Enka Insaat ve Sanayi A.S. · BIST:ENKAI
Enka Insaat ve Sanayi A.S — Q3 2013 Earnings Presentation
52 slides from Enka Insaat ve Sanayi A.S's earnings presentation, 2013

Slide 1: — J ——s Z
in) ~~ — J ——s Z ™ -~ a Bet “Engine Sng fa tter Future”

Slide 2: Introduction
INTRODUCTION 56 Years of Construction Experience Worldwide A Group of Companies Composed of More Than 50 Subsidiaries Operating in 6 Major Geographical Areas: CIS, Asia, Middle East, Europe, Africa & Turkey Successfully Completed 455 Projects in 42 Countries, with Historical Value of US$ 37 Bi

Slide 3: Capabilities & Operations
CAPABILITIES & OPERATIONS With a Solid Background of 56 Years ENKA Operates in 4 Main Segments Engineering & Construction Energy Real Estate Trade & Manufacturing 3

Slide 4: Milestones
MILESTONES 1957 – Founded as a Limited Liability Partenership as Şarık Tara & Sadi Gülçelik ENKA Limited Şirketi 1962 – Focused on Design, Engineering and Construction Activities of Industrial Plants, Buildings and Infrastructure 1967 – The Partnership Was Transformed into a Joint Stock Company as E

Slide 5: Milestones (Cont'd)
MILESTONES (Cont'd) 1983 – ENKA Sports, Education and Culture Foundation and Sadi Gülçelik Sports Center Establishments 1984 – First Natural Gas Combined Cycle Power Plant in Turkey 600 MW Trakya CCCP 1986 – Multinational Joint Ventures 1986 – Outstanding Achievements with Fast-Track Projects in Lib

Slide 6: Milestones (Cont'd)
MILESTONES (Cont'd) 2000 – Power Generation as Independent Power Producer (IPP) 2001 – Certified by BSI for ISO 9001 Quality Management System 2002 – Merged with Enka Holding, Enka İnşaat ve Sanayi A.Ş. As Principal 2002 – Certified by BSI for ISO 14001 Environmental Management System and OHSAS 1800

Slide 7: Milestones (Cont'd)
MILESTONES (Cont'd) 2010–ENKA Set a New World Record For Power Plant Availability (with 99,8% which is 7% Over the Industry Average) over The 12- Month Period with GE 9 FA Gas Turbines 2011–First Contract Awarded in Continent America – New US Embassy Compound in Santa Domingo, Dominican Republic 201

Slide 8: Vision and Values
VISION AND VALUES The Following Vision and Values Define What is Meant to be ENKA. - Excellence - Innovation - Speed - Safety - Being a Good Member of the Community - Its People 8

Slide 9: Shareholder Structure
SHAREHOLDER STRUCTURE 31,56% 50,08% TARA FAMILY 12,41% ENKA FOUNDATION 5,95% FREE FLOAT GÜLÇELİK FAMILY As of December 31, 2012 9

Slide 10: Consolidated Financial Highlights
CONSOLIDATED FINANCIAL HIGHLIGHTS ( Million USD ) 30.09.2013 2012 2011 2010 TOTAL ASSETS 8.124 8.238 7.460 7.115 TOTAL EQUITY 5.394 5.099 4.533 4.172 CASH & MARKETABLE SECURITIES 2.658 2.707 2.164 1.969 REVENUE 4.954 5.746 5.037 4.596 EBITDA 818 729 857 788 EBITDA MARGIN % 16,5 12,7 17,0 17,1 NET PR

Slide 11: Revenues by Business Lines
REVENUES BY BUSINESS LINES 30.09.2013 31.12.2012 31.12.2011 ( Million USD ) USD % USD % USD % CONSTRUCTION 1.836 37,1 1.384 24,1 993 19,7 POWER GENERATION 2.556 51,6 3.653 63,6 3.266 64,8 REAL ESTATE 355 7,2 442 7,7 407 8,1 TRADE & MANUFACTURING 353 7,1 395 6,9 458 9,1 ELIMINATION (146) (2,9) (128)

