Replay available

Golar LNG (NASDAQ:GLNG) Q1 2022 Earnings Call

Golar LNG (NASDAQ:GLNG) Q1 2022 earnings call, held 2022-05-26. Watch the replay and read the transcript on 6ix.

Thu, May 26, 2022 at 10:00 AMendedReplay
Golar LNG (NASDAQ:GLNG) Q1 2022 Earnings Call
Company
Golar LNG Limited (NASDAQ:GLNG)
Period
Q1 2022 earnings call
Date
Thu, May 26, 2022, 10:00 AM ET
Replay
Watch the replay on this page · 58 min
Results news release
Interim results for the period ended March 31, 2022 · Thu, May 26, 2022

On 6ix: 6ix.com/event/golar-lng-limited-glng-q1-2022-earnings-call

Replay

Transcript

Automated transcript · Written by software from the replay's audio. It can mishear names and figures; the replay is the record.

0:00 Good day and thank you for standing by. Welcome to the GOLA LNG Limited Q1 2022 conference call. At this time, all participants are in a listen-only mode. After the speaker's presentation, there will be a question and answer session. To ask a question during the session, you will need to press star 1 on your telephone. Please be advised that today's conference is being recorded. If you require any further assistance, please press star 0. I would now like to hand the conference over to your speaker today, Karl Staubo, CEO. Please go ahead.

0:35 Thank you and welcome to Goal RLNG's Q1 earnings results presentation. Thank you for taking time to dial in. My name is Karl Fredrik Staubo, CEO of Goal RLNG.

0:46 Before we get into the presentation, please note the forward-looking statement on slide 2.

0:52 I'm accompanied today by our CFO, Mr. Eduardo Maranhao, to present this quarter's results. On slide four, we have outlined the company overview. Golar today owns two FLNGs, the Golar-Hilly in operation in Cameroon, and the Golar-Gimme under construction to start a 20-year contract with BP from Q4 of next year. Furthermore, we own an LNG steam carrier, the Golar Arctic, where we announced last week that we have agreed with SNAM to forward sell the ship as a converted FSRU. Lastly, we own the Golar Tundra, the most modern promptly available FSRU globally, currently operating as an LNG carrier.

1:42 We have developed three FLNG designs that form the basis for our growth plans, All three designs are based on the same proven liquefaction technology, and we will highlight some of the key characteristics of the different capacities of the units later in the presentation. As a result of significant corporate transactions over the last 12 months, we have three listed shareholdings. We own 6% of New Fortress Energy, valued at $558 million on yesterday's close. We own about 31% of Cool Company Limited, the shipping spinoff we established during Q1 of this year. We own around 24% of Avenir LNG, a small-scale LNG shipping and terminal business.

2:33 And the total value of these investments amount to approximately $720 million. Golar celebrates its 75th year of operation this year. 50 of which we've been actively involved with LNG maritime infrastructure assets. Golar has through its history pioneered some of the key developments in the sector including the industry's first FSRU, the first FLNG as well as the first ever integrated FSRU to power plant projects. We have a market leading operations and have achieved 100% commercial uptime since the startup of Hille in 2018. We're now focusing the company for FLNG growth opportunities.

3:24 Turning to slide five, and again, as a result of the M&A activities over the last 12 months with a total enterprise value of $6.2 billion at the time of sales, we have significantly strengthened our balance sheets. We currently have $1.4 billion of cash and listed securities, where about half is cash and half is listed securities. We currently have a net cash position. Adjusting for the remaining capex on the FLNG GIMI, we have a total net debt position after delivery of GIMI of $300 million. That number excludes operating profits between now and GIMI delivery, so we anticipate that that number will be lower.

4:19 Based on increased capacity utilization of HILI, commodity upside on the tolling fee, and startup of GIMI in Q4 of next year, we expect EBITDA generation to quadruple in 2024 versus 2021 levels. We've also refined corporate facilities, and we currently have no debt maturities until 2025. I'll now hand the call over to Eduardo to present our Q1 results.

4:51 Thanks, Karl, and good morning, everybody. I'm very pleased to provide an update on our group results for the first quarter of 2022. So turning over to slide number seven, I wanted to show some of the highlights of this quarter, starting with our FLNG units. Our first vessel, Helid, continues to operate with a very solid performance, delivering 100% uptime. The Brent-linked kicker in our contract generated an incremental EBITDA of $16 million this quarter, or 36% up when compared to Q4 last year. Since 1st of January, we've started to realize our TTF-linked production from Train 3, which added an incremental EBITDA of $22 million. I will explain those different elements in more details further in this presentation.

