Slide 1: Investor presentation
Ge SOAR SOVEREIGN Al RESOURCES - NYSE AMERICAN: SOAR Investor presentatio Secure intelligence. Sustainable infrastructure. October 2026 © 2026 Volato Group, Inc. (to be renamed SOAR Al, Inc.). All rights reserved. Private an SOAR Al and Sovereign Al Resources are subject to pendi

Slide 2: Disclaimer and forward-looking statements
Disclaimer and forward-looking statements This presentation has been prepared by Volato Group, Inc. (NYSE American: SOAR), which is changing its corporate name to SOAR AI, Inc. (together with its subsidiaries, the “Company”), and is being provided on a confidential basis solely to prospective invest

Slide 3: What has changed: Recent developments
What has changed Recent developments The merger has closed, customer contracts are signed, and construction of the first campus is underway. Merger closed SEP 11 $1.17B contracted SEP 22 Alignment Engine merger completed September 11, 2026. The AI infrastructure Master services agreement and two fou

Slide 4: Investment highlights: SOAR AI at a glance
Investment highlights SOAR AI at a glance $1.17B 8,000 154 MW ~$133M Contracted orders GPUs under contract Ohio power available Customer prepayments Two 4-year take-or-pay orders MI355X and MI455X Roadmap to 480 MW Under signed orders Contracted demand before first service. Powered industrial campus

Slide 5: Business overview
S ECT IO N 0 1 Business overview

Slide 6: Who we are
Who we are Company overview We develop powered AI data centers and provide GPU capacity to customers that need control over their data and models. AI infrastructure Community-integrated campuses Customer control • Develop and operate AI data center • Repurposed industrial sites, or greenfield • Dedi

Slide 7: GPU-as-a-Service business model
GPU-as-a-Service business model How we earn revenue Customers reserve dedicated compute capacity for a fixed term and pay whether or not they use it. Secure powered Deliver dedicated Earn contracted 1 2 Deploy GPU clusters 3 4 capacity compute revenue • Control repurposed industrial • Procure AMD In

Slide 8: Offerings | Today and next
Offerings | Today and next What we sell Contracted revenue today comes from dedicated capacity. Additional offerings broaden the customer base over time. T OD AY NEXT NEXT NEXT Dedicated GPU capacity Shared capacity On-prem and edge Next-generation systems platforms • Single-tenant AMD Instinct clus

Slide 9: AMD Instinct platform and technology
AMD Instinct platform and technology Technology We build on AMD’s GPU roadmap and open software stack, and add our own data-movement technology. AMD GPU roadmap Open software NeuralSync DPU • Phase I: AMD Instinct MI355X • AMD ROCm open software ecosystem supports • Proprietary FPGA-based network ac

Slide 10: Where AI infrastructure demand is going
Where AI infrastructure demand is going Market Demand is shifting toward dedicated capacity, and communities are scrutinizing how new data centers are built. 56% → 41% Customers we serve Why we can win Public-cloud share of AI inference • AI platforms and model builders: large, long-term • Dedicated

Slide 11: Contracted demand
S EC TI ON 02 Contracted demand

Slide 12: Contracted demand: $1.17 billion of take-or-pay orders
Contracted demand | $1.17 billion of take-or-pay orders Customer contracts A master services agreement and two four-year orders with a large AI customer cover both deployment phases. Order #1 | AMD Instinct MI355X Order #2 | AMD Instinct MI455X GPUs 4,000 GPUs 4,000 Contractual start date December 3

Slide 13: Contracted revenue profile
Contracted revenue profile Signed orders only Annual contract revenue under the two signed orders, assuming capacity is accepted on the contractual start dates. Order #1 (MI355X) Order #2 (MI455X) $300M $1,173M Total contract value 48-month terms, 2027 to mid-2031 $250M $200M $193.4M $193.4M $193.4M

Slide 14: AI infrastructure
S EC TI ON 03 AI infrastructure

Slide 15: Ohio campus | Phase I
Ohio campus | Phase I Industrial AI campus Building 285 at a former paper mill is being converted into a liquid-cooled AI data hall. 9,216 25 MW 49 MW ~$730M 240 AMD MI355X and MI455X GPUs Phase I design block Lease power by Feb. 2027 Phase I program incl. compute Projected jobs Phase I build Why an