Slide 12: EBITDA by Business Lines
EBITDA BY BUSINESS LINES 30.09.2013 31.12.2012 31.12.2011 ( Million USD ) USD Margin USD Margin USD Margin CONSTRUCTION 303 16,5 125 9,0 259 26,1 POWER GENERATION 213 8,3 267 7,3 272 8,3 REAL ESTATE 255 71,9 308 69,7 306 75,1 TRADE & MANUFACTURING 41 11,5 23 5,8 27 5,9 12

Slide 13: Top Management
TOP MANAGEMENT BOARD OF DIRECTORS M.Sinan Tara Chairman of the Board Haluk Gerçek Vice Chairman of Board Erdoğan Turgut Member of Board (Non-executive Member) E. Melih Araz Member of Board (Non-executive, Independent Member) V. Ergin İmre Member of Board (Non-executive, Independent Member) EXECUTIVE

Slide 14: Work Force
WORK FORCE As of Technical Administrative Workers Total September 2013 Staff Staff ENKA Istanbul 328 113 66 507 Head Quarters ENKA Subsidiaries 794 614 2.103 3.511 in Turkey ENKA Construction Abroad 2.033 1.066 18.146 21.245 ENKA Construction 266 156 745 1.167 Subsidiaries Abroad Total 3.421 1.949 2

Slide 15: Engineering & Construction
ENGINEERING & CONSTRUCTION Specifically in O&G&PC Industry, ENKA Provides Engineering, Fabrication Construction, Commissioning and Start Up Services for Major Internatioal Clients Such as; Exxon Mobil, Shell, Chevron, Lukoil etc. ENKA has also Solid Relations with Leading OEMS & Extensive Experience

Slide 16: Resources
RESOURCES ENKA Owns a Construction Machinery & Equipment Fleet Comprising of 3.740 Pieces Worth of USD 314 Million; and 800.000 Square Meters of Site Facilities (Work Shops, Camps, Warehouses, Offices and etc.) Mobilized in Different Countries where Fabrication and Construction Works are Being Perfo

Slide 17: Awards
AWARDS ENKA’s 411MWe CCPP Yajva State District Power Plant EPC Project has been Awarded “The Best Project in the Power/Industrial category” in 2013 Global Best Projects Competition of ENR (Engineering News- Record) ENKA’s Kosovo Motorway EPC Project (Sections 1,2,3 & 4a) has been Awarded “The Be

Slide 18: Certificates
CERTIFICATES ISO 9001: 2008 ISO 14001: 2004 OHSAS 18001: 2007 QUALITY MANAGEMENT SYSTEM ENVIRONMENTAL MANAGEMENT SYSTEM HEALTH & SAFETY MANAGEMENT SYSTEM ASME S ASME A ASME U ASME U2 POWER BOILERS POWER BOILER ASSEMBLIES PRESSURE VESSELS ALTERNATIVE RULES FOR PRESSURE VESSELS 18

Slide 19: Certificates (Cont'd)
CERTIFICATES (Cont’d) ASME Nuclear NPT STAMP ASME Nuclear NA STAMP ASME Nuclear NS STAMP EnBW KTA 1401 's Nuclear Certificates 19

Slide 20: Engineering
a ee ———— | | ENGINEERING

Slide 21: Backlog as of 30.09.2013
BACKLOG AS OF 30.09.2013 COUNTRY (Million USD) % IRAQ 1.136 32,5 US EMBASSY PROJECTS 487 13,9 RUSSIA 402 11,5 OMAN 343 9,8 GABON 237 6,8 TURKEY 230 6,6 UNITED STATES 228 6,5 LIBYA 171 4,9 KAZAKHSTAN 74 2,1 AUSTRALIA 67 1,9 SAUDI ARABIA 19 0,5 OTHER 98 2,8 TOTAL 3.494 100 21

