Mining Americas (TSX:MAI) reported Q3 2026 results on this call. Replay available.

On 6ix: 6ix.com/event/mining-americas-inc-mai-q3-2026-earnings-call
Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.
0:00 Hello and welcome to the Minings Americas Inc. Third Quarter Results Conference Call. All lines have been placed on mute to prevent any background noise. After the speaker's remarks, there will be a question and answer session. If you would like to ask a question at this time, just press star followed by the number one on your telephone keypad. And if you would like to withdraw your question, just press star one again. Thank you. I will now turn the call over to our Darren Blasutti, Chief Executive Officer. You may begin.
0:26 Thank you, Operator. and welcome to our our third quarter conference call and I'll thank everybody for joining today. We'll be discussing our third quarter financial and operating results which were released earlier this morning as well as continue to update the progress in our growth projects which we released last week in a big press release which I hope everybody had a chance to read and after a brief presentation of course as the operator said we'll be have some time for questions and answers If you're joining in over the phone, we also welcome you to join the webcast in the corresponding slides. The link can be found on our website and also in the Q3 results news release. On the line for management with me today, we have President and Chief Operating Officer Darren Koningen, CFO Alfred Colas, as well as other members of our leadership team.
1:15 We will, of course, be making forward-looking statements throughout the presentation, and as such, we encourage listeners to review the relevant disclaimers on slide number two. The third quarter of 2026 marked our first full year of ownership of the Pan operating complex in Nevada. And looking back, Darren and I are proud of not just what we've achieved through production and cash flow from the operation, but also from the exemplary safety that the team has continued to show at site. The Pan mine has played a very key role, enabling us to advance the business and our growth projects, which we've seen much progress over the past year. Beyond the financial and operating results in Q3, we received the major permits required for construction and operation of our Cerro Doral open pit heat bleach mine located in Zacatecas, Mexico, unlocking significant value for our company and de-risking a key part of our growth pipeline.
2:13 In October, we bought 15,600 puts representing 60% of PAN's expected goal production for the next nine months with a floor price of $3,800 an ounce gold to insure against potential lower gold prices, which we see as prudence given the significant investments we are making in our growth projects, especially at Copperstone and GoldRock. I will now hand it over to our CFO, Alfred Colas, to walk through some of the financial highlights for the quarter. Thanks, Darren.
2:46 All amounts are presented in U.S. dollars. In the third quarter, gold production was 7,915 ounces. Gold sales were 7,620 ounces at an average realized gold price of $4,281 per ounce. This was the first full quarter of 100% exposure to spot gold prices, having settled all the remaining gold prepay and call option contracts in the second quarter. Quarterly revenue was $32.7 million. and earnings from mine operations was $11.1 million. The company realized the net loss of $3.6 million or 3 cents a share and EBITDA of $1.6 million.
3:31 However, when excluding the non-recurring Cerro de Oto permit payment of $5.3 million, adjusted net income was $1.6 million or 1 cent a share and adjusted EBITDA was $6.8 million. Our balance sheet remains robust. We ended Q3 with cash and cash equivalents of $36 million and working capital of $104 million, up from $82 million at the start of the year. Total available liquidity is now $66 million, including $30 million undrawn on the company's $75 million revolving credit facility with Scotiabank and National Bank. Q3 cash costs were $2,055 per ounce sold of gold all unsustaining costs were $2,121 per gold ounce sold.
4:24 While these increased quarter over quarter, our year-to-date cash costs of $1,836 per ounce sold and all unsustaining costs of $1,988 per ounce sold remain within our guidance, despite higher than budgeted diesel fuel costs. The company remains on track to achieve 2026 guidance at the Pan Mine with gold production of 32,000 to 38,000 ounces, cash costs of $1,750 to $1,900 per ounce sold, and own sustaining costs of $1,850 to $2,000 per ounce sold. In terms of the changes in our cash position through the third quarter, our PAN operation contributed $6 million net of inventory changes.
5:10 CapEx at the operation used $3 million. We spent $2.3 million in CapEx at Copperstone, $5.3 million for the Cerro de Oto permit payment and $1 million on interest charges. Combined with other financial items such as FX loss, our cash balance declined by $7.5 million in the quarter. And now I'll hand it over to President and COO Darren Koningen to discuss the PAN operating results and an update on our growth projects.
5:40 Thanks, Alfred. I'm pleased to say the Pan Mine continues to have an exemplary safety record with the operation now nearing five and a half years with no last time incidents. The mine plan adopted in early 2026 together with the new mining contractor supported a sustained mining rate of approximately 60,000 tons per day in Q3, which is consistent with Q2 and over 30% above the 2025 average. Mining rates actually peaked close to 70,000 tons in June before higher than anticipated equipment operator turnover affected performance during Q3. Through proactive workforce planning and additional retention incentives, the company is now seeing further productivity improvements.
6:27 Head grades at PAM were slightly below expectations for Q3 and for the first nine months of 2026. Reconciliation against the 2026 budget plan showed a slightly higher for a portion of lower-grade material and less higher-grade material. Gold prices also remained above those assumed in previous mine plans, supporting the use of dynamic cut-off grades to economically mine, stock, and leach additional lower-grade mineralization. Despite the higher-than-budgeted diesel prices compared with the start of the year, the impact on operating costs has been somewhat offset by the economies of scale from the increased mining rates. We remain within our guidance ranges for both cash costs and all-in sustaining costs for the year to date.
