Orezone Gold (TSX:ORE) Q3 2026 earnings call. Replay available.

On 6ix: 6ix.com/event/orezone-gold-corporation-ore-q3-2026-earnings-call
Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.
0:00 Ladies and gentlemen, thank you for standing by. My name is Abby and I will be your conference operator today. At this time, I would like to welcome everyone to the ORAZONE third quarter 2026 results webcast and conference call. All lines have been placed on mute to prevent any background noise. After the speaker's remarks, there will be a question and answer session. If you would like to ask a question during that time, simply press star followed by the number one on your telephone keypad. If you would like to withdraw your question, press star 1 again. Thank you. And I would now like to turn the conference over to Mr. Patrick Downey, President and Chief Executive Officer. You may begin.
0:40 Thank you and welcome to the OZONE Q3 webinar and conference call. With me today, I will have Peter Tam, Executive Vice President and Chief Financial Officer. I will be using forward-looking statements, so please be aware of that. Okay. So the third quarter was another important period for Orzone, highlighted by record gold production and strong financial performance and continued progress across both of our operating mines. We produced a record 59,674 ounces of gold during the quarter, bringing our year-to-date production to 157.29 ounces. Consolidated all-in sustaining costs were 2,475 per ounce for the quarter, with year-to-date costs of 2,409 per ounce.
1:36 From a financial perspective, we generated approximately 112 million in adjusted EBITDA and reported net income of 28 million. These results reflect the contributions of both Bomboré and Casabarri and demonstrate the growing scale of our business. Importantly, we ended the quarter with approximately 147 million in cash and volume, providing us with a strong financial position as we continue to invest in our operations and advance our growth initiatives. Another significant milestone during the quarter was the release of our updated life of mine plan for Casa Berardi in September which we will touch on later in this call. I'd now like to hand over to Peter Tam.
2:22 Thanks Patrick. On our financial performance, Q3 was another consecutive quarter of mine earnings, free cash flow, and net income. Gold sales benefited from record gold production of over 59,000 ounces and a realized gold price slightly under $4,200 per ounce. Gold sales were modestly below gold production due to settlement timing of quarter and gold shipments at both operations. Our balance sheet continues to delever with cash flowing up to $116 million. and senior bank debt being reduced to $56 million at quarter end. Cash in the quarter was impacted by the annual dividend of $16.8 million paid to the Burkina State on their 15% share of Bonboré 2025 net earnings.
3:07 Next slide. For Bonboré, quarterly production at Bonboré continues to trend higher with 40,562 ounces produced in Q3. at an all-in sustaining cost of $2,246 an ounce sold. Q4 is expected to continue this trend with higher production forecasted to allow Bombardier to achieve its production guidance for 2026. Next slide. For Casa Berardi, as expected, Q3 was lower than the previous quarter. Production was lower than the previous quarter due to open pit mine sequencing and the use of lower grade stockpiles. Porter was further impacted by a seven-day voluntary shutdown of mining and processing operations due to local wildfire activities.
3:57 Despite these factors, the operations exceeded planned throughput and recoveries, allowing production to remain on target. Similar to Bon Barre, gold production in Q4 is expected to be highest in the year. I'll hand that call back to you, Patrick.
4:11 Thank you, Peter. So moving on to our 2026 guidance, We remain on track to achieve both production and cost guidance for the year. Our consolidated gold production guidance remains unchanged at 222,000 to 247,000 ounces, with all-in sustaining costs expected to be between 2,200 and 2,400 per ounce. At Bombori, we expect full-year production within the lower half of our guidance range, and our all-in sustaining costs are expected to be within the upper half of the guidance range. Importantly, construction and commissioning of Stage 2A hard rock expansion is now being completed, yet again under budget, so congratulations to the team for a third time in a row. We have also completed Stage 5 tailing storage facility lift, and we are now into Stage 6 lift, which is advancing ahead of schedule.
5:09 At Casa Berardi, we expect production to achieve the midpoint of our guidance range, with our costs projected towards the lower end of the range. We have completed our 2026 storage facility lift to level 5022 and deliveries of underground mobile equipment are generally continued throughout the period and will remain on track for 2027. As previously discussed, our production profile for 2026 is weighted towards the second half of the year, particularly in Q4. With progress made during the third quarter and improved access to high-grade material expected at both operations, we remain well positioned for a strong finish to the year. Next slide.