Slide 22: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Erbil Combined Cycle Power Plant Project – Erbil, Iraq Sulaymaniyah Combined Cycle Power Plant Project – Sulaymaniyah, Iraq Dohuk Combined Cycle Power Plant Project – Dohuk, Iraq Lukoil Power Plant Project – Basra, Iraq ME&I Works, First Commercial Production Pro

Slide 23: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Ufa Medical Center Project – Ufa, Russia Engineering Contract of Trans Anatolian Natural Gas Pipeline Project (TANAP) Morine-Merdare Motorway Project – Kosovo Development of Muscat International Airport Project – Muscat (MC3), Sultanate of Oman Presidential Palac

Slide 24: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Combined Cycle Power Plant Projects – Erbil, Sulaymaniyah and Dohuk, Iraq Job Owner: MGH - Mass Group Holding Ltd. Scope: To Convert its Erbil Independent Power Project (IPP) from Simple-Cycle to Combined-Cycle Technology. The Project is on an EPC basis. Erbil Ga

Slide 25: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Lukoil Power Plant Project – Basra, Iraq Location: Basra / Iraq Client: Lukoil Mid-East Limited and South Oil Company of Iraq Engineering, Procurement, Construction and Commissioning of 6x42 MW Simple Cycle Power Generation Plant Plant will Supply Electrical Powe

Slide 26: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION ME&I Works, First Commercial Production Project – Basra, Iraq Client: Shell Iraq Petroleum Development B.V. (SIPD) The Majnoon Oil Field is One of the World's Richest Oil Fields with Proven Reserves of 12,8 Billion Barrels of Oil, and the Estimate of Potential Re

Slide 27: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Al Najybia 4x125 MW Gas Turbine Power Plant Project – Basra, Iraq Located in Basra, Iraq Contract Price: USD 237 Million The Project is in the Scope of “Mega Deal Projects” by Ministry of Electricity of Iraq. Engineering, Procurement, Construction, Commissioning

Slide 28: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION US Embassy Projects – Afghanistan, Dominican Republic, Papua New Guinea, Russia, Equatorial Guinea The Netherlands and Mauritania The Collaboration between ENKA and CADDELL Construction Co. of USA Started in Early 2000’s Companies Agreed to Jointly Carry Out the

Slide 29: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Berezovskaya Coal Fired Power Plant, Mechanical Erection Works Krasnoyarsk, Russia End Customer: OJSC “E.ON Russia” EPC Contractor: Energoproekt ENKA is Mechanical Erection Works Contractor for the Construction of the 800 MW Berezovskaya Coal Fired Power Plant Pr

Slide 30: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Khabarovsk Refinery Structural Steel and Mechanical Erection Works Khabarovsk, Russia Expansion of the Existing Refinery, which was Built During the 1930’s. The Scope of Works Include the Erection of Several Main Units, which are the New Combined Hydrocracking an

Slide 31: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Engineering Contract of Trans Anatolian Natural Gas Pipeline Project (TANAP) Trans Anatolia Natural Gas Pipeline (TANAP) Project Will Transport The Natural Gas to be Produced in Shah Deniz 2 Field and Other Fields of Azerbaijan through Turkey to Europe. Memorandu

Slide 32: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Morine-Merdare Motorway Project – Kosovo BECHTEL – ENKA General Partnership ( 50% - 50% ) The Contract Price : EUR 824 Million (Inc. VAT) Starting from Vermice on the Albanian Border, Reaching Merdare on the Serbian Border and Connecting the Southwest of Kosovo t

Slide 33: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Development of Muscat International Airport Project (MC3)– Muscat, Sultanate of Oman Consortium of BECHTEL – ENKA Joint Venture with Bahwan Engineering Company The Contract Price : USD 1,8 Billion ( ENKA’s Share = USD 702 Million ) Job Owner : The Ministry of Tra

