EDP S A completes unique hybrid project in the Iberian Peninsula at Pracana

· Issued by EDP S.A.

Summary by 6ix AI

EDP has completed Pracana, a hybrid project in Portugal that combines hydropower and ground-mounted solar generation at one site, adding solar to a hydropower plant that began operating in 1951; the complex is now fully operational. Pracana is EDP's sixth hybrid project in Portugal.

Key details

  • Pracana has a total installed capacity of 89 MW (megawatts) and estimated annual generation of 140 GWh (gigawatt-hours).
  • The ground-mounted solar part is 48 MW, 87 GWh a year and around 90,000 modules; the hydropower part is 41 MW and 53 GWh a year.
  • EDP says Pracana's output is equivalent to the consumption of around 51,800 households and avoids around 35,000 tonnes of CO₂ (carbon dioxide) emissions a year.
  • Construction of the solar plant began in January 2025, the substation was energised in December 2025, the first solar electricity was generated on December 19, 2025, and components were brought into operation progressively throughout 2026.
  • EDP currently has 11 hybrid projects in the Iberian Peninsula with more than 1 GW (gigawatt) of combined installed capacity across Portugal and Spain.

6ix AI wrote this summary from the release below and checked it against the release.

The completion of Pracana reinforces EDP's commitment to hybridisation as one of the most innovative solutions for accelerating the integration of renewable energy and increasing the flexibility of the electricity system. In the Iberian Peninsula, the company currently has 11 hybrid projects with more than 1 GW of combined installed capacity across Portugal and Spain, bringing together different combinations of hydropower, wind, ground-mounted solar, floating solar and energy storage.

In Portugal, Pracana is EDP's sixth hybrid project. It joins Alto Rabagão and Alqueva, which combine hydropower and floating solar, as well as Mina de Orgueirel, Monte de Vez and Charneca das Lebres, which combine wind and ground-mounted solar generation. In Spain, EDP has a further five hybrid projects. Beyond the Iberian Peninsula, EDP's hybridisation strategy also extends to other markets, with projects in Poland, the United States, Chile and Singapore combining different renewable technologies and energy storage solutions.

A historic asset ready for a new chapter

Pracana's energy story began in 1951, when the hydropower plant entered operation. Seventy-five years later, the site is entering a new phase with the integration of ground-mounted solar generation. Construction of the new solar plant began in January 2025, the substation was energised in December that year, and the first solar kWh was generated on 19 December 2025. The different components were progressively brought into operation throughout 2026, and the complex is now fully operational.

Pracana's evolution illustrates a new phase in the use of renewable assets: not only building new capacity, but also transforming and optimising existing infrastructure, combining different technologies to generate more renewable energy and use the grid more efficiently.

Pracana in numbers

  • Total installed capacity: 89 MW
  • Estimated annual generation: 140 GWh
  • Ground-mounted solar: 48 MW | 87 GWh/year | around 90,000 modules
  • Hydropower: 41 MW | 53 GWh/year
  • Equivalent consumption: around 51,800 households
  • Avoided emissions: around 35,000 tonnes of CO₂/year