Slide 1: Lehman Brothers CEO Energy/Power Conference
Lehman Brothers CEO Energy/Power Conference Bruce Williamson September 2, 2008 Investor & Public Relations | Norelle Lundy, Vice President | Nir Grossman, Senior Director | 713-507-6466 | [email protected]

Slide 2: Forward-looking Statements
Forward-looking Statements This presentation contains statements reflecting assumptions, expectations, projections, intentions or beliefs about future events that are intended as “forward-looking statements.” You can identify these statements, including those relating to Dynegy’s 2008 financial esti

Slide 3: Trailing 12-Month Trends
Trailing 12-Month Trends $160 Crude Oil ($/Bbl) Natural Gas ($/MMBtu) $14 $140 $12 $120 $10 $100 $8 WTI - Crude Henry Hub $80 $6 $60 $4 $40 $2 $20 0 S O N D J F M A M J J A S O N D J F M A M J J A Power ($/MWh) Electric Utility & IPP Averages $100 120% Utilities 110% $80 100% $60 90% 2009 CIN Hub On

Slide 4: Why Invest in Dynegy?
Why Invest in Dynegy? If you are worried about… … consider Dynegy’s belief … and Dynegy’s advantages Demand growth is expected to continue over the longer term as Dynegy is well positioned to capture growth Supply/demand industry fundamentals remain strong in 3 economic regions balance Barriers to e

Slide 5: Electricity Market Growing in an Uncertain Environment
Electricity Market Growing in an Uncertain Environment Two major trends are colliding with a constant Global competition for energy Rising U.S. energy consumption Rising barriers to entry Global oil, natural gas/LNG, Eastern coal and power have experienced a step-change in price Electric forward cur

Slide 6: Barriers to Entry Remain High
Barriers to Entry Remain High New Generation – Estimated Costs and Lead-Time Concentrate $4,600 – 6,800/KW Solar Photovoltaic $8,000 – 12,000/KW Wind $2,000 – 2,200/KW Delays will increase Simple Cycle $700 – 1,100/KW the value of Gas Combined Cycle $900 – 1,500/KW Dynegy’s existing operating assets

Slide 7: Regulatory Uncertainties
Regulatory Uncertainties Successful U.S. energy policy must address 3 critical, interrelated issues: Prior focus: SOx, NOx, mercury, particulates The New focus: Environment climate change Price of Electricity Federal Leadership The U.S. Energy Economy Dependence Cost to consumers Price of Global oil

Slide 8: Dynegy's Carbon Emission Profile
Dynegy’s Carbon Emission Profile As a general rule: Coal facilities produce 1 MM tons of CO2 per 1 MM MWh of generated volumes Gas-fired facilities produce 1 MM tons of CO2 per 2 MM MWh of generated volumes West Capacity Midwest Capacity Northeast Capacity Combined Cycle Combined Cycle Combined Cycl

Slide 9: Hypothetical Midwest Carbon Cost Example
Hypothetical Midwest Carbon Cost Example Carbon Cost Scenarios – Possible Impacts to Dynegy’s Midwest Fleet 2007 Midwest Generation = 25 MM MWh 2007 Midwest CO2 Emissions = 25.6 MM tons Natural gas Potential cost of CO2 per ton increases 24 set by new regulation $/MMBtu $/MWh $/MWh increase in power

Slide 10: Current Market Creates Opportunities for Dynegy
Current Market Creates Opportunities for Dynegy CIN Hub On-Peak Prices ($/MWh) Power prices have risen $90.00 (1) significantly year-over-year, Cal 09 Prices $85.00 despite near-term volatility We are focused on “Current + 1” Cal 09 Current Avg(1) $74.23 $80.00 commercial strategy $75.00 We’re activ

Slide 11: Managing Supply Contracts Offers Advantages
Managing Supply Contracts Offers Advantages 2008 Coal Prices ($/MMBtu) $7 $6 South American Market prices of Eastern $5 and South American coal $4 exclude cost of delivery Eastern $3 $2 DYN PRB Delivered Price = $1.39 Dynegy’s delivered PRB $1 price includes benefit of Powder River Basin Source: Ene

Slide 12: Why Invest in Dynegy?
Why Invest in Dynegy? Geographic Diversity Dynegy’s Competitive Advantages: Northeast Midwest 21% Geographic diversity means Dynegy is well- 46% positioned in 3 key regions West 33% Dispatch diversity includes both baseload generation, which provides today’s core earnings, Fuel Diversity as well as