Slide 34: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION Gabonese Republic Projects Presidential Palace – Conference Center – Mausoleum Mosque The Total Contract Price of 3 Projects: USD 260 Million Job Owner : Gabonese Republic Location: Franceville and Libreville The Projects Include Construction of a Mausoleum, a Mo

Slide 35: Selected Projects Under Construction
SELECTED PROJECTS UNDER CONSTRUCTION The Obari 4x160 MW Gas Turbine Project – Obari, Libya Located in Obari, Libya Job Owner: General Electricty Company of Libya (GECOL) Contract Price: EUR 170 Million Scope: Engineering, Equipment Supply, Erection, Commissioning, Start-Up as well as 50 Kilometers o

Slide 36: 56th Year
56th YEAR

Slide 37: Real Estate
REAL ESTATE Type Location Size (NLA) Occupancy Rate Class A Office Area Moscow 330.000 m2 92% USD 850/m2/Year Retail Area Moscow** 215.000 m2 100% USD 650/m2/Year 5 Star Hotel Moscow 235 Rooms * * * Occupancy and Rate of rooms of the Hotel may vary daily. * * 1 out of 9 Shopping Centers is located i

Slide 38: Real Estate Rental Revenue
REAL ESTATE Year Rental Revenue Change Change (%) 2013 (3Q) USD 355 Million USD 30 Million* 9,2% ** 2012 USD 442 Million USD 35 Million 8,6% 2011 USD 407 Million USD 35 Million 9,4% 2010 USD 372 Million * The Change is between 3Q 2012 and 3Q 2013 ** 3Q 2012 Real Estate Revenue was reailsed as USD 32

Slide 39: Real Estate EBITDA
REAL ESTATE Year EBITDA EBITDA Margin Change Change (%) 2013 (3Q) USD 255 Million 72% USD 38,1 Million 18% 2012 USD 308 Million 70% USD 3 Million 1% 2011 USD 311 Million 77% USD 56 Million 21% 2010 USD 255 Million 69% * The Change is between 3Q 2012 and 3Q 2013 ** 3Q 2012 Real Estate EBITDA was reai

Slide 40: Real Estate (New Investment Projects)
REAL ESTATE (NEW INVESTMENT PROJECTS) Kuntsevo Multifunctional Complex Job Owner : ENKA TC (Fully Owned By ENKA) Total Investment : USD 425 Million The Existing Shopping Center which was Opened In 1997 with a Total of 19.400 m2 is demolished in 2012 The Complex will Include: Shopping Center with a

Slide 41: Real Estate (Further Investment Projects)
REAL ESTATE (FURTHER INVESTMENT PROJECTS) Sergiev Possad Shopping Center Job Owner: ENKA TC (Fully Owned By ENKA) Total Investment: USD 45 Million The Complex will Include: Shopping Center with a Net Leasable Area of 21.000 m2 A Car Park of 734 spaces With a Building Area of Approximately 32.0

Slide 42: Real Estate (Further Investment Projects)
REAL ESTATE (FURTHER INVESTMENT PROJECTS) Further Investment Plans in Russia are: Renewing of Marina Rosha & Kashirskaya Shopping Centers Construction of Multifunctional Shopping Center Project in the Land Owned by ENKA TC, Located in the City of Toliatti, Samara Project Development of the Bel

Slide 43: BINJEIRGW
BINJEIRGW

Slide 44: Financial Overview
FINANCIAL OVERVIEW Operator Ownership: 100% ENKA Debt-to-Equity Ratio: 75/25 Export Credit Agency (ECA) and OPIC Facilities Fully Covered Political and Commercial Risk is Approximately 94% Exhaustive Due Diligence Over 2 Years by ECA and OPIC No Local Currency Risk: Payments Calculated in USD and Pa

