring it can meet the future demands of a rapidly growing population and economy. The project will reduce congestion, improve travel time reliability and support more efficient freight and commuter movements across the Perth metropolitan area.

The contract will generate revenue of approximately $250 million to CPB Contractors.

ACS Group and HOCHTIEF Chief Executive Officer and CIMIC Group Executive Chairman Juan Santamaría said:

"We're building on our strong relationship with the WA Government, and working alongside Main Roads WA and the Office of Major Transport Infrastructure Delivery, to safely and reliably deliver the Kwinana Freeway Upgrade. By strengthening connectivity between communities, employment centres, industrial precincts and key freight routes, the upgrade will support growth, unlock economic opportunities and deliver a safer, more resilient transport network."

Design and construction of the Kwinana Freeway Upgrade includes:

.

Construction of a new 2.5km southbound lane and bridge widening between Roe Highway and Berrigan Drive (increasing from four lanes to five)

.

Construction of a new 3.3km northbound lane from Russell Road to Beeliar Drive (increasing from three lanes to four)

.

Construction of a new 11km lane in each direction between Russell Road and Mortimer Road (increasing from two lanes to three)

.

New coordinated ramp signals on the northbound side of the freeway between Safety Bay Road and Roe Highway

.

Improvements to noisewalls, safety barriers, surfacing and drainage

.

Civil and Intelligent Transport System works to facilitate eleven new coordinated ramp signals on the northbound carriageway of the Freeway between Safety Bay Road and Roe Highway.

ACS, Actividades de Construccion y Servicios SA on 6ix

Earlier from ACS, Actividades de Construccion y Servicios

Later from ACS, Actividades de Construccion y Servicios

All ACS, Actividades de Construccion y Servicios news releases