Power Grid Corporation of India (NSE:POWERGRID) Q2 2027 earnings call, held 2026-11-03. Watch the replay and read the transcript on 6ix.

On 6ix: 6ix.com/event/power-grid-corporation-of-india-limited-powergrid-q2-2027-earnings-call
Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.
0:00 Wish all of you a very happy Diwali and a prosperous New Year in advance. I would now take your permission, sir, to start the proceedings. On behalf of POWERGRID Corporation of India Limited, we welcome you to the select analyst meet organized to discuss company's performance and the way forward post the declaration of financial results for the second quarter as well as the H1 that ended on 09/30/2026, and to interact with the analysts out here. To formally commence today's proceedings, I now invite Srimati Aljana Luthraji.
0:49 She's the company's secretary and compliance officer. She'll introduce the dignitaries on the dais and initiate the proceedings. Over to you. Yeah. Thank you, Bakun. Good afternoon, everyone. Today, we have our senior management team of Paragat with us to discuss the company's performance and business outlook post the declaration of Q2 FY twenty twenty results. I would to for us today. Are company. With Thank Shri Akhilesh Patak, Director of Projects, Shri Pankaj Pandey, OSG Operations.
1:57 So we will commence today's proceedings with the corporate video of the company. Can we have the video, please? There are places where the road ends, where mountains rise beyond the clouds, where deserts reach beyond the horizon, and where every step forward demands extraordinary determination. A journey that has helped connect a nation, strengthen its progress, and bring electricity to every corner of India. POWERGRID has become a vital force in India's growth story. For thirty seven years, this spirit has powered a remarkable journey.
2:44 From the remotest substations to the most complex transmission projects. Today, POWERGRID's network spans nearly 1.87 lakh circuit kilometers of transmission lines, two ninety three substations and over 6.49 lakh MVA of transformation capacity During twenty twenty five to '26 we achieved our highest ever annual capital expenditure accelerating the development of critical transmission infrastructure Our operations and maintenance teams keep the grid running with minimal tripping and 99.8% system availability Drone based patrolling, digital interventions and centralized asset management strengthen preventive maintenance and remote monitoring.
3:35 And as we strengthen today's grid, we are engineering tomorrow's solutions. PG Nirmaan, our advanced project management and monitoring application. PG AMRID, our AI based defect identification system automates the monitoring of transmission infrastructure. India's first all terrain substation inspection robot developed and patented in collaboration with IIT Kanpur marks another leap in indigenous innovation Through our payment processing and facilitation center, PPPFC, we are streamlining vendor bill processing and advancing a more efficient, transparent and paperless payment system. Through advanced technologies like statcoms and synchronous condensers, POWERGRID is strengthening grid stability and building a stronger and resilient grid.
4:28 The successful deployment of India's first 400 kilovolt insulated cross arm technology on the Maharani bag to Narela line offers the potential to reduce right of way requirements by 35%. Digital substations and emergency restoration technologies further enhance grid resilience. Our vision extends beyond transmission. With over 100,000 kilometers of optical fiber network, POWERGRID is strengthening India's digital connectivity. POWERGRID Teleservices is developing a 1,000 rack 14 MW Tier three data center in Manisar targeted for commercial operations in 2026. Meanwhile, our first large scale solar PV plant at Nagda, Madhya Pradesh advances our sustainability journey.
5:22 Our expertise also reaches beyond national borders. With engineering consultancy services in over 25 countries and a transmission public private partnership in Kenya in collaboration with Africa fifty, POWERGRID continues to take Indian engineering excellence to the world. Yet our responsibility goes beyond infrastructure. In twenty twenty five to twenty six, we incurred INR391.16 crore rupees on CSR initiatives spanning healthcare, education, livelihoods and sustainable development. Medical equipment, ambulances and vishram sadhans are helping strengthen healthcare access and community welfare.
6:11 We are equally committed to protecting the environment. At Bina Guri and across our establishments, rainwater harvesting and recharge pits strengthen water conservation and promote sustainable resource management. Together, we have turned challenges into milestones. Together, we are shaping the future. Thank you. Now I invite Sri Vamsi Ramamo Hanbura, CMD Power Grid to share his opening remarks and also presentation on the ground.
7:01 Over to you sir. Good afternoon, everyone. And I'm extremely pleased to be before you, along with my entire board, with the newly minted director of finance, mister Amoljit, and director of projects, mister Patakji, and director of operations designate, mister Pandey, along with our director of personnel,.
7:48 Right? I'd like to introduce once again a high quality infrastructure company entering into its next phase of growth. That is what Power Grid is. Riding on our experience in maintaining one of the largest transmission utilities in the world and aptly recognized in the highest quadrant in terms of maintenance of the transmission systems. This is what the company what we want to introduce Power Grid has and with a substantial and strong investment owing to the energy transition and renewable energy integration and more importantly, the intense growth of electricity. I should say more appropriately, electricity intensive growth what is happening now both in the industry, agriculture, transport, digitalization, and all these efforts. It's by and large, it is electricity intensive growth which is going to propel the growth of the generation and the offshooter's transmission because transmission is a common denominator for the movement of electricity from point to point. The mobility as I always say, the mobility to electricity is given by the transmission line of the system only. That is the industry where we are working in. Known for its financial discipline and highly competent and dedicated workforce, execution capability including 765kV order, one of the highest transmission voltage levels and also HVDC projects remotely or in one of the most toughest conditions.