5:39 Construction of our second FLNG unit, the GIME, continues in Singapore and is now 83% technically complete. We continue to make substantial progress on commercial discussions for future FLNG units and we have a strong pipeline of opportunities for growth projects. So moving on to shipping and FSRUs, the formation of Cool Company was successfully completed this quarter. We've raised $275 million in a private placement in January, followed by the listing of its shares in the Euronext exchange in Oslo. In connection with that, Cool Company acquired eight of our TFTE's vessels. In May, we announced the award of over €269 million contract with SNAM for the conversion of the Golar Arctic into an FSRU.

6:30 Due to the current geopolitical situation in Europe, We continue to see a very active FSIU market and have received inquiries from multiple European counterparts for the deployment of our last unit, the Golar Thunder. We continue to strengthen our balance sheet and since the start of this year, we have released $470 million in cash proceeds from the coal company spin-off and also the sale of a portion of our NFE state. In February, we have repaid $317 million of our outstanding convertible bonds, and then also entered into a new bilateral corporate facility of $250 million. We've continued our share buyback program, and so far we have repurchased approximately 400,000 shares this quarter, leaving 108 million shares after that outstanding.

7:25 So moving on to slide number eight, This quarter we recorded an adjusted EBITDA of $93 million. This result is inclusive of Healy, Arctic, and Tundra, but excludes the eight TFTE vessels that were sold to Cool Company. When compared on a like-for-like basis to the previous quarter, this represented an increase of 55%. Net income attributable to GOLOR was $345 million in this quarter, and that includes 168 million non-cash gain which was recognized on our Healy Brent Oil and TTF linked derivatives and also a 344 million also non-cash market-to-market gain recognized on our NFE shares based on a March 31st position which carried the value of $42.61 per share.

8:22 Our share of contractual debt at the end of the quarter stood at $1.7 billion dollars. However, half a billion of that relates to 40 FTE vessels that were sold to Cool Company in April. So that leaves us with the $1.2 billion of contractual debt post the completion of the eight vessel sale. Total cash at the end of Q1 was $329 million. When we consider the various subsequent events that took place since the end of the quarter, including, for example, the $253 million of sale of NFE shares Our total cash position, including access to revolving credit facilities, stood at around $870 million. Further to that, when we take into account the value of our listed securities in NFE, Cool Company, and Avenir, we have a liquidity position of just close to $1.4 billion.

9:17 We estimate that this amount could allow us to fund two new LNG growth projects. Moving on to slide number 10, I wanted to provide a bit more color on the breakdown of our share of the distributable earnings from Healy. As a result of the higher Brent and TTF prices, our share of Healy's EBITDA almost doubled from the previous quarter, reaching $57 million in Q1 of 2022. Interesting to note that this increase of almost three and a half times when we compared to Q1 of 2021 came at no additional capex to Golar. While the base tariff stood in line with the previous quarters, we recorded an incremental $16 million from Brent-linked revenues and close to $23 million from TTF-linked earnings, already net of the swaps that we have entered.

10:17 When we assume the forward commodity prices, our share of the 2022 adjusted EBITDA from Healy remains on track to reach around $245 million in 2022. I will now hand over to Karl who can talk a bit more about that forward-looking estimate.

10:38 Thank you, Eduardo. Turning to slide 11, which elaborates on the embedded upside on the commodity exposure of Hilli's tariff. As you can see, during 2021, Golar's per rata share of Hilli's EBITDA was $99 million. This is expected to grow by two and a half times for 2022 on the back of higher Brent-linked earnings, where Golar generates $2.7 million of EBITDA for every dollar Brent is above 60. This is expected to generate about $91 million of EBITDA for 2022. Furthermore, the startup of the incremental For the full year, the TTF-linked production is expected to add $81 million in incremental revenue, where the TTF gas price exposure for Q2 and Q3 has been hedged at $25.38 per MMB2.

11:51 We remain open for Q4 TTF gas price exposure. Perenco, the charter of the unit, has a one-time three-year option to declare up to 0.4 million tons of increased production from 2023 until end of the contract in July 26 on the same TTF link tariff as the current 0.2 produced this year. The option is declarable within the end of July, and we see it as increasingly likely that Perenco will take up the option on the back of strong gas prices, but subject to the final outcome of the drilling program to tie in more reserves to Healy. We do not expect Perenco to take up the option until closer to expiry of the option in July.