Slide 16: Path to first service
Path to first service Phase I and II milestones Construction is underway against a schedule that targets customer-ready capacity on December 31, 2026. SEP 2026 OCT 19 NOV 16 NOV 30 DEC 31 FEB 2027 JUN 30, 2027 Mobilization Floor usable Equipment roll-in Internal power-on Order #1 start Chiller and 4

Slide 17: Growth path
Growth path Phased expansion Prove the model in Ohio, scale the campus, then repeat it at additional powered sites. I N P R OGR ESS C ONTR A C TED R OA D MA P E V AL U AT I N G 1 Phase I 2 Phase II 3 Campus expansion 4 Additional sites • 9,216 MI355X and MI455X • 4,000 MI455X GPUs • 154 MW available

Slide 18: How we choose sites
How we choose sites Site evaluation framework We weigh each potential campus against these criteria, whether a repurposed industrial site or a greenfield site. 1 2 3 4 5 Power Water Permits and zoning Workforce Community • Existing grid • Industrial water rights or • Industrial zoning in place • Loc

Slide 19: Where we're going
Where we’re going Roadmap Deliver the contracted capacity, scale the Ohio campus, then replicate the model at new sites. 202 6 202 7 BE YO N D Deliver Scale Replicate • Order #1 contractual start: December 31 • Order #2 contractual start: June 30 • Grow the Ohio campus along the roadmap to • Close p

Slide 20: Capital plan and offering
S ECT IO N 0 4 Capital plan and offering

Slide 21: Capital plan | Funding by phase
Capital plan | Funding by phase Sources and uses We build against long-term contracted demand, funding each phase with customer prepayments, debt and equity. Uses Equity / convertible Senior debt Customer prepayments Total sources Phase I | 9,216 GPUs ~$730M $158M $450M $186M $794M Phase II | 4,000

Slide 22: Private placement summary
Private placement summary Proposed terms Proceeds fund the equity portion of the Phase I and Phase II deployments. Issuer Volato Group, Inc. (NYSE American: SOAR), to be renamed SOAR AI, Inc. $200M Estimated placement Offering size Estimated at $200 million Securities Convertible notes and common st

Slide 23: Key risks and how we manage them
Key risks and how we manage them Execution The main concerns we have heard from investors, and what is in place to address them. Owner-procured long-lead equipment, construction manager at risk, weekly critical-path tracking against the Dec. 31 Construction and schedule start date Signed take-or-pay

Slide 24: Leadership and milestones
S ECT IO N 0 5 Leadership and milestones

Slide 25: Leadership team
Leadership team Management CE MH DS MP Chris Ensey Mark Heinen David Stanfill Mike Prachar Chief Executive Officer Chief Financial Officer Chief Technology Officer Chief Operating Officer • 25 years building mission- • 30+ years in finance, 25+ in • 12 years in high-performance • Chief Operating Off

Slide 26: Upcoming milestones
Upcoming milestones Next 9 months Near-term events that will show progress against the plan. Name change to SOAR AI, Inc. effective; trading Special shareholder meeting, including financing Oct. 19–20, 2026 Dec. 2026 under the new name and listing proposals First quarterly report as a combined compa

Slide 27: Thank you
S OA R A I · N YS E AME RI C AN : S OAR Thank you Investor contact: [email protected] 8050 Freedom Ave NW, North Canton, Ohio 44720
Source: company website
More decks from Volato Group, Inc.
Investor Presentation (July 2024)40 slides · Jul 19, 2024
Investor Presentation (June 2024)40 slides · Jun 7, 2024
Q1 2024 Earnings Presentation13 slides · May 15, 2024
Investor Presentation (April 2024)40 slides · Apr 24, 2024
Q4 2023 Earnings Presentation17 slides · Mar 26, 2024
Investor Presentation (February 2024)40 slides · Feb 21, 2024