5:54 Turning to slide nine, I'd like to spend some time discussing the updated Casa Berardi Life of Mine Plan released in September. We firmly believe this plan represents an important milestone for Orzone and establishes a clear foundation for the long-term future of Casa Berardi. This plan outlines a 14-year mine life with total gold production of approximately 1.63 million ounces, with average annual production expected to be approximately 116,000 ounces and a life of mine all in sustaining cost of just under $1,900 per ounce. A key component of the plan is the restart of higher-grade underground mining, which is expected to support a stronger and more sustainable production profile over time.
6:41 From an economic perspective, the Life of Mine Plan outlines an after-tax net present value using a 5% discount rate of approximately $1.05 billion under base case consensus gold price assumptions. We believe the updated Life of Mine Plan provides a solid foundation rather than representing the full potential of the asset as there are a number of operational improvements and exploration opportunities that could further enhance the production profile and economics over time. Next slide. At Casa Berardi, we see significant opportunities to enhance performance beyond our current life of mine plan. On the operational side, higher mill throughput, which we are now seeing, and improved grade control and increased gold recoveries have the potential to drive the production above the life of mine plan while reducing unit costs.
7:38 On the exploration side, resource expansion and new discoveries offer opportunities to add higher grade arches and strengthen the production profile and extend mine life. We have also updated the development rate. We started at five meters per day approximately when we took over the mine, and we are now well over 16 meters per day, and we had a record in the past week of over 26 meters per day in our development rates, so everything is appearing to be on plan as we move forward into 2027. Exploration, it continues to be a key component of our strategy. With two established operating mines and significant prospective land positions, we see considerable opportunities to expand our resource base, improve future mine plans, and identify additional higher-grade mineralization.
8:33 I'll briefly highlight the work underway at Bombore and Casa Berardi. Starting with Bombore, our 2026 exploration has focused on three primary objectives. The first is extending mineralization at depth beneath the existing life of mine pits. The second is identifying and further delineating higher-grade subzones. And third is extending near-surface mineralization along strike. The drilling program has continued to deliver encouraging results on all fronts. Highlights from the third quarter include 2.97 grams over 34 meters, including 4.5 grams over 7 meters. We also reported 4.28 grams per ton over 11 meters and 8.34 grams over 6 meters.
9:26 These results continue to support our view that there is meaningful exploration potential both within and beyond the currently defined mining areas. Looking ahead, we expect to release an updated Bombori Life of Mine Plan during the first quarter of 2027, which will incorporate an additional 100,000 metres of drilling on the property. Our exploration in 2027 is expected to include infill drilling of the higher-grade subzones with the objective of evaluating potentially suitability for underground mining. At Castle Berardy, Thank you very much. while continuing resource conversion drilling in advance of mining.
10:39 Results to date have been very encouraging. Highlights include 6.47 grams over 21.5 meters, including 8.94 over 12.7 meters. These results reinforce our confidence in the exploration potential of the property and the opportunity to identify additional higher-grade mineralization. Looking ahead, we are budgeting approximately 100,000 meters of exploration drilling at Castle Variety in 2027 and will continue to targeting downplunge extensions, infill for conversion and targeting of new zones. So before we open the call for questions, I'd like to highlight several important catalysts we expect over the coming months.
11:25 First, we anticipate another strong quarter of production in Q4, supported by improved access to higher-grade material at both Bomboré and Casa Berardi. Secondly, we expect to release the Havel-Hosco preliminary economic assessment during the fourth quarter. The release is taking slightly longer than anticipated due to a delay in one consultant's work, but we expect to deliver a comprehensive and technically sound report when complete, and we look forward to that release. Thirdly, we continue to advance an active exploration program across both operations with 12 rigs currently operating. We expect ongoing exploration results at both properties to provide further insight to the potential for resource growth and mine life extensions.
12:12 And finally, as mentioned previously, we are targeting the release of an updated Bombory life of mine plan during the first quarter of 2027, incorporating an additional 100,000 meters of drilling. With that, I will open it up for questions. Thank you. We'll now begin the question and answer session. If you have dialed in and would like to ask a question, please press star 1 on your telephone keypad to raise your hand and join the queue. If you would like to withdraw your question, simply press star 1 again. If you're called upon to ask your question and are listening via speakerphone on your device, please pick up your handset and ensure that your phone is not on mute when asking your questions. Again, it is star one to join the queue.
12:58 And our first question comes from the line of Cosmos Chui with CIBC. Your line is open.
13:07 Hi, thanks, Patty and team. Maybe my first question is on Casa Verde and good to see that operations continue to improve at Casa. I don't think I saw in the press release, but do you happen to have a breakdown of the underground mining grades? versus the open pit grades. Is that something that you can share with us? Is that something that we should track? Is that something that's important?
13:36 Peter, did you get that at hand?