12:40 The commodity exposure on HILI enable us as an LNG provider to charge significantly higher tolling fees than for traditional long-term tolling arrangements. As you can see from the boxes on the slide, the affecting tolling fee for HILI during 2021 was $3 per MMBTU. This has increased to an effective tolling fee of $13 per MMBTU during 2022. Hence the commodity exposure of our FLNG contracts, both existing and the ones we will target going forward, we see an extremely compelling risk reward. And we will continue to target similar type of structures.

13:26 Turning to slide 12 and an update on the construction of the FLNG GIME. She is now 83% technically complete for her conversion at Keppel Shipyard in Singapore. We have currently worked over 19 million man hours on the conversion. The reminder of the build is mainly around construction, installation and testing of equipment ahead of her 2023 sail away and Q4 23 startup. In light of the recent resurgence of COVID in certain parts of Asia, we continue to closely monitor and take precautions for any potential COVID impacts for the 3,500 workers on site.

14:13 We currently have no material impacts on site, and again, this is a situation we are monitoring closely, and we feel comfortable with the situation where it stands today. Turning to slide 13, and as promised earlier in the presentation, elaborating on the different FLNG designs we have available. We have developed three different designs, all based on a generic design, meaning that they will not be tailor-made to a specific field, but can be redeployed or interchanged, increasing operational flexibility and reducing residual value risk. They're also based on the same proven liquefaction topside and an extension of Golar's proven operational track record.

15:02 The Mark 1 has a liquefaction capacity of up to 2.7 million tons a year and it's suitable for stranded and associated gas resources. Both Hidli and Gimmi are Mark 1 designed FLNGs and are based on conversion of existing LNG most carriers. The Golar Gondria remains a Golar-owned conversion candidate for potential future incremental Mark I units. The Mark II design is also a conversion of an existing LNG carrier into an FLNG. However, instead of adding liquefaction equipment to the width of the ship, Mark II places the liquefaction topside on a new ship midsection added to an existing carrier.

15:49 This allows for larger liquefaction capacities of up to 3.5 million tons and reduces the conversion construction time. Hence, this is a fast track solution for somewhat larger production projects than for Mark 1. Lastly, our Mark 3 new build design is one we have worked to develop for more than a decade. Mark 3 has a liquefaction capacity of up to 5 million tons and is competitive also to larger shore-based liquefaction solutions. The lower capex per ton and lower carbon footprint, even compared to land-based solutions, make the Mark 3 a more economical, faster-to-deploy liquefaction solution for large liquefaction projects globally.

16:38 The new-built hull also allows for increased storage and leg space. So our primary focus going forward is to develop projects that suit one of these three design alternatives. On page 14, we outline why we mainly focus on floating African LNG projects when we look at our growth pipeline. When considering FLNG growth projects, there are three key input factors that drive the delivered cost for LNG. Those are source gas, liquefaction cost, and lastly, the shipping distance or shipping costs from production site to the end user.

17:26 We believe that you can develop a stable source gas price of between $1 to $3 per mmVTU, dependent on the size of the field in question, if you target African gas. This compares to current spot prices for Henry Hub's source gas, in the US, where most of incremental liquefaction projects are planned, of around $9 per MMBTU today. Secondly, as we are building a fit-for-purpose, efficient liquefaction design in Asia, Golars CapExpertone, compared to other floating or shore-based liquefaction solutions, is very competitive. Lastly, African gas, from a geographical point of view, has a shorter sailing distance to end users, whether they are in Europe or in Asia, compared to US liquefaction projects.

18:22 Hence, if you have a lower input cost, a lower capex per ton, and a shorter shipping distance, you should have a compelling competitive advantage when looking at the economics of incremental growth projects. elaborating on that on slide 15. Again, this is a familiar slide that we have presented at earlier occasions, but it gives a strong picture of the LNG value chain and the economics of an FLNG project. With source gas in Africa at around $1 per MMVTU, liquefaction cost on a tolling fee basis similar to what we charge BP on the GIME of between $2 to $3 per MMVTU, and shipping costs of around $1.50.

19:10 African FL&D projects can today deliver LNG to end users for about $5 per MMVT. If we compare that to current gas prices, these projects have a repayment of less than one year in the current market environment. This backdrop drives our FL&D project pipeline for potential charters, and also explain why Golar is focused on projects where we can get exposure to commodity prices, driving the effective tolling fees significantly higher than for long-term tolling fees, as proven by the FLNV Healy. This business model doesn't only work in a high gas price environment. On the right-hand side, we have highlighted the $5 MMBTU of landed LNG price versus historical LNG prices.

