CATL kicks off trial production of battery cells in Hungary

· Issued by Contemporary Amperex Technology Co., Limited via CNW

Summary by 6ix AI

Battery maker CATL began trial production on September 22, 2026 on the first two production lines of its newly built battery cell factory in Debrecen, Hungary. This followed an occupancy permit in August 2026, after which CATL obtained all relevant permits and completed all preconditions of its IPPC (integrated pollution prevention and control) permit.

Key details

  • The trial is meant to set up, optimise and validate the production equipment and manufacturing processes before series production starts.
  • Before issuing the occupancy permit, the Hajdú-Bihar County Government Office carried out regular on-site inspections to follow up on earlier issues that had caused serious worries among local inhabitants. Authority representatives confirmed that CATL had resolved all deficiencies identified earlier in the permitting process.
  • CATL has made battery modules (assemblies of battery cells) in Debrecen since autumn 2024 and has produced 537,000 modules since then.
  • CATL says that once all facilities are ready, the Hungarian plant will be its largest manufacturing base outside China, with a 100 GWH (gigawatt-hour) capacity. CATL announced the plant, its second in Europe, in August 2022, and construction of the first cell building started in summer 2023.
  • CATL says employee health, safety and environmental factors will be monitored during the trial operation and the results will be submitted to the authorities.

What’s still pending

  • Series production has not yet started; trial production comes first.
  • The 100 GWH capacity applies once all facilities are ready.

6ix AI wrote this summary from the release below and checked it against the release.

DEBRECEN, Hungary, Sept. 22, 2026 /CNW/ -- CATL begins trial production on 22 September 2026 in its newly built cell factory in Debrecen as the company had fulfilled all preconditions required to commence trial run. The purpose of trial production is to set up, optimise and validate the production equipment and manufacturing processes ahead of the start of series production. CATL Debrecen continues cooperating and working closely with the government and the authorities in order to keep high standards on the environmental issues as well as the health and safety of its employees.

CATL announced the construction of its second European battery plant in Debrecen in August 2022, with the aim of integrating to the European automotive and e-mobility supply chain and better serve leading European automakers. Construction of the first cell building started in summer 2023 and by spring 2026 the building had been equipped with the most advanced technology. After obtaining the occupancy permit in August 2026, the company obtained all relevant permits and completed all pre-conditions required by its IPPC permit prior to start trial operations from 22 September on the first two production lines of its cell manufacturing facility.

Prior to issuing the occupancy permit, the Hajdú-Bihar County Government Office carried out regular on-site inspections at CATL's facilities in order to follow up on previous issues creating serious worries in local inhabitants. Authority representatives confirmed that the company had resolved all deficiencies identified earlier in the permitting process.

As a strategic manufacturing hub, CATL's Debrecen plant will supply the most well-known, leading European automakers, which have already built significant electric vehicle production capacity in Hungary in recent years. As a global technology leader CATL implemented the most advanced, flexible production lines in Debrecen in order to fulfil the needs of its valued clients at all times. The company has already been manufacturing battery modules since autumn 2024 in Debrecen and has already produced 537,000 modules ever since. Once all facilities ready, the Hungarian plant will be CATL's largest manufacturing base outside China with a 100 GWH capacity.

Alongside obtaining the permits and completing pre-conditions required to launch trial operations, CATL Debrecen remains committed to working closely with the Government and the authorities to prioritize the health and safety of its employees. Furthermore, employee health, safety and environmental factors will be thoroughly monitored during the trial operation as well, and results will be submitted to the Authority proactively. CATL's investment is not only important for Debrecen and its region, but also for the Hungarian economy and the European e-mobility supply chain. CATL is committed to transparency and welcomes the authorities to visit its site at any time.

View original content to download multimedia:https://www.prnewswire.com/news-releases/catl-kicks-off-trial-production-of-battery-cells-in-hungary-302886085.html

SOURCE CATL

© Canada Newswire, source Canada Newswire English

Contemporary Amperex Technology Co., Limited on 6ix

Earlier from Contemporary Amperex Technology

Later from Contemporary Amperex Technology

All Contemporary Amperex Technology news releases