13:37 Yeah, I mean, we do have that obviously internally here.
13:41 Yep.
13:42 It is something we could share sort of going forward. In Q3, the open pit grade to the mill was obviously a bit lower. That was obviously reflected in our Q3 production for CASA, so... I would say I believe that was sort of around the 1.8-ish area, and then sort of for the underground grade, it was closer to 3.5.
14:03 Great. And that's something we should continue to track, right, because then we can see how things have improved, would you say, Peter or Patty?
14:14 Yes, we would agree with that, yes. That is correct, yes.
14:17 Okay. and then you know the other thing that I've been tracking of course Patty is your underground development rates great to see that it was 11 meters per day in the previous two quarters 15 meters per day average October and then the new information was I guess 26 meters per day as a high watermark that you've reached is that sustainable number one to 26 meters per day Patty and And can you remind us to get to your new life of mine plan? What's sort of like the intermediate target in terms of meters per day and then the longer term target as well?
14:55 Well, we were expecting to be around about 18 average by the end of the year, moving into 22, 23 next year. Obviously, we're extremely excited to see 28 and a half. I always ask the question, unless you can do it one day, why can't you do it the next day? So but having said that it's what's really we have seen is that there's an uptick in the contractor performance but with the life of mine being released we have attracted some very significant underground development miners back to the company and they've come in they've got lots of experience they don't have to learn the mine they know the mine so I'm hoping that we will continue to see an uptick in that but I expect to see 28 meters a day every day Well, I'd love it, but I don't think we'll see it every day. But what I'm seeing is a very, very positive trend ahead of where we plan to be. So we've also brought new equipment in, which is very important, particularly around bolters.
15:54 Bolters were one of the key things. And so we've ordered ahead for 2027 equipment already in 2026. So we want to keep it ahead of the curve. But all in all, very positive. But next year, Average of 22 to 23 to meet the plan and we're well on track to get there.
16:13 That sounds great.
16:15 Maybe switching gears a little bit to Burkina.
16:18 As we've seen in the country now there are refineries and I think the government encourages the refining of gold production within the country. Does that impact Bombory in any way and could you maybe talk about the current sort of flow of the metal production out of Bombory and more importantly at this point in time the flow of cash flow at this point in time and could that change?
16:46 Yeah, I'll hand that over to Peter. He generally looks after that to answer that question but happy to do so.
16:51 Yeah, thanks Cosmo for the question. So Burkina has opened their new refinery in country and and we do congratulate them on the successful construction. We have visited the refinery and we are working with them right now to finalize the refining contract and sort out the logistics and other arrangements. So in the interim, we're continuing to ship our gold as scheduled and be able to sell our gold as we have normally. So all of that is sort of happening uninterrupted. So no issue with selling the gold and repatriating those proceeds back to the country. I suspect once we get the new refining agreement arrangement in place, we'll continue to be able to do that.
17:34 Great. Maybe one last question, and maybe likely for Peter as well, but Patty, if you want, you can take it. Depreciation. I guess depreciation was a bit higher than what I expected in Q3, and it was an increase from Q2, and it impacted your earnings number, EPS, which is not cash, but still it impacted it. Maybe could you remind us is it due to the acquisition of CASA you know increasing the any kind of PP&E and hence higher depreciation or is that something else that I should be aware of and what should I be sort of modeling for Q4?
18:14 Yeah look Cosmo I think you've mentioned it I think you've hit the nail on the head obviously it is with our new operations that we brought on that we acquired earlier in the year Some of that is the PPA adjustment and having to obviously amortize that now over the updated lifeline that we have. So I would say that is something you would expect to see sort of on a go-forward basis.
18:37 Great. Thanks, Patty and Peter. Those are all the questions I have. Thanks again. And our next question comes from the line of Mohamed Sidibe with National Bank. Your line is open.
18:51 Hi, Patty and Tim, and thanks for taking my questions. Maybe for my first question, if I could start with the Bomboré Stage 2, where I think the investment decision is still pending, and I think you're leaving that under review. If Stage 2 does not proceed, what is maybe the realistic throughput and recovery ceiling after stage 2a that the mine can reach because you know so far even just in Q3 you can see that throughput is performing quite well at the mine and probably beyond the 2.5 million ton per annum from stage 2a there. So any color on you know what the potential upside or realistic throughput Bombora is without stage 2b?
19:32 Yeah so we've just commissioned stage 2A, which is the thickener, the oxygen plant and the rock breaker. So we get that set in and then we look at the blend, but that'll be part of next year's budget. I think hopefully like every other operation we've built, we will be able to push it harder. We're seeing around now about 2.8 to 3. We'll see whether we can get beyond that as we move forward. Again, each rock type, there's several different rock types at Bomboree, is to do a grind and hardness. But yeah, I would expect that we will be above nameplate, which I think was 2.5.