20:02 This business model makes money in most historical LNG price scenarios. However, we are strong believers that the energy and gas prices the next 10 years will be significantly higher than the previous 10 years. And hence, FLNG should be an even better business going forward than what we have seen historically. In terms of illustrative economics, a tolling fee based on a large Mark 3 5 million tons FLNG unit and a $3 tolling fee. We can generate an EBITDA of such a unit of around $750 million a year versus a capex of around $2.5 billion for such a large unit.

20:47 Integrated projects, however, using a 2.5 million ton Mark 1 design as an example and the landed gas price of $25 per MNBTU In current gas price environment, that would create an annual EBITDA of $2.5 billion to the project owners that we would target to be split between the upstream provider and the FLNG owner. So whether you go integrated or tolling, it's an attractive business. But if you believe, as we do, that we will see higher energy prices, you want to focus on integrated exposures. Turning the attention to FSRUs and the developments that we have seen in Europe year to date, we have highlighted how the FSRU market has significantly changed on slide 17.

21:42 Entering into 2022, Europe had a total of 32 import facilities, where 29 are land-based and three are FSRUs. Year to date, we have seen 22 potential FSRU projects surfacing, where eight have already secured an FSRU and 14 remains on the planning stage. This compares to a global FSRU fleet of 46 units and an estimated availability of another three to five units in total between now and 2025. So the way we see it, it's three to five units available to service up to 14 of incrementally planned FSRU projects.

22:35 We at Golar have received strong interest from several European countries for our open, modern FSRU, the Golar Tundra. Turning to slide 18, you can see that the gas price fundamentals keep on strengthening and keep on providing length. Starting on the far left, you can see the forward prices in May last year, in January this year, and the 20th of May. The point being as one thing is that the front month is constantly lifting, but we're encouraged to see The future gas price also lifting, providing further visibility for potential FLND talkers.

23:24 On the mid-side, you can see the expected liquefaction projects to come on between now and 2028. These are essentially pre-Ukraine-Russia situation liquefaction projects. and this was seen to be needed to meet a balanced LNG market going forward. On the far right, we've taken some statistics to show how meaningful the impact of the Ukraine-Russian situation may be on the need for liquefaction going forward. The global LNG market was last year 400 million tons. Russian pipeline gas exports to Europe was last year about 115 million tons, over 25% of the global LNG market.

24:18 Hence, if European countries are to make real their ambitions to replace Russian gas with international LNG, we need to see a significant ramp up, not only of regas terminals, which key focus is on right now, but gas sourcing, Keep in mind that the gas price in December was significantly higher than what it is today, even in the midst of the current situation. So this is a fundamentally tight market, pre-geopolitical shocks, and after we expect it to be significantly stronger for longer. Turning to slide 19 and a bit further background on last week's announced forward sale of the Golar Arctic.

25:06 Golar Arctic is the only remaining steam LNG carrier in our fleet. By a long model, the less competitive assets we have in our fleet. We entered into an agreement with SNAM where they will pursue a development of a virtual pipeline into Sardinia. is listed in Italy and has a market cap of around 18.7 billion euros. The transaction is a forward sale of the Arctic at 269 million euros, payable in installment at defined milestones. Our estimated conversion capex is $160 million, excluding contingencies and vessel costs, Hence, we think that by doing this measure, we have significantly high-graded the value of the ship. We found a long-term use for a steam carrier, and we leverage on the learning effects we did from a recent and similar conversion of the Golar Viking, which was sold to LNG Croatia.

26:22 Turning to corporate and slide 21, GOLA recently announced our 2021 ESG report now available on our website. We continue a very strong safety record. We improve lost time injuries. We high grade our AER data. And we're proud to say that throughout the pandemic, we have maintained a very high retention We have more than 70% of cadets still employed with us. And for senior officers, we have a retention of more than 94%. Not only is that important to keep high quality operations, it's also important to cater for future growth, especially in light of the LNG new buildings coming on stream going forward.

27:23 Turning to slide 22, highlighting the earnings potential from our existing asset portfolio. Last 12 months, we made $148 million of EBITDA. Add to that the contractual EBITDA of GIMI starting in Q4 of next year, and the commodity upside on the commodity link production from Healy, We expect our run rate EBITDA to be more than $400 million from 2024 onwards. And on a fully delivered basis, we trade at an EV EBITDA of just shy of seven times, with capacity to add at least another two FLNG growth projects just from our current balance sheet positions.