7:14 Last week, we also announced a progress update on our growth projects, including Copperstone, Gold Rock, Cerro de Oro, and Santana. At the Copperstone Underground Gold Project in Arizona, construction is continuing to advance. Major grinding mill rehabilitation was completed during the quarter, and a new mill drive and motor were secured. Removal of the old grinding circuit and surrounding area was completed in advance of civil and concrete works. The construction support team has now been expanded with additional key personnel in place to maintain timely progress during the major construction phases. The company's technical group has also been actively searching for equipment alternatives in order to minimize the impacts of the current supply chain challenges being experienced by all ongoing development projects. Notably, we have recently mobilized the underground mine contractor and started mine rehabilitation with early access, further de-risking the future startup of production mining activities.
8:20 The CapEx for the Copperstone project is actually comprised of almost 50-50 split between minehab and redevelopment and the surface plant and infrastructure upgrades that were the primary focus in Q3. Through the end of the quarter, the company has committed a total of almost $5 million of cumulative costs of the Copperstone project, including $3 million as growth capital. The project continues to be on track with anticipated production startup towards the end of next year. We anticipate releasing a mineral resource update this quarter to quantify potentially open-pit mineable gold mineralization based off the existing project resource models for Copperstone. And surface drilling continues in the existing open pit area with a goal to eventually expand the areas of known mineralization.
9:10 At the fully permitted Gold Rock project, which is part of the Pan-Operating Complex in Nevada, early works have recently progressed, including the upgrading of the road from Pan to Gold Rock, ordering liner for the pads and ponds, and refurbishment of a company-owned crushing circuit. We anticipate releasing an updated mineral resource estimate for Gold Rock later this quarter once the Copperstone Old Pit resource has been completed. We also have placed an order for 100-ton haul trucks to be used to remove historic heap leach pad material from the Gold Rock site to the heap leach pad at Pan for some additional residual gold recovery during the Gold Rock construction period in 2027. In Mexico, with the major permits in hand for Cerro de Oro Open Pits, Heat Bleach Gold Project in Northern Zacatecas, Mexico. We continue to progress the project towards a construction decision. In the first half of 2027, the company anticipates releasing an updated mineral resource estimate, which will incorporate higher gold prices than the $1,700 an ounce that was used previously. In the second half of the year, the company anticipates completing a pre-feasibility study for the project as well.
10:24 And lastly, for the Centeno pit, Keep Leach Gold Mine in Sonora State, Mexico. Production started there in 2021, but mining and leaching was put on hold in 2025, while we waited for permits for expanding the keep leaching areas. In recent months, we have been making progress regarding the expanded permit applications, and also new water rights have been granted, which further de-risk a production restart decision. We have also advanced metallurgical test work designed to investigate The leachability of sulfide-bearing gold mineralization at greater depths at Santana, and the results have been encouraging so far. Finally, tests have also been initiated in this third quarter to investigate options for the potential re-leaching of the existing heat bleach pad at Santana.
11:12 Early efforts are aimed at achieving more complete solution saturation in various areas of the pad. And with that, I'll hand the call back over to Darren Blasutti.
11:23 Thanks, Darren. It's been a very exciting, dynamic year since we bought PAN, catalyst-filled. And so as we sit here today, about a year out from having both Copperstone and GoldRock producing gold, there's a lot of work ahead of us in the next year. We're obviously all disappointed with where the current share price is today. But again, it's management's job to keep its head down. focus on building these mines out for the future development or for the future benefit of our shareholders. And we will do just that. I think as we move forward, every ounce of the company's management and board will be focused on building Copperstone and Gold Rock and continuing to have PAN generate cash flow as we move forward.
12:15 With that, this concludes the presentation portion of the conference call. We have some time for questions Questions and answers, I'll pass it back to the call operator for those instructions. We will now begin the question and answer session. If you would like to ask a question, simply press star followed by the number one on your telephone keypad. Again, if you would like to ask a question, just press star followed by the number one on your telephone keypad. There is no question at this time. I will now turn the call back over to Darren Blasutti for closing remarks. Darren?
13:03 Thank you very much, operator. Well, as I said, you know, we're moving forward with our projects. As Darren Koningen updated us, a lot of Darrens in the room, you know, we're making great progress on both Copperstone and Gold Rock. Again, we expect the upcoming catalyst to be two resource updates this quarter on both the Copperstone Open Pit, which I think we get very little value for, and of course the Gold Rock project, which we look forward. We've done a lot of pre-construction work on it already. It clearly is a very high return project at these gold prices. And so the plan for the management is to make sure that these things are valued in our stock price as we go forward. And again, I'll just say that we look forward to better days ahead as we continue to drive forward our growth profile through 2028, where we think in 2029 we'll produce somewhere between 170 and 180,000 ounces of gold at much lower prices than we produce today.
14:01 That's the thesis that I think everybody's invested on and that we, the management and board, have invested in. And despite setbacks that we've had recently with goal price reductions and disappointment our share price, we will continue to work very hard to deliver on those goals. And I expect that we're on track to do those things and we continue to be on track. And again, we look forward to the coming quarters to show you the progress we're making. With that, thank you very much and appreciate you guys joining the call today. Thank you. This concludes today's conference call. You may now disconnect.