The European Commission has approved proposed changes to the financing rules for ThyssenKrupp's €3 billion sustainable steel plant in Duisburg and confirmed they comply with EU state aid law (rules limiting government funding for companies). ThyssenKrupp is finishing negotiations to revise the plant's financial arrangements.

Key details

  • The project budget is largely supported by the German federal government and the state government, which are covering two thirds of the total investment.
  • The original subsidies were tied to the immediate integration of hydrogen, a requirement ThyssenKrupp says is no longer feasible. It held talks with German and European authorities to revise the terms so it would not lose the funds.
  • Chief Financial Officer Axel Hamann said the adjustments are needed to respond to changing economic conditions.

What’s still pending

  • ThyssenKrupp's negotiations on the revised financial arrangements are not yet finished.
  • The German government still has to apply the updated rules and adjust its existing financing commitments.

6ix AI wrote this summary from the release below and checked it against the release.

Copyright © BusinessAMBE 2023

Key takeaways

  • ThyssenKrupp is once again negotiating the financing of its €3 billion sustainable steel plant.
  • Approval by the European Commission guarantees essential state aid under revised conditions.
  • Adjusted agreements safeguard the feasibility of the project by scrapping impractical hydrogen requirements.

ThyssenKrupp is currently putting the finishing touches to negotiations to revise the financial arrangements for its €3 billion sustainable steel plant in Duisburg.

Changing economic conditions

According to the company’s Chief Financial Officer, these adjustments are necessary to respond to changing economic conditions.

Adjustment of financing conditions

The project budget is largely supported by the German federal government and the state government, which are covering two thirds of the total investment. Although the original subsidies were tied to the immediate integration of hydrogen, such a requirement is no longer feasible.

To avoid losing these funds, the organisation held extensive discussions with both German and European authorities to revise the conditions of the agreement.

Approval by the EU

CFO Axel Hamann expressed his satisfaction that the European Commission has officially approved the proposed changes to the financing rules and confirmed that they comply with EU state aid legislation.

Thanks to this approval, the German government can swiftly apply the updated rules and adjust the existing financing commitments, thereby safeguarding the financial viability of the project.

Want to receive more energy news? Sign up for our weekly Energy Insider newsletter

Follow Business AM on Google News as well

Want access to all articles? Take advantage of our temporary promotion and subscribe here!

© The Content Exchange, source News

thyssenkrupp AG on 6ix

In the deck

Earlier from thyssenkrupp

Later from thyssenkrupp

All thyssenkrupp news releases