28:18 To summarize on slide 23, we are a leading owner and operator of pioneering maritime LNG infrastructure. We expect our EBITDA to quadruple in 2024 versus 2021 levels. We have cash and listed securities of 1.4 billion and fully delivered net debt of less than $300 million. We have a book value of of standing currently at 2.54 billion dollars and we are very focused on our FLNG growth pipeline going forward. That concludes our Q1 presentation and I'll now hand it over to the operator for questions.

29:06 Thank you. We will now begin the question and answer session. As a reminder, if you wish to ask a question you will need to press star 1 on your telephone. To withdraw your questions, please press the hash key. Please be advised that there is a limit of two questions per person. And the first question comes from the line of Chris Tseng from Weber Research. Please go ahead.

29:33 Hi. Good afternoon, Karl and Eduardo. How are you?

29:37 Hey, Chris.

29:38 Hey. Hi. Thanks for the question. Can you provide some Was it based on price or timing deployment or perhaps preference by Golar to unload its remaining steam vessel?

29:58 This is a project that we have developed with SNAM over a long time. It predates the geopolitical situation in Europe. I think the backdrop for their decision is the success of the LNG Croatia and the capacity needs in Sardinia and that this would be a cheaper alternative than to buy more modern tonnage for that specific project.

30:26 I see. All right. Thanks. And just to follow for that, can we think of the difference between the sale price that 269 million euros and the conversion costs for the 100 and the change. Is that the best of sale price? Is that the right way to think of it?

30:45 Sorry, you're breaking up a bit.

30:47 You said the difference between the 269 million euros and the conversion costs. Is that effectively like the best of sale price?

31:00 Yeah, that's of course one way you can put it. So if you take the difference between the due and net of outstanding debt of around $30 million, you get the and the equity balance

31:12 ownership. All right, great. Okay, thanks. And just one last quick one, just for the other three designs, the Mark 1, 2 and 3, which one could be deployed the fastest?

31:24 We're currently working on projects on a tolling fee basis for Mark 3 and on an integrated basis where we are balancing the decision between Mark 1 and 2. It's difficult to say which one comes first. Currently, it's tempting to say more of one or two.

31:46 Okay. Thanks. I'll turn it over. Thanks, guys. Thank you. Thank you. Next question comes from the line of Sean Morgan from Evercore. Please go ahead.

31:59 Hey, Karl and Eduardo. Question on the potential conversions and new FLNGs. You said that You know, net cash balance is obviously, you know, net debt balance is actually quite low. So you could potentially finance these out of cash. Would you want to do that? Or would you look at a more balanced approach to incorporate more debt? Or do you kind of look at potential expansion of LNGs as a way to sort of deleverage as you grow?

32:28 I think first and foremost, we have... Cash and Distance Securities of $1.4 billion and the company is free cash flow positive every quarter going forward based on the current performance of the group. So that means that all that money can be the project growth and around half of it is already in cash form. So I think we can fund one SLNG project just out of available cash the way we see it right now. and should we get more than one FLNG project, we could look at the listed securities position or relever on Healy and Gimme, which on average has very low leverage at the moment.

33:18 Okay. And then, you know, another question we get a lot, it's sort of difficult to gauge, is in terms of counterparties off the coast of Africa. You talked about the low to extract the gas reserves from that region.

33:53 If you think about it, we are about to start to work for BP in Africa, and we are working for Prenko in Africa. So on both of those, that explains to you who the counterparts are. In that context, it's BP and Prenko, and they are the ones interfacing with the local government. And to some extent, they're a good representation of... the different sort of opportunity sets, one of them on a fixed tolling fee to a solid counterpart for a long time, and one of them with more commodity exposure. So the way we're working this is mainly with partners with a significant presence in country, but it also explains some of the reasoning why it's a bit difficult from time to time to guide on exact timings of when projects will be sanctioned.

34:48 because we can want to have done it yesterday and so can the ChartBrew but you are reliant on governmental bodies, environmental sign-offs and upstream to be in place and that's really what's driving the timeline more than the interest from either us or the ChartBrew.

35:09 Okay, yeah, and so beyond your two existing counterparties, though, is there like, you know, five to six other EMPs that are working in that region, or is it more limited scope of potential partners?

35:21 That's a fair statement that you have several other guys operating in that area. You have a lot of proven and associated gas reserves, and in this market, that's a waste of resource.

35:32 Okay. All right. Thanks, Karl. Thank you. Thank you. Next question comes from the line of Ben Nolan from Stiefel. Please go ahead.