9:11 In one single shot, what we should say is the projects are being commissioned and opportunities for sustained earnings and expansion and roadmap for long term growth and shareholder value. I wanted to place this before you, so I take this opportunity to run a small presentation on this. The disclaimer over here. We'll be trying to cover the highlights and overview, execution and operations, competition, what is there in the sector, order pipeline and outlook, financial performance, sustainability and recognitions. In this pattern, we would like to go forward. As you are aware, we are about 3.29 lakh crore of fixed assets going much beyond the 3 lakh crore which was there sometime back. 1.87 lakh circuit kilometres, almost 6.5 lakh MVX transformation capacity and availability continues to be in the order of 99% plus.
10:05 The shareholding pattern continues to remain the same in terms of the shareholding at 2.42 lakh crore is the market cap. The credit profile on the domestic front, highest safety and on the international front, at par with the sovereign rating. The SPV rationalization also has been undertaken as part of governance given the nature of the TBCB projects where every time given a project, a new TBCB adds up to us a new SPV, so we try to consolidate them and one of the fastest approval in the CPSC domain is what we have got recently. So 28 SPVs have been merged into two SPVs so that it is better way of governance of the projects. Major elements which have been commissioned in Q2 FY27, nine eighty one sq kilometers of transmission lines and 14,600 mVA transformation capacity.
10:56 Importantly, the transmission lines are Kopal and Raichur in Karnataka, Bidar to Maheshwaram, a link between the Karnataka state and closer to the Hyderabad Maheshwaram and Sikhar K3, an important line in the Rajasthan belt. Substations are new substations, Kopal and Beedar, and on the 400 kV, Bikaner to Bikaner in Rajasthan. If you look into the H1, FI 20 six-twenty seven, 2,600 circuit kilometres of transmission lines, 25,000 MVA capacity what has been coming over there. And the complete two EBCB SPV projects which have been commissioned over here are the Ramgad two transmission system and the Bidder transmission system. So like in a TBCB project, multiple elements are there. We are saying that the entire what has been interested to the TBCB has been completed, not one or two elements under the project. All the elements which are concerned with that, these two projects have also been commissioned. Apart from that, after September 26, major elements commissioned are the to Narendra line, one of the toughest and challenging lines, and the Kopal to Gadak linking two of the pooling stations for the RE power and the Gadak Substation which is 400 kV.
12:05 And project execution CapEx and capitalization, the guidance as what we have said last year was INR37000 crores and we are moving up and then we should be able to catch up with about to INR40000 crores. So INR37000 to INR40000 crores is the CapEx what we are looking at and the capitalization guidance would be about 25,000 crore to 30,000 crore. And the availability, as I said, would be continuing to be in the highest order in terms of 99.81% and tripping per line less than 0.2, that is 0.17 where we are standing. This is the line of Srinagar to Dras. This is a line which is connecting to the Leh. Leh is presently connected with the Power Grid transmission line, a radial line which is there, one of the toughest locations where these lines have been built. So recently on October 29, there was a challenge in this line having trip. So during... At this at about 11,800 feet and minus 10 degrees centigrade, this is what POWERGRID employees have been working to make sure this line was restored so as to bring power to the coldest part of India.
13:07 It was done in record time over here. And we have also upgraded our posture in terms of our visibility of our assets in terms of national transmission asset management center. We have upgraded it, which is... Which requires as per the timeline, which is to be done every time we need to upgrade the system. So this has been upgraded completely. These are the real pictures of it and we also improved upon the posture of cyber security by operationalizing this I three SOC, this security operation centers of Power Grid. On the capability and technology, Power Grid has been closely associated with one of the OEM and has designed and finally got this product out, a two twenty kV mobile GSV, last time it has been set, but this time it has been also put to use. It has only been developed but also has been deployed in one of our substations.
14:02 And on the capability front, as we understand, HVDC is one of the critical technologies which is required for evacuation of power and long distances. Power Grid under the aegis of Ministry of Power along with METI, that is Information and Technology Ministry, come together and we are going ahead in trying to indigenously design and develop a silicon carbide MOSFET. For this, a lot of work has already been done. A good amount of traction we see on this development front. So about 13,000 SIC power modules are expected to be developed, which will be deployed in a given substation of Power Grid. So this also has been the decks have been cleared for this and we are eagerly looking for the participation which is quite a good number where people are keen to develop this within the country. This will actually improve upon the indigenization of the technology within the country. These are VSC based power modules what we are working upon.