20:13 Great. And as it relates to Stage 2b, how have the conversation of the government advanced on that topic, or are you still in a wait-and-see mode on that one?
20:23 Yeah, I think we're waiting to see. There's been no final settlement on the KIACA front. We haven't seen that final announcement. We'd like to see that settled first before we make any decisions and we have informed the government of that. It's not something we haven't talked about.
20:43 And then for my second question, if I may, on Heva House Co., with the PEA coming by the end of the year, can you give us a sense of the scale of Heva House Co., how you're thinking about the asset and potential capex or capex intensity and how we should look at that? Any additional color ahead of the PEA would be appreciated, if possible. Thank you.
21:06 Well, I obviously don't want to pre-release anything, but All I can tell you is it was a 3 million tonne per annum feasibility study in 2012. That's exactly the way we're looking at it. So all those quantities, etc. are very well defined in that feasibility study. We've gone through that fairly detailed. So we are using generally the same quantities that were in there, the same sort of layouts, etc. We're just updating them for current costs and we're likely doing a little bit of a schedule change as to how we build plants. That's the way I would look at it. I really can't get into any more detail other than that. It is a 3 million ton per annum plant. Open pit.
21:47 That's great. That's helpful. Thanks a lot, Paddy. That's everything for me. Okay. As a reminder, it is star 1 if you would like to ask a question. Our next question comes from the line of Jeremy Hoy with Canaccord Genuity. Your line is open.
22:05 Hi, Patty and team. Thanks for taking my questions. I guess for me, I'd like to touch on your goal of achieving 300,000 ounces per year. You're a good way of the way there already. What are the other major components that get you there? I think it's pretty easy to see. Are you expecting to get much of an uplift in production, perhaps from underground at Bonvore? Or, well, you had already commented on 2B. So let's just talk about the potential for underground on Bonvore, which you had included in your presentation as well.
22:47 Yeah, so right off the bat, if you look at the castle level mine, we'd be pushing towards 150,000 ounces a year. And that's the goal. And we're doing a lot of drilling and Hopefully we'll have drill results out here in the next week to 10 days that will continue to show that that is the case that we will be following. Bombori would go over 200,000 ounces, 230 to 250 if and when we do stage 2B. It's really a no-brainer if you look at it from a return on invested capital. We've done a review of it. It's still around $80 million. As you can see now, we've done three bills there on time, on budget. So we would expect that to be the case. You know, if you take that against a North American asset for this, it would be 400 million, not 80 million.
23:32 So we would love to get started on that, but we want to make sure that we're on the right track. And then Hever Hospital, I would say would add in the region of 110,000 ounces a year. We will get straight into feasibility study right after the PEA coming out towards the end of the year. but our plan would be to do infill drilling and get up to date on the permitting. A lot of the work was done to schedule 19 already, so it really is a gap analysis and then getting straight into that. It will be of a capital cost that we as Orzone can take on ourselves. So if you add all those together, there's a clear path to 500,000 ounces, really not 300,000 ounces. So 300,000 ounces is the short-term goal here.
24:23 Yeah, great. That's, that's, it is quite the step up. On Havahasco, we're getting the study shortly and looking forward to the details there. At a high level, could you walk us through the timeline to first production?
24:39 Well, I would say if you could get a, you know, there was a lot of feasibility work done. And so normally, I would say a feasibility would be 18 plus months. but we will have a look at and see if we can push it with our team since we've got quite a strong internal team here. We've gone through two feasibility studies and two bills in the past couple of years but never mind they're in Africa, they're still bills, they're still studies. I would expect that we could try and get that done early 2028 and then make an investment decision with the board by mid-2028. Going into permitting would probably take another 18 months so I would say at a minimum it would be two and a half to three years.
25:26 Great. Okay, thanks. Well, I appreciate you answering my questions. I'll step back in the queue. And that concludes our question and answer session. I would now like to turn the conference back over to Mr. Patrick Downey for closing remarks.
25:42 Well, thank you everyone for being on the call and the webinar. Look forward to a Very strong Q4 to end the year. Drill results and our Hable Hospital PEA. So I'm looking into 2027 as we move forward in both CASA and Bombore. So let's just hope the gold tape holds up. Ladies and gentlemen, this concludes today's call and we thank you for your participation. You may now disconnect.
Follow Orezone Gold Corporation into a list and get an email when it puts out news.