35:43 Yeah, thanks. So I guess I'll start again on the FLNG side. You know, there's been – you guys have been working on this for a while. And maybe could you just characterize what the conversations are like today with your customers versus maybe a year ago? There's obviously been some thought that there would be some positive developments, but there haven't been any major incremental ones in the last number of years. So how do you think now is different, I guess, is the question.

36:18 I think what's happened, this is mainly currently a driver of the gas fundamentals and the fact that the gas market is tight. You just see the amount of interest. When the gas price is high, the economics for these projects is significantly better. And that's what drove the incremental increase in interest the first six, well, up until the Russia-Ukraine situation. After the Russia-Ukraine situation, you've seen first a massive scramble from Europe to secure FSO use. Now they're slowly moving into the LNG carrier market, and you can see term rates almost being doubled at the spot rate, even as we enter into the soft part of the year, because Europe is scrambling to secure energy security.

37:08 And then ultimately, they now understand that the market was tight. They have created the import terminals, but they haven't got their hands on the hydrocarbons.

37:17 So you now see a lot of these countries leading the way.

37:23 You've seen the likes of Germany first go to Qatar, then to US, and yesterday they announced that they think West African gas is a significant part of Europe's energy solution. So that's coming, and with the European countries, you can more easily secure offtake and financing than you could pre the Russia-Ukraine situation.

37:50 Okay, so people seem to be more serious. Is that sort of the takeaway here?

37:59 The economics are better, and the financing and off-stake are more available than ever.

38:05 Okay. And then for my second question, I might flip in a twofer on this one. So you talked primarily about Africa, and you gave the illustrations about Africa, although In the past, you guys have talked about other regions like the Middle East, the Mediterranean, different other places. Are those still on the table, first of all, or are they substantially behind it? And then for part number two, you talked about being able to fund two incremental units. But a Mark III, the cost is substantially different than a Mark I. So is that assuming like one Mark III and one Mark I, or how should we think about how you're thinking about two units?

38:43 First part of your question is... Yes, it's also other geographies than West Africa. That's why we say mainly African gas, because we see the attractions of the input and the distance. But there are other areas, for example, in the Middle East, where the gas is essentially free. So that's obviously still part of the project and the considerations or development. But we are focused mainly on African, but there are other projects as well, both in the Middle East and elsewhere. Sorry, the second part of the question.

39:23 Oh, just how to think about when you say you can internally fund two projects, Mark I versus Mark II, or a combination.

39:32 If you take the Catholics on these, you have, of course, you can source debt fundings. So if you take the example of Hilly, for example, when we built that one, it was a $1.4 billion capex, and we had $960 million of debt available. So that's a $500 million equity check. And with a $1.4 billion cash-invested securities balance and a free cash flow to equity positive operation, we can fund it through balance sheets. When it comes to the larger assets, you can typically get yard financing, which you can not as easily get for conversion.

40:17 Okay, so when you talk about self-funding two of these, it's one of each. Is that how to think about it?

40:27 We will take the project that we think makes the best economics. If that's two Mark IIs or one Mark III and a Mark I, remains to be seen when we announce the project.

40:39 Okay. But just two in general, that's the capacity is the takeaway. Okay.

40:46 We can comfortably come to you from the current balance sheet and the rest is a timing thing. So we all generate cash flow pretty much every day. So it depends on the timing of when further units be on those two. But I think If we double the FLMV fleet, we can look at our situation at that point. But for now, the focus is on getting to the next two.

41:10 Yeah, absolutely. All right. I appreciate it. Thank you.

41:13 Thank you. Thank you. Next question comes from the line of Craig Lewis. Please announce your company name.

41:22 Yeah, hi. Thank you, and good afternoon, everybody. Hi, Craig. Karl, I was hoping you could comment a little bit on the ongoing drilling campaign you highlighted in the press release and the well testing that's going on in West Africa. And really what I'm curious about, and maybe it's a little bit of both, is the driver or the customers doing those drilling campaigns, Is that going to potentially lead to more volumes for the hilly, or is it potentially going to lead to maybe an extension on the hilly with Perenco?

42:12 It's a good question, and it's kind of yes to both. The primary purpose of the drilling campaign, we understand, is to tie in more proven reserves so that you increase the gas flow and enable the 0.4 million in increased production. What we have very clearly publicly stated, both to the market and of course to Perenco and SNH, the governmental body in Cameroon, is that we will not enter into extension discussions until they declare that point four because currently we of course have paid for equipment that's not fully utilized and every incremental production is straight through to net income or free cash flow to equity if you like and we don't want to be working on any extensions until we better utilize the equipment already in place.