14:55 And as well as the operations front, we also deployed the insulated aerial work platform which will be giving that much ease and also minimize the outage requirements. We have also indigenously in the country developed a 100 kg payload capacity for a drone, which is essential for us to take over the material or such other things including steel and cement to remote areas where we need to erect the tar, so this has already been successfully done. We are deploying this as well. The TBCB outcome for the half yearly 27, nine projects under ISTS is what Power Grid has been successful and two projects under the intrastate. The interstate stands about 7,600 crore is the annual tariff and the intrastate is about 4,500 crore annual tariff, taking the total to about INR 8,107 crore as annual tariff in the first half of this financial year.
15:56 And it's interesting to note that we have also got the HVDC project of Barmir and also deployment of the first synchronous condensers, about eight synchronous condensers. The first series of asynchronous condensers will be deployed by Power Grid. Looking into the order pipeline, the TBCB stands about 1.95, RTM about 0.25 lakh crore and with the total standing as 2.20 is the total works in hand for power grid. The Pang evacuation scheme, as what people were keen to know, this was initially envisaged under the HVDC route, but given the challenges in terms of the altitude, ultraviolet rays, and also the cosmic rays, the complexity of deploying such technologies at high altitudes was reviewed and an AC solution has been identified.
16:42 It has been actively discussed in the recently concluded NCT meeting, which would be standing at about 31,000 crore. The other business which Power Grid undertakes in terms of the data center, storage and smart meters about 0.04 lakh crore. The ones which are going to come in future under the TBCB bidding pipeline, interstate and intrastate put together is about 63,000 crore which is already under bidding, with most of it under the ISTS and a small part under the intrastate. And to be floated, this number is only of the intrastate. 4,147 is of the intrastate. A good number of intrastate projects are also underway. So the bidding pipeline is about INR67000 crore.
17:28 Added to this with the Green Energy Corridor three, which is about INR1.36 lakh crore for the intrastate, this is an interested project and INR500000 crore for the BES. Most of it would be coming under the TBCB route, meaning that there is a good amount of opportunity for the participants to work in this direction. This will be facilitating about 135 gigawatt of RE across The States. This was also an opportunity for the transmission companies. Robust collections revenue, as we are very pleased to inform you that the billing and the realization is always one of the finest what we have been And the number of outstanding dues is also more than forty five days has come down significantly and the receivable dues as you see from the graph stands about ten point five four days.
18:17 So both in terms of our execution capability, the order book, the pipeline and the collection part, all these parameters were thought I should place it before you all. The financial performance, in the consolidated front for quarter, the profit after tax is 8%, which has already been shared with you and the PBT is at about 6%. Wanted to give you a feel as to what has happened in this entire part. On the operating income, $8.87 on the operating income is the plus, that is more than 7%. 7.7% is the growth on the operating front for transmission and because of the regulatory part, this is what last time also we have taken pains in trying to explain you that it is that regulatory assets which we have the trajectory of the regulatory tariff is that minus INR354 crores is on account of the regulatory tariff which moves there. And minus INR193 crores are just one off kind of things which we will be getting because of the difference in the order from the regulator.
19:25 The time taken by the order to give the by the regulator to give the orders and the differential tariff is that INR193 crores and such other aspects. So effectively the growth stands about 3%, while the operating income as you see stands at about 7.7%. As far as PAT growth, again even here we see a 9% growth in the PAT, but because of the regulatory asset, the trajectory of the tariff for the regulatory assets, that is the one which has an impact on the income, but on the PAT you see it has a 1.7% and the other issues are minus 82% and put together it is 8% over here. So translating that about 8% of the top line growth and roughly the 8% under the even on the PAT. On the stand alone, we see that it's about 7% for the PAT on the stand alone front.
20:17 The gross fixed assets as on date about INR2.8 crore stand alone and consolidated R3.29 crore. The debt equity is R59.41 crore, which is having enough room for us to actually work upon the massive projects pipeline which we are NSH ing, one to 1.5. The other key financial information, interest from subsidiaries increased from seven ninety four to twelve oh one, incentive 159 to 98, dividend from JVs from 24 to 60, dividend from subsidiaries 300 to three forty five. So these are the figures, other key financial parameters. We also tied up with the GBIC green loan for about JAPANIS yuan about 80,000,000,000, term loan from SBI about 10,000 crore, UBI 5,000 crore and bonds about 2,000 crore, and something more is also an offering.
21:13 On the telecom and consultancy, we have about INR 300 crores, $2.83 crores under telecom and on the consultancy also close to INR 400 crores. This kind is of revenue what we are getting from both these locations because we are riding strong on the telecom footprint, what we have across the country and also our expertise in providing the consultancy to within the country and beyond the borders. This is the data center, this is the shape what it is standing now as we speak. We are shortly going to also bring this data center into operation, maybe in terms of weeks we should be bringing this into operation. It's a 100% Indian owned infrastructure by a government company, seven layer security system, about thousand racks and 14 megawatt. It's a commercial data center to be utilized under a tier three certified data center and expected commissioning as I was saying in a couple of... In few weeks, we are going to get this through. It is a metium paneled cloud service provider and a sovereign cloud. This will be the characteristics of this data center.
