Cushman & Wakefield Releases 2026 Data Center Development Cost Guide, Citing 21% Rise in Per-MW Construction Costs

· Issued by Cushman & Wakefield Ltd. via Business Wire

Summary by 6ix AI

Cushman & Wakefield, a commercial real estate services firm, published its 2026 Data Center Development Cost Guide covering the United States and Canada. It says construction costs rose an average of 21% per megawatt (MW) since the last edition in the fourth quarter of 2024, citing supply chain constraints, skilled labor wages, land fundamentals and component costs.

Key details

  • The guide puts the global data center development pipeline at approximately $2.3 trillion in investment capital, of which $492 billion is under construction and the remaining $1.8 trillion is tied to planned and precommitted projects.
  • All-in greenfield (new-build) development costs in the United States and Canada average $17.6M per megawatt for the most modern facilities, excluding chips and GPUs (graphics processing units). Power infrastructure is the largest cost category at an average of 21% of total costs, with contingencies second.
  • Powered land in primary U.S. markets averaged $584,000 per MW in 2026 year-to-date, 35% above its five-year average and 51% higher year-over-year, according to the guide.
  • The guide says skilled labor shortages in mechanical, electrical and plumbing trades drove a 5% average annual wage increase from 2021 to 2024, with steeper growth in secondary and tertiary markets.
  • The guide says Texas markets rank among the lowest-cost development environments, citing their regulatory climate, lower construction labor costs and mature contractor ecosystems.

What’s still pending

  • Capital expenditure in frontier markets (the guide's category beyond primary, secondary and tertiary markets) is projected, not certain, to grow 6.9-fold from current levels to $631 billion.

6ix AI wrote this summary from the release below and checked it against the release.

Cushman & Wakefield (NYSE: CWK), a leading global commercial real estate services firm, has published its 2026 Data Center Development Cost Guide, revealing that data center construction costs have risen an average of 21% per megawatt (MW) since the previous edition was published in the fourth quarter of 2024.

Covering markets across the United States and Canada, the guide provides a comprehensive overview of data center development economics spanning land acquisition, labor markets, construction costs, and capital expenditure trends across primary, secondary, tertiary, and frontier markets. It attributes rising development costs to worsening supply chain constraints, rising skilled labor wages, evolving land fundamentals, and escalating costs for critical components.

"The data center industry is entering a new phase where access to power, land, and skilled labor are increasingly determining where growth can occur,” said John McWilliams, Head of Data Center Insights at Cushman & Wakefield. “Our 2026 Data Center Development Cost Guide shows that while development costs have risen significantly, demand for AI and cloud infrastructure continues to reshape investment patterns across North America. The result is an unprecedented pipeline of development that is extending beyond traditional hubs and into emerging markets with the scale and resources needed to support the next generation of digital infrastructure."

The global data center development pipeline now represents approximately $2.3 trillion in investment capital, of which $492 billion is currently under construction and the remaining $1.8 trillion is tied to planned and precommitted projects. For context, this figure exceeds the estimated total market value of all New York City real estate by approximately $640 billion.

All-in greenfield development costs in the United States and Canada average $17.6M per megawatt for the most modern facilities, excluding chips and GPUs. Power infrastructure remains the single largest cost category, representing an average of 21% of total greenfield development costs, while contingencies rank second, reflecting ongoing uncertainty driven by long material lead times, labor shortages, and a shifting regulatory environment.

Land acquisition activity has intensified across North America, with powered land in primary U.S. markets achieving average values of $584,000 per MW in 2026 year-to-date—35% above its five-year average and 51% higher year-over-year. Skilled labor shortages in the mechanical, electrical, and plumbing trades continue to compound cost pressures, driving a 5% average annual wage increase from 2021 to 2024, with even steeper growth recorded in secondary and tertiary markets.

The report also highlights a growing geographic shift in development activity. Frontier markets are projected to see capital expenditure grow 6.9-fold from current levels, reaching $631 billion, as developers seek locations with available land, accessible power, and more favorable regulatory conditions. Texas markets continue to rank among the lowest-cost development environments due to their business-friendly regulatory climate, lower construction labor costs, and mature contractor ecosystems.

Click here to view the report.

About Cushman & Wakefield

Cushman & Wakefield (NYSE: CWK) is a leading global commercial real estate services firm for occupiers and investors with approximately 53,000 employees in over 350 offices and nearly 60 countries. In 2025, the firm reported revenue of $10.3 billion across its core service lines of Services, Leasing, Capital markets, and Valuation and other. Built around the belief that Better never settles, the firm receives numerous industry and business accolades for its award-winning culture. For additional information, visit www.cushmanwakefield.com.