43:12 But, you know, if you find substantial gaps, that should lead to extension discussions as well. But for us, it's sort of you have to tackle one obstacle at a time. And for us, it's the increased production that's the key driver on Haley right now.

43:28 Yeah, perfect. Thank you for that. And then, you know, realizing that we were selling the steam of the Arctic, you know, obviously you're highlighting the tundra and the opportunities for the tundra. I guess a two-part question there. One is, as we think about the path forward for the Tundra, is that more around an asset sale or could we potentially just see that be contracted and remain a core part of the fleet? And just piggybacking on that question, are there opportunities for Golart to expand its FSRU footprint?

44:11 Okay, so the first part of your question. At the beginning of this year, there were several FSRU projects being worked, none of them in Europe. I think with what happened in the geopolitical situation, as we tried to highlight on the slide, the incremental increase in new FSRU projects out of Europe is unprecedented. and on the balance we are very confident that that unit will end up in Europe and not elsewhere. If you look at what's communicated by the various governments in Europe some of them are targeting and chartering opportunities and some of them are targeting acquisition of units. I think for us we remain agnostic whether we sell or charter.

45:03 We will do what we think caters for the best risk-adjusted economics. And that's our target. And with the amount of interest and the specification of Tundra, we feel very comfortable about that situation. When it comes to the second part of your question, what we want to focus on going forward is FLNG projects because we think we have a unique competitive edge. and we still think that the economics of SLNG projects is the most compelling in the LNG value chain, at least for the next decade or so. However, we have no non-compete with any of the corporate transactions that we have concluded over the last 12 months and should there be an attractive SSRU project coming up, there's no reason why we should not take it on. However, I would highlight that our focus is LNG growth.

46:01 But we remain open to anyone who wants to talk to us for any attractive LNG infrastructure business.

46:10 Perfect. Hey, thank you for the caller, everybody. Have a great day. Thank you. Thank you. The next question comes from the line of Craig Shear from 2E Brothers. Please go ahead.

46:24 Hi. Thanks for taking the questions. So, besides the GANDRIA that you already have, how do you see availability of vessels for acquisition for additional Mark I or Mark II conversions? And do you have any thoughts about timing an announcement of a full 2.4 MTPA deployment of the HILI post your mid-2026 PRANCO contract expiration? Okay, hi Craig. So when you talk about source vessels for Mark 1 or Mark 2, those will most likely be based on a MOS design carrier, so the one with the bowls on top.

47:11 Those carriers are mainly steam carriers that will face significant operational challenges due to the new environmental regulations from 1st of January. So basically the new EXI and CII regulations. Hence, these ships will be less suitable to operate as LNG carriers and more suitable for floating storage jobs or as conversion candidates, whether for FSRU or FLNG. Because of the amount of those ships that will become less competitive for shipping and therefore need to find alternative work, With a limited amount of companies with a track record of successfully redeploying or recharacterizing those type of ships, we're confident that there will be abundant vessels available for conversion candidates.

48:13 To the second part of your question, when it comes to HILI, I think we always try to do A before we do B before we do C and so forth, and for us, The next step on HILI is to secure the 0.4 million tons in July of this year. After that, I think it's for sure in Perenco and Cameroon's government to try to find solutions to keep that unit in country. For both of them, this has been a massive economical success, and we think both of them have an interest in keeping the unit in country. on the other hand I think the operational track record and the fact that the unit has no construction risk and lastly that is very soon the quickest FLNG you can get your hands on internationally we think that in this gas price environment her attractiveness for potential work outside of Cameroon is increasingly attractive by the day so to try to give some guidance on when we think we have development there, we would say it's hard to probably up to 12 months after the point four so by summer next year or so in that time period.

49:34 Great. And one last question on FLNG negotiations for new projects. I think we all understand that the upstream, you know, producers are your counterparties, but how many upstream producers have in Africa have set in stone relationships as far as royalties, profit sharing, what have you, with the host governments, and to the degree there's a major upsizing of a play with with, you know, say your FLNG, does that reopen these things and make very complicated discussions where obviously the host governments want to get as much value from the current market as possible?

50:34 That's an extremely qualified question. And I think you're touching upon parts of the core of why the reason some of these projects It's a bit difficult to guide on exactly when they will happen. I think it's fair to say that neither us nor any upstream partners would enter into such projects without very clear agreements with host governments on these specific points that you touched on, like the agreements on how things should be shared, flexibility and so forth. This is basically the the key gating item in terms of timeline for the new FIDs. The flip side of the argument is that these are stranded gas reserves that are proven and no one has the technology to monetize those fields.