22:12 Sustained commitment to ESG on the... One of the targets which we have set for ourselves, that is 50% from RE, this already we achieved last year itself and zero waste to landfill, more than 90% has been achieved. Net water positive, we are more than 50% and net zero target, we are very well onto the track there. And the CRISIL ESG score has moved us from 58 up to 66, we have moved up the ladder and the same thing with NSE sustainability, we are standing at 70. As far as accolades, we are selected as the finalist in three categories in S and P Global Energy Awards, one of the finest awards in this industry on Excellence in Energy Infrastructure Project of the Year Targeted Programme Impact Award and Terry UNDP fifth Water Sustainability Award also has been taken up by Power Grid.
23:05 Thank you everyone. Thank you. That was a fantastic overview, sir. We now move on to the next segment, which is questions and answers. Gentle reminder for all of you to raise your hand, introduce yourself and the house that you... So the first one is over here. We will try our best to ensure that we, you know, answer all your questions. In the interest of your own time, we will not be taking repetitive or the duplicate questions. Over to you, sir. Hi. Good afternoon, sir. I am Mohit Kumar from ICIC Securities.
23:51 My question is, I think that I saw on the slide, I think I've cut the guidance for capitalization from INR 300 to 30,000 crore to INR 150 crore to 30,000 crore range, right? My question is, are you seeing more challenges on the ground and is it related to supply chain issues or with the land with the land acquisition or right of issues? See, as you understand, the ministry has come up with the guidelines for providing compensation to the landowners. This was the way how we had to go forward. It was asked also by everyone.
24:37 So a set of guidelines have been issued notified by the Ministry of Power, wherein it's market based compensation is what they are looking at it. So a few of the states have adopted and will have to work through the process, a couple of states which have adopted, will have to work through the process, process, which they're almost done. And with that coming in, the right of way will be that much eased. With the compensation being paid to the landowners as per the market rate, we see that is going to ease the situation and that is going to improve upon the fronts which will be available for building up the transmission lines. While the targets, what we are seeing is INR 25,000 to 30,000 crores, there is no challenge as far as the most of the equipment, absolutely supply is part of it. We don't see it. We have the transformers and all, which we have some time that was a challenge.
25:22 No longer be able to be the active approach what we have undertaken in trying to bring a bulk procurement what we started. So that has helped to bring certainty to the industry of transformer manufacturers and and we are getting supplies out there in position. It is basically the fronts which have to be made clear by the by the state local administration. Should there be a push back a little, that is the reason we are seeing. But otherwise, most of the projects what we are planning will be on time. Should we... Should things go forward right, then we should be able to catch up with one of the finest figures. My second question is given the fact that you are sitting now on INR 2.2 lakh crore and the PAG is also coming up. So your total order book will be roughly around INR 2.5 lakh crore. How do you expect the CapEx and commissioning will move in FY 2028 and FY 2029?
26:13 Just how the CapEx and capitalization and capital expenditure will move in FY 2028 and FY 2029 based on the current order book? Yes. You see these projects as you see, we have also secured a couple of projects recently in this pipeline. So with the initial expenditures on the projects and all, they are good and the CapEx will be continuing to be in the range much beyond 40. Is it possible to put a put a numbers on the CapEx and commissioning for FY '28, FY '29? No. But then definitely, they will be very encouraging. Let me see that. Yes. Not very specific numbers over here. But you see with the massive HUDC project with us with a lot of synchronous condensers also over there and a couple of intrastate projects which are there with us, the numbers are going to be much better only. My last question is, is it CapEx one also another issue also what I would like to draw your attention here with the market rate being played for the compensation land compensation, that is also a component which is going to improve the drive the CapEx up. That is the reason we need to identify what will be the quantum of that element, which is unknown, which as we move forward, the clarity will become that much.
27:25 So the CapEx is going to increase. Understood. Last question, is it possible to share the cross block of TBC projects at end of Q2 FY twenty twenty seven and the run rate EBITDA for that asset? Is it possible? Yes. So basically, if you have seen, we Understood, sir. Thank you. Thank you and all the best. So Sumit Kishore from Axis Capital.
28:36 So you mentioned that the annual tariff one in H1 FY twenty twenty seven is somewhere around INR 8,100 odd crores. What is the associated project cost for these set of projects? So each of the project is quite different. Cumulative project cost. I think we'll allow that. You can estimate that. This is the costing part of what is going to do. This is entirely based on the public domain. See, the idea is to idea is to gauge whether the flurry of project wins that you have had... We have given you the quantum of order book in pipeline, we're giving you, right, about 2,200,000 crore. And in that case, primarily it is TBCB. So that could give an indicative cost as to what kind of a project which are already in the pipeline, also accommodating for these projects for which tariff has been set. So as a whole, this is what it is.
29:28 Whether we have one in this quarter or previous quarter, put together we have about 2.2 lakh crore of projects which are being built by us. So the idea is to gauge whether the IRR profile of the newer TPCB projects and the larger ones that you have won is similar or better than what you had won earlier. It would be in the best interest of everyone, there's numbers out there. I can assure you that. Okay. Okay. So one more question is on HVDC project pipeline here on. You have won a large HVDC project. What are the next few projects which are likely to come under tendering? And what is likely to get awarded, say, by FY 2028, 2029?