Slide 13: We Believe Dynegy is Significantly Undervalued
We Believe Dynegy is Significantly Undervalued Implied Price per Share based on Asset Valuations Sandy Creek ~$2,600/KW Plum Point ~$2,800/KW Coal/Dual Fuel Asset Value ($/KW) Gas/Oil Asset Value ($/KW) 1,500 1,750 2,000 2,250 2,500 2,750 Calcasieu Peaker ~$160/KW 150 $ 3.75 $ 4.79 $ 5.84 $ 6.89 $ 7

Slide 14: Appendix
Appendix Investor & Public Relations | Norelle Lundy, Vice President | Nir Grossman, Senior Director | 713-507-6466 | [email protected]

Slide 15: Diverse Portfolio Provides Advantages
Diverse Portfolio Provides Advantages Geographic Diversity Fuel Diversity Dispatch Diversity Northeast Combined Cycle Midwest 21% 33% Peaking Baseload 46% 45% 22% Simple Cycle Fuel Oil 36% 7% Total Gas-fired Coal West 69% 24% 33% Intermediate 33% 18,277 MW Located in 13 states – serving regions that

Slide 16: Guidance
As presented August 7, 2008 Guidance 8/7/2008 ($MM) Guidance(1) Adjusted EBITDA $955 Interest payments (430) Cash taxes (15) Collateral (15) Working capital / non-cash adjustments / other 15 Adjusted cash flow from operations $510 Maintenance capital expenditures (170) Environmental capital expendit

Slide 17: Midwest Generation
Midwest Generation Regional Market Drivers MISO – Outright power price for uncontracted baseload volumes, and spark spread for uncontracted gas-fired peaking units PJM – Spark spread for uncontracted gas-fired combined cycle units Capacity markets – MISO capacity sold under bilateral agreements; PJM

Slide 18: Midwest Power Market – Basis Differentials
Midwest Power Market – Basis Differentials Transacting further east PJM provides more liquidity… Illinois Hub CIN Hub …and creates additional risk Dynegy uses forward power Average Day-Ahead On-Peak Prices ($/MWh) contracts to optimize assets 140 CIN Hub IL Hub PJM Hub Traditionally the differences

Slide 19: Midwest Power Market – Basis Differentials
Midwest Power Market – Basis Differentials Basis Differential Examples ($/MWh) Note: For all examples, the assumed basis differential on the contract date is $10, as differential moves away from $10 results are affected Real-time Year Ahead Forward Power Sale Sale Forward Settlement @ Basis @ Physic

Slide 20: West Generation
West Generation Regional Market Drivers Spark spread for uncontracted gas-fired combined cycle and peaking units, and ancillary services California has no formal capacity auction market; greater demand is expected for capacity in 2009 as utilities will have reduced Resource Adequacy requirements Reg

Slide 21: Northeast Generation
Northeast Generation Regional Market Drivers NYISO – Spark spread for uncontracted combined cycle gas and fuel oil units, and outright power price for uncontracted baseload coal volumes ISO-NE – Spark spread for uncontracted combined cycle gas units New England – formal capacity market auction for 2

Slide 22: Assumptions For Hypothetical Midwest Carbon Cost Example
Assumptions For Hypothetical Midwest Carbon Cost Example Assumptions based on hypothetical variables, which are dependent on a variety of factors including market conditions and future environmental regulations Actual results may vary materially from these assumptions (1) CO2 emissions and generatio

Slide 23: Linking Commercial with Capital Strategies
Linking Commercial with Capital Strategies Maintaining a Solid Foundation in a Cyclical Business Focus on Maintain Keep Respond to Recognize discipline Continuously core options change with the cycles throughout evaluate business open the right cycles option At Dynegy, this means: Debt Maturity Prof

Slide 24: Debt and Lease Obligations ($ MM)
Debt and Lease Obligations ($ MM) $8,000 Increase in debt and lease obligations since $6,743 $6,813 $6,839 December 31, 2007 primarily reflects the following: Draw of $111 million on Plum Point construction loan $6,000 Repaid $21 million on Sithe Energies Senior Debentures $4,000 $2,000 $0 12/31/07

Slide 25: Central Hudson Lease – Northeast Segment
Central Hudson Lease – Northeast Segment Central Hudson Cash Payments Imputed Debt Equivalent at PV(10%) remaining as of 6/30/08 ($MM) of future lease payments = $776 MM(1) 200 $179 Imputed Interest 175 Imputed Debt Equivalent $48 150 $141 $142 $143 $143 $16 $112 $28 125 $113* $38 $67 $105 100 $95 $