51:27 That's what we cater for and today we don't see anyone else doing XLNG or floating liquefaction as a service with a proven track record at least. Therefore, I think we are the solution in terms of monetizing the unit and it's a matter of finding a fair framework that works for the government, the upstream partner and for us. Great, thank you. Thank you. Next question comes from the line of Chris Robertson from Jefferies. Please go ahead.

52:11 Hey, good morning, Karl. Thanks for taking my question. I apologize in advance. It's a little mundane. But on the NFE shares, how are you guys thinking about those in terms of are you just wanting to hold them until you need to monetize ahead of a new FLNG project? Or what's the thinking there?

52:28 And that's a good question, Chris. So I think, as you know, we got 18.6 million shares in total consideration when we sold the share component of the consideration. Earlier in May, we sold one-third of that holding, freeing up $253 million. We like the development of NFE. We like the direction they are taking the company. However, we have no lockup and no board sit and no access to any non-public information. Hence, we're pretty much free to do what we want with that shareholding. The way we see it now, it's far better to sit NFE than to sit cash. And we have significant balance sheet flexibility to fund at least one LNG project without touching that facility. I'm sorry, those shares.

53:24 And for now, we are holders of the name.

53:29 Okay. Is there any room for, I guess, a greater partnership with New Fortress now that they're getting into some floating LNG with offshore rigs? Any expertise that you could offer or discussions there?

53:44 I think I've disclosed by NFC and Wes Edens on his earnings calls. We are, as Goal are, working together with NFC, helping them out to develop their fast LNG solution. both on the engineering side and also on the operational side. Keep in mind GOLAR still operates all of the maritime assets like the ships and the FSUs that we sold to NFE. So we have a good working relationship on sort of all levels of the organizations. There's currently no specific plans but I think we would certainly be open to working together when the right opportunities arise.

54:34 Got it. Yeah, I appreciate the time and thanks for the thoughts on that, Karl.

54:38 Thank you. Thank you. Next question comes from the line of Nick Linan from Sefton. Please go ahead.

54:49 Hi. Thanks for taking my question. How many yards are there that you think can do Mark 1 or Mark 2 conversions? And how many do you think could do Mark 3 new builds? And do you have any guaranteed slots for either of those types of work? And if so, like when you have options on those slots until, because it seems like the yards are getting quite busy now.

55:17 that's a very correct observation the yards are getting extremely busy so to some extent that's a bit of an unusual situation for I think anyone in the maritime space we haven't seen that since sort of the 2006 to 2008 cycle but then again the yard capacity has been built down significantly since then and then the resurgence in activity has caused longer lead times and obviously the general supply squeeze globally but To answer your question, on March 3, we think it's essentially one shipyard that we think is up to the part. And on that one, we are in detailed discussion about securing slots.

56:04 The way the shipyards think about things is that they are, of course, selling most of the capacity to fairly aggressive LNG Carrier and Container Orders, but they are saving some space for what they call large offshore infrastructure projects. They have learned over time, as most other people have, that the shipping markets are cyclical and it's not wise of them to build down engineering and offshore capabilities because you never know when they are in demand and when that ramps up activity. So they are saving some slots for larger projects, but it's a limit to how long they hold the slots, given the pressure on container and LNG carrier orders. That said, I think we have long-standing relationships with the key yards in question, and we are currently working to secure slot options for Mark 3s. When it comes to Mark 1s, we have built a temple in Singapore and we think that's the best shipyard to build Mark 1s.

57:07 We haven't not explored others and we have no intention to explore others for Mark 1s either. When it comes to Mark 2s, that's considered to be done at a different shipyard from both Mark 1s and Mark 3s. So basically we have one select shipyard we've been working on for quite some time on Mark 2 and 3 and we're already having a very established relationship with Keppel on Mark 1.

57:36 Okay, thanks for the detailed answer. Thank you. There are no more questions at this time. I would like to hand back over to Karl Staubo for final remarks.

57:50 Thank you all for listening in and for good questions and we look forward to connecting with you next quarter. Have a great day. That does conclude our conference for today. Thank you for participating. You may all disconnect.

Follow Golar LNG Limited into a list and get an email when it puts out news.

Latest news releases

Companies on this call

Speakers

Craig Lewis

Analyst

Ben Nolan

Analyst, Stifel

Craig Shear

Analyst, 2E Brothers

Chris Robertson

Analyst, Jefferies

Karl Fredrik Staubo

CEO

Sean Morgan

Analyst, Evercore

Eduardo Maranhao

CFO

Chris Tseng

Analyst, Weber Research