30:15 Do you have any such sort of visibility that you can share with us? Okay. As you understand, CTIL is a the have So So to seven to gigawatts, I'm understanding. They're both in Brahmaputra Basin and also to evacuate power from the Khawdas and to the Rajasthan areas to the mainland. So these are the HTC projects which have been planned and from Brahmaputra Basin. So exact timeline and all, once they get mature enough, which can be placed in the public domain, I'm sure that will be coming up. Presently, is not so, but then there are a couple of projects which are being actively being considered. So they should be placed under the bidding rule or maybe being discussed actively into the NCT, which would be obviously known. That will be the time when we are sure what project is going to So can two projects get awarded in FY '28?
31:14 '28 maybe, yes. With the quantum of generation coming up massively in these locations both in a big trend from now to twenty one and a half year, which could happen. It could happen. Thank you, sir. Hello. Yes, thank you for the opportunity. Good afternoon, sirs. Namit Arora from In Growth Capital. Thank you for a very insightful presentation. Sir, my question is on the new initiatives, data centers and BESS. So I understand in a few weeks you will be commissioning this particular data center, it has all the sovereign specs. Could you give us some more background on what are the future plans for further activity on the data center side, some indication on timelines and the capacities you are considering?
32:13 Okay. So you see we are while we are a transmission company, we see a good opportunity in the communication front. So that's the reason Power Grid is having a decent position and niche position in the telecom sector. Power Grid provides bandwidth to one of the major players, OTT players and also for the government entities, Power Grid provides the telecom infrastructure, the bandwidth. So having said that, being in the power domain as well as the communication domain, we moved into the data center domain because as we see data center is measured in terms of the power, MW and also we find that we understand this business, we have a good strength of IT team also with Power Grid and there's a lot of domestic requirement, in house requirement is also substantial. Keeping that and also the sector's requirement, we found that there's a good amount of space which is which is left untapped, which is owned by a government company to be provided to government companies or others for both of them. So we we found an opportunity over here and we crystal this as our first data center as a pilot data center so that we can actually work work upon ourselves directly. So this particular data center primarily was done by the Power Grid engineers predominantly over there. So this data center in our own premises in Manasir, this has been done. Since the land was part of the substation, so a little initial challenge, I'm talking about four to five years ago in getting the clearance from the regulators and all that's done.
33:36 So the pilot data center is standing. It's fully ready now. So we're just looking for an opportune time to introduce that into the market. So as far as the other projects, we are also ready with another data center in the southern part of the country to have a different location. So we already secured the land over there and we are also actively pursuing the potential in other locations, but we wanted to first get this pilot data center, the complete group of that data center. So as far as the future plans are there, we are very excited about it. The first data of Power Grid won by government. So... Because we also have the telecom connectivity, the understanding of the power sector, a good strength of the IT engineers in Power Grid and in house requirement itself, so we see a great potential in this data center. Thank you, sir. All the best for the imminent commissioning of this data center.
34:23 Thank Thank you. And sir, my second question was on BSS. You mentioned about it in one of the slides. Do you foresee that going forward also that would be an integral part and you will see a lot of these integrated initiatives? So one is in isolation where the states given the kind of VGF that the government has given, few of the states have embarked upon it, quite a lot of challenges in that trying to actually be reality, the battery part, a good potential in the country. Having said that, the regulator in a couple few months ago has come up with the regulations, modified the existing terms and conditions of tariff regulations, wherein they came up with the option of an integrated storage system. This can be also these systems, that is the storage systems can also be developed by the transmission service provider under the section 62 rule that is under the RTM mode. So we have also we are also pursuing actively and we've got the clearances from the Northern Region and the Western Region. We filed our petitions before the regulator. Should there be a requirement for them to have a storage need, which is there very much over there, we see a good traction on this front, wherein we will be able to develop the develop the storage facilities under the section 62 route, under the RTM route, which will be available for the grid stability, this will be very helpful over here. We are ready with that. We are ready with that solution and this can open a new window for Power Grid to enter into the storage systems.
35:45 Because under the 62, we can actually create an ecosystem for subsequently being scaled up to the competitive nature. So we feel that it's a good opportunity for us to work along with all the stakeholders so that we can improve upon the storage requirements of the country. Thank you very much for the detailed responses and all the best to the entire team. Thank you so much. Thank you, sir. Over here. We'll get it from your right side. Yes, sir. Sir, this is Atul Tiwari from JPMorgan Research. Sir, just two questions. Sir, first is on the right of way issue. So the right of way issues we thought had been broadly resolved because I think in the previous couple of analyst meets, it was communicated that the system has gone through the necessary adjustments the new rules are in place.