Slide 45: Project Overview
PROJECT OVERVIEW 3 Gas-Fired Combined Cycle Power Plants (Total 3,854 MW) – Gebze 1,554 MW – Adapazarı 777 MW – Izmir 1,523 MW Annual Generation is 32 Billion kWh Net and the Annual Natural Gas Consumption is around 6.5 Billion cbm, Capability of Meeting 14% of Turkey’s Total Demand, since Turkey’s

Slide 46: Project Overview (Cont'd)
PROJECT OVERVIEW (Cont’d) BOTAŞ Turkish Pipeline Corporation, a Turkish State Entity, Supplies Natural Gas Under 16-Year-Term Contract (Will expire at the end of 2018) Turkish Undersecreteriat of Treasury Guarantees Back Obligations of TETAŞ and BOTAŞ, Very Competitive Tariffs - 4.2 Cent/kWh Average

Slide 47: Project Rationale
PROJECT RATIONALE Strong and Growing Projected Demand for Electricity (8%p.a.) Existing and Forecasted Energy Shortage at that Time, Improving Economic Situation in Turkey. Proximity to Main Electricity Load Centres – Will Reduce Transmission Losses from Plants in East (Near Domestic Coal and Hydro

Slide 48: Debt Funding
DEBT FUNDING TOTAL COMMITTED AMOUNTS (Million USD) TOTAL DEBT (75%) 1.530 TOTAL EQUITY (25%) 510 TOTAL PROJECT COST 2.040 48

Slide 49: Debt Funding
DEBT FUNDING PROJECT FINANCE TOTAL AS OF 31.12.2012 US EXIM, USA 860 55 HERMES, GERMANY 185 1 OND, BELGIUM 125 6 OPIC, USA 300 37 OTHER BANKS 60 0 TOTAL 1.530 99 All Outstanding Project Finance Loans have been Fully Paid Back in the 2Q 2013 49

Slide 50: Overview of Project Agreements
OVERVIEW OF PROJECT AGREEMENTS NATURAL GAS EPC SALES CONTRACT BECHTEL AGREEMENT BOTAŞ ENKA JV PARTS & TREASURY PROJECT TREASUR SERVICES GUARANTIES COMPANY GE Y AGREEMENT ENKA TETAŞ OPERATIONS ELECTRICITY SANTRAL & BAKIM SALES MAINTENANC AGREEMENT E AGREEMENT 50

Slide 51: Turkey's Energy Consumption in 2012
TURKEY’S ENERGY CONSUMPTION IN 2012 SOURCES MILLION KWH % NATURAL GAS 104.499 43.1 HYDRO 57.865 23.9 COAL 67.164 27.7 WIND, GEO & OTHERS 9.969 4.1 TOTAL PRODUCTION 239.497 98.8 IMPORT 5.827 2.4 EXPORT (2.954) (1.2) Source: TEIAS TOTAL CONSUMPTION 242.370 100 51

Slide 52: Turkey's Energy Consumption in 2012 (Cont'd)
TURKEY’S ENERGY CONSUMPTION IN 2012 (Cont’d) SOURCES MILLION KWH % THERMAL 174.872 72.2 HYDRO 57.865 23.8 WIND 5.861 2.4 GEOTHERMAL 899 0.4 TOTAL PRODUCTION 239.497 98.8 IMPORT 5.827 2.4 EXPORT (2.954) (1.2) Source: TEIAS TOTAL CONSUMPTION 242.370 100 52
Source: Internet Archive copy of enka.com
More decks from Enka Insaat ve Sanayi A.S.
Q3 2026 Earnings Presentation43 slides · November 2026
Q2 2026 Earnings Presentation45 slides · August 2026
Q1 2026 Earnings Presentation45 slides · May 2026
FY2025 Earnings Presentation46 slides · 2026
Q3 2025 Earnings Presentation46 slides · November 2025
H1 2025 Earnings Presentation47 slides · August 2025