Slide 26: Debt & Other Obligations Capital Structure – 6/30/08
Debt & Other Obligations Capital Structure – 6/30/08 ($ MM) Dynegy Inc.. Key: Secured = $919 Dynegy Holdings Inc. Secured Non-Recourse = $897 $1,150 Million Revolver(1) $0 Unsecured = $5,023 Term L/C Facility $850 Tranche B Term $69 Sr. Unsec. Notes/Debentures $4,047 Sub.Cap.Inc.Sec (“SKIS”) $200 Si

Slide 27: Liquidity ($ MM)
Liquidity ($ MM) $2,400 $2,000 $1,706 $1,600 $1,449 $1,485 $794 $1,200 $1,056 $890 $800 $1,121 $619 $400 $912 $328 $429 $271 $0 12/31/07 3/31/08 6/30/08 8/1/08 Cash Availability Standby facility (1) Liquidity excludes $28 million cash posted as collateral as of June 30, 2008 Liquidity decreased from

Slide 28: Enhancing Flexibility with Liquidity Options
Enhancing Flexibility with Liquidity Options Complementary sources of liquidity increase our flexibility and ability to execute our commercial strategy in a rising commodity price environment Current Liquidity Remains Strong with Traditional Facilities Cash on hand (as of 6/30/08) $271 million Revol

Slide 29: Significant Environmental Progress
As presented February 27, 2008 Significant Environmental Progress On target to further reduce emissions in the Midwest 2007 2008 2009 2010 2011 2012 Vermilion Hennepin Havana Baldwin 3 Baldwin 1 Baldwin 2 Major Assumptions Cost Composition Estimate of remaining spend is $850 – $900 million for a tot

Slide 30: Anticipated Capital Expenditures (2008 – 2012)
As presented August 7, 2008 Anticipated Capital Expenditures (2008 – 2012) ($MM) 2008 2009 2010 2011 2012 Maintenance $ 170 $ 210 $ 245 $ 220 $ 190 Environmental 200 265 225 185 100 Development (Plum Point) (1) 220 110 110 - - Discretionary Investment (target IRR 15% or more)(2) 30 40 10 - - TOTAL $

Slide 31: Development Detail
Development Detail Development JV Joint venture not consolidated as we are not the primary beneficiary of the earnings and losses of the JV Proportionate share of earnings and losses recorded in earnings from unconsolidated subsidiaries in our financial statements Several thousand megawatts of green

Slide 32: Reg G Reconciliation – 2008 Guidance
Reg G Reconciliation – 2008 Guidance 2008 EARNINGS ESTIMATES (1) (IN MILLIONS) Power Generation GEN - MW GEN - WE GEN - NE Total GEN OTHER Total Net Loss $ (30) Add Back: Income tax benefit (20) Interest expense 430 Depreciation and amortization expense 380 EBITDA (2) $ 655 $ 144 $ 70 $ 869 $ (109)

Slide 33: Generation Assets – Midwest & Northeast
Generation Assets – Midwest & Northeast Net Primary Dispatch Region/Facility (1) Location Capacity (2) Fuel Type Type Region MIDWEST Baldwin Baldwin, IL 1,800 Coal Baseload MISO Havana Units 1-5 Havana, IL 228 Oil Peaking MISO Unit 6 Havana, IL 441 Coal Baseload MISO Hennepin Hennepin, IL 293 Coal B

Slide 34: Generation Assets – West & Notes
Generation Assets – West & Notes Net Primary Dispatch Region/Facility (1) Location Capacity (2) Fuel Type Type Region WEST Moss Landing Units 1-2 Monterrey County, CA 1,020 Gas - CCGT Intermediate CAISO Units 6-7 Monterrey County, CA 1,509 Gas Peaking CAISO Morro Bay (6) Morro Bay, CA 650 Gas Peakin
Source: SEC EDGAR · 8-K filed Sep 2, 2008
More decks from Dynegy Inc
FY2017 Earnings Presentation30 slides · Feb 26, 2018
Debt Investor Presentation (December 2017)10 slides · Dec 11, 2017
Merger or Acquisition (October 2017)28 slides · Oct 31, 2017
Debt Investor Presentation (October 2016)44 slides · Oct 3, 2016
IPO Roadshow (June 2016)17 slides · Jun 15, 2016
Investor Day (April 2014)94 slides · Apr 11, 2014