36:33 But it does look like that the issue is still dragging on. So could you please elaborate on this that when do we expect the final resolution so that we don't have these kind of negative surprises on the capitalization front? So that is the first question. And the second question is that in your work in hand, 2.2 lakh, how much will be the transformation capacity that you will need and by what time you will be able to award it on your transformer vendors? The second question part of it, yes, we are working working on the bulk procurement model. So anticipating the requirement existing in hand, put together, and then we are working upon this. So we are very well comfortably placed in terms of our orders, and we are going very, very comfortable in terms of not only inviting the tenders, placing orders and also obtaining the units also on time. We are not finding much of challenge as far as the transformers go there.
37:30 Coming to the right of way, as you all must be aware, prior to 2017 and all, their compensation was paid only limited to the damages which were occurring for the crop or any other particular maybe a building or something only damages would have occurred. That was the only compensation what was under the one sixty four, section one sixty four of the act. Thereafter, the compensation towards the land which was getting damaged, the demolition value of land, that one between the towers and across the corridor. Now imagine between the towers as you see in the picture, in between the four legs of the tower and from tower to tower there's a corridor again. So there is a significant amount of land apart from the crop. Crop was paid, but the land compensation there's a challenge because you need to identify the exact land owner over here. And land being a state subject, while we have earlier said that the guidelines have been notified by the government of India. Guidelines are notified by government of India, but will have to be adopted by the respective state which is going to notify those guidelines, such notifications will then be applied. So few of the states have been taken up have been taken up this new model wherein we are... There is an effort which is being made to identify the market rate.
38:42 That particular unknown factor of what is the market rate in a given area, so they are working upon that. So there is a mark... Independent market values are being a pointer. Their averages, different solutions are being sought out, that is as per the guidelines and the states are adopting it. So this particular process will have to culminate so that we are able to identify the appropriate rate so that it can be made payable to that landowner. Identification of landowner also an issue here, and the crop compensation where there could be a farmer who must be tilling that soil, but here identification of the landowner, the real owners in terms of brother, son, and all, we have to undertake all that exercise, that we have almost digitized. POWERGRID has also... Parallelly, we have digitized all that activity also so as to have a clear track as to what's being paid across. So POWERGRID has been working on this. The state governments...
39:31 Whenever a new state government adopts, it takes a little time for them to realign their state machinery to understand these new guidelines, notify them appropriately and also adopt them. The moment that is done, we expect there could be better traction. But having said that, there cannot be one magic one which is going to say that there is not going to be any more ROW in the If there is any country in the world where transmission lines are being built at this big base, I should say that is India where it's being built. Such massive transmission lines. Power Grid almost built about five and a half thousand circuit kilometers of transmission lines last last year. I think nowhere in the world we'll see. And even in India, I should say we have almost 6,500, six and 0.5 thousand... 6,500 circuit kilometers, you know, last year. About 7,000 circuit kilometers in the ISTS which have been commissioned, Power Grid has been about five and a half thousand circuit kilometers. Now I'm not talking about any market share here.
40:27 I'm talking about what we actually delivered on-site. We have completed our couple, our our colonel, our. All of these projects have been completely done. Our bidder, all these projects are done. Despite these challenges, we are inching and not only moving fast also. Wherever it is there, you know, for example, after in certain locations, things are becoming that much more easier also. Some places, it is getting very easy, but then people have to adopt it and we have a good number of holidays. Right? We need to account for the Diwali's, the chats and all. That also sometimes not transmission projects. Every infrastructure project has a push during this holiday season. We will also have to account for all of that. Sir, could these issues impact your FY 2028 capitalization as well? Or do you believe that all this will be sorted out within FY 2027?
41:12 It will. I mean, to believe that there is not a single project of Power Grid which has been put on hold. Everything is going ahead. We have never stopped or started new project or delayed project. Every project is going on. Should we have... And another interesting thing, what I'd like to say is that the transmission project is not that every year we have a... It automatically throws off projects coming in. It has a gestation period. It is not linked to the financial year. Exactly by March 31, few projects will come up. Absolutely no. The the timeline for the projects are as much as what is given in the TSA. And sometimes the delays which are also well recognized by the regulator, all of that put together, should there be a delay in a couple of weeks or so in a project that is going to get in the next quarter, it is going to be done so. No project has been left. No project. You may identify if any project, you necessary project project one hour, let me know. If there is one company which has done every project in the last part, it is Power Grid. Check up anything. There are projects, for example, even in Kopal area, which is one of the toughest thing. POWERGRID is the one who completed the project.
42:15 POWERGRID project, POWERGRID POWERGRID project, POWERGRID POWERGRID, all these projects have been completed by POWERGRID people, other parties were working over there. They also feel the challenges. It's not that there is a magic wand with POWERGRID or with anybody else. I would say, yes, our teams are very well inspired. They understand they are on the ground to get the project done. We do not have any projects which are not come. So we are concerned that's the next year should we miss the bus, there is next bus immediately is which we are going to board that. No issue. Because our projects are not definitely quarterly wise a project should come. That's not the way how the industry is. Okay, sir. Thank you. Thank you. Gentlemen over here. Yep. Go ahead. Yep, please. No. We can't hear you.
43:00 Hello. Yeah. Yeah. This is Mahesh Patil from ICICI Securities. So my question is on the bidding that we are seeing this year. Right? So there are a lot of construction road EPC players that are bidding almost... They're having almost one fourth of the bids done by project cost. So how do you see that? Especially in interest rate, is there increase in competitive intensity? And do we see any impact on our return profiles because of that? Our return profile will not be dictated by other companies or their participating. As what I have showed to the team, our returns will be will be very well encouraging. That's what I'm saying. As far as the other players are coming, competition competition is is welcome. Welcome. We have been standing as a PSU. I should say one PSU, which has been an extremely regulated company. If there is one company from that extremely regulated front, we have moved into the completely competitive domain, I should say this part. A government company from that extremely regulated front to a competitive world, we have not only moved into the competitive world, we have started winning projects also.
44:00 Not only we won the projects, we have completed them also. Not only have we completed the projects, we have successfully commissioned and also earned good returns on these projects. The entire cycle, if there is one company, we are there. Should there be new parties who are participating in that, they are welcome. The more they understand what transmission is, the better they will be faring in their next projects for sure. Okay. And so my second question is on the timelines. Right? So I think we sometime back mentioned that the transmission project timelines you have requested and the government has approved, you know, increasing the timelines from eighteen to twenty four months to twenty four to thirty months. So how do we see the CapEx phasing? Are we pushing some CapEx going forward? And is that applicable for the is that applicable in retrospective for the existing projects or only for the new projects that we're bidding? The simple answer is for the old projects, no.
44:52 It's pretty Okay. After all. For the new projects, yes. And as far as the timelines are there, it was initially the... Few of the private players were thinking that they can do projects faster. They were saying no. And they brought it down to eighteen months. And if there is one company which has done the projects in about eighteen months, it is Power Grid again. We only done a seven sixty five k v system in eighteen months. No other player except Power Grid, which has completed within eighteen months. But having said that, it is not possible with the kind of what clearances what we need to obtain from multiple agencies to build a project within eighteen months. Technically, yes, we can do it. Power Grid has the capability. Even a substation after getting a land, we have done within nine months. Nine months is seven sixty five kbps substation is impossible. It looks like this is not true. To that extent, Power Grid has the capabilities. We are able to stitch these things together.
45:37 More importantly, I'm very glad to note that every substation what we have commissioned, be it, and all, one single shot, they come on the bar. It is not that we have been struggling, sir. We have an issue here. We are not talking about small systems. It is not that us us twelve five hundred MVA substation. We are talking about each substation having a capability do do So So lastly, the status of the Khawaran Akhur project, if you can share, let's say, the first two years firstly, are we on track for the four year time line? And in the first two years, what is the CapEx that we are envisaging here? CapEx figures, I'm not able to exactly stay tuned that one. The progress is fantastic.
46:27 Should somebody would like to visit Kowda, they can see it for themselves. They can see all the units also going there. And all these projects are visible on our screen. Every day, we monitor these projects over there, even from any part of the... I mean, in our cabins, we see into this and one of the largest HVDC in our center. The AP center of Kowda will be our KPS 2, Power Grid's own KPS 2, where there will be HVDC apart from the existing AC substation. Yes. Should you be visiting there, you can see it for your eyes, one of the finest projects which is coming over there. Works are going on schedule, if I have to say. Yes. Transmission line, there's good amount of time, but then the best of it will be possible. Okay, sir. Thank you. Thank you. All the units and all are being supplied. Already the transformers are being supplied. The firewalls are being built, everything is going as possible. Please. Yes. Sir, Amit Binder from Axis Capital.
47:17 I just wanted to understand like earlier the government target was INR 9,160,000,000,000 of CapEx from FY twenty twenty two, thirty twenty two. So bidding was being done according to that. Now we have this new one three one hundred thirty five gigawatt REC corridor coming in. So how much is the pipeline left? And is there an overlap between the two plants? Any projects that are going out in this process? Sorry. So earlier, government had put out a plan of INR 9,160,000,000,000 from FY 2020 to 3022. So the bidding was happening according to that. Now this new plan has come in for 135 yard connectivity. So is there a overlap between the two plant? And is there some let off that we should take, one? And of the earlier plant, how much has been done and how much is remaining for bidding to come up in the next two to three years? See, what is bidding? I've already said on the inter... Interstate part of it. Interest rate is about 63,000 crore, interstate and interstate. Intrastate now it depends upon how much the state is looking at it.
48:18 Most of the states are also catching up with the interstate. And coming up with this GC three, GC three what you're talking about? Yes. This in all probability is an offshoot of that particular plan wherein the government is pushing and providing fund for these projects, which will invariably have to be discharged under the TBCB route. So this is covered from that. Right. So it's a part of the time point once it gets us given some interested subjects. Right. So for me to comment upon it and give emphatic answer would be wrong, but then, yes, we have to naturally draw the correlation that the big picture is drawn by c and this final funding arrangements is done under the GEC, green energy corridors. Right. And on the second part of the question that I was asking, of the 9.16, much is done and how much is left, if you have any idea? Don't Specific number I need to give to you should you... Alright. Got it. Okay. But the potential is so much high.
49:13 That's the more we... As we speak also, every state is declaring more and more of coming in. So we need to actually integrate them. And to integrate them, we need more better solutions. Not only we have transmission lines, we need the support systems. We need synchronous condensers, statcoms, batteries, storage systems, all of that also would be required because to integrate the RE, we need these new systems. Right. And just one question is that earlier your target I think was crores is what you were looking on the intrastate transmission, I believe, one or two years ago. Now with you participating in the bids more, are you seeing more capital allocation or more targets the targets being expanded on the intrastate kind of the business part of the business? No. For us, intrastate, yes, it picking up in terms of the number of tenders, but then interstate is also quite a good number of tenders in the interstate as well. So we are looking into the merit of the project and see where we can have a better sync with the project.
50:11 Those are the projects we will be working. Right. Got it. Thank Thank you. Those are my questions. Last few questions, so then we can wrap up. Yes. Yes. Sir, this is Mohit Pandey from Citi Research. Sir, my question is around what are we doing to protect ourselves our returns against commodity inflation? I understand for a lot of our projects, we enter into pre bid types with equipment suppliers. So if there are any further say, for example, copper goes up another 20% over next one year, then what exactly are we doing to protect our returns? Yeah. See, while some of the points, it is fixed, some of the supplies are fixed in nature, but some are also having the price variation provision, meaning that if there is variation in the market, we are also having to accommodate that particular variation.
51:02 But having said that, we have factored in such kind of variations in multiple projects. It's not one single project what we are talking about. Multiple projects, we have the kind of the appropriate cushions what we have provided in each of the projects. So we are sure that all of that will be adequate enough for us to push the projects through. Because we cannot obviously look into this increase in copper or aluminum in a given year. But then at the same time, we are accommodating these costs in different projects and different heads. Yeah. Sir, any broad sense you can provide? What proportion would be fixed and what on the... Yeah, with these variation clauses? And also if, for example, copper falls 20% next year, do we get to retain the benefits or how does it work? We do get to retain the benefits. Price variation, yes.
51:50 Okay. The price variation, there is a definitive price variation formula which is based upon certain indices which are predetermined. So the moment of the index, the quantum of that particular material in that equipment, the weightage which is given to it, that is the one which will dictate the price, the one which is already finalized or agreed upon. So it may move up or down, but we have to accommodate or properly take care of that positive moments, we take care of it, and the negative moments will be a win for the Power Okay. Thank you, sir. Okay. I think we should now move to the next... The one last? Okay. Hi, This is Darshan Parmar from Jefferies. I just had one question regarding the bidding pipeline.
52:37 If you could just give a sense on how the bidding pipeline would trend going ahead because it was INR 1.2 lakh crore in 1Q and now it's INR 63,000 crore. So going ahead, how do you see the bidding pipeline? Okay. INR 1.2 lakh crore something's already taken under bidding, right? When HUDC moves, it takes a big chunk out of that. The new chunk will have to add, like somebody is asking when the new HUDC come, the moment the HODC gets materialized, again it just pushes that forward. So the market is continuing to reinvent itself and it's going to come up, it's going to be there. And apart from that the interest rate is another one which has moved up, 1.36 lakh crore of interest rate which is coming, apart from the 63,000 and lot of interest rate as we speak, a lot of states are also coming up with the projects. So the and most of them under the bidding rules. So the pipeline, there is no dirt in the quantum of projects. As I'm saying you, the more the RE is going to be injected into the country, there will have to be again a transmission system to evacuate and transmission system is a common denominator for every single megawatt which is going to be put into the grid, you need a transmission system.
53:39 So it is a common denominator, whether it is an intrastate or an interstate, any generation coming up, there is a need for transmission to be there because there is no other way how electricity can be moved from point A to point B. So this is the industry where we are talking about. Well, on that note, I now invite mister Sanjay Sharma, executive director corporate planning, to give the vote of thanks. We will have two quick segments after that. One is a photograph of the gentleman sitting here on the dais, and the other one is when I'll call up all the team members of POWERGRID to be on the stage. Sanjay sir. Thank you, mister Bakal. Respected Chairman and Managing Director, members of the Board of Directors, other members of the Power Grid family that is our investors, analysts and friends.
54:33 On behalf of Power Grid, I thank all of you for joining us today for the quarter two FY twenty six-twenty seven Analyst Meet. And I must say, at the peak of the results season, thanks for taking our time for this. To our investors and analysts, your questions are always valuable to us, and your continued phase in Power Grid motivates us for doing better. The numbers we have shared together speaks for themselves, and we are continuously working towards out with coming better numbers. I thank the team from AdFactors, our team from Western Region 2 for helping us organize this event in a successful manner. Thank you everyone. On behalf of Power Grid family, I would like to extend your deep, powerful greetings to everyone and thank you all for being here with Power Grid. Thank you.
Follow Power Grid Corporation of India Limited into a list and get an email when it puts out news.
company's secretary and compliance officer at POWERGRID Corporation of India Limited
Director of Projects
OSG Operations