Global Power Synergy Public Company Ltd · SET:GPSC
Global Power Synergy Public — Non-Deal Roadshow (March 2019)
47 slides from Global Power Synergy Public's roadshow presentation, Mar 12, 2019

Slide 1: Corporate Presentation
Corporate Presentation THE INNOVATIVE POWER FLAGSHIP OF PTT GROUP Non-Deal Roadshow in Japan MARCH 12-15th, 2019

Slide 2: Disclaimer
Disclaimer The information contained here is being furnish on a confidential basis for discussion purposes only and only for the use of the recipient, and may be subject to completion or amendment through the delivery of additional documentation. Except as otherwise provided herein, this document do

Slide 3: Industry Overview, Company Overview, Investment in Affiliates, Financial Performance
Industry Overview Company Overview Investment in Affiliates Financial Performance 3

Slide 4: Current Power Industry Structure in Thailand
Current Power Industry Structure in Thailand • EGAT and IPPs dominate electricity generation market, with the combined market share 75%. • EGAT is the sole purchaser for almost all of the electricity generated, while VSPPs sell electricity directly to the MEA and PEA • SPPs sell electricity to both

Slide 5: Summary of Power Development Plan (PDP) 2018
Summary of Power Development Plan (PDP) 2018 Social & Reliability Economic Environment o Consider the whole country o Electricity tariff from PDP o Maintain generation from electric system including 2018 will not be higher renewable energy to generation, transmission and than current tariff comply w

Slide 6: Source of Fuel
Thailand Power Development Plan : Power Generation by Fuel Source (Unit: %) PDP 2015 New PDP 2018 Source of Fuel (in 2036) (in 2037) Natural Gas 37 53 Coal / Lignite 23 12 Hydro Power 15 9 Renewable 20 20 Nuclear 5 - Others 0.1 0.06 Energy efficiency - 6 Source: Ministry of Energy 6

Slide 7: Company Overview
Industry Overview Company Overview Investment in Affiliates Financial Performance 7

Slide 8: GPSC Innovative Power Company at a Glance
GPSC Innovative Power Company at a Glance Shareholding Structure In 2019, Total Committed Generating Capacity Electricity 1,955 MWe, Steam 1,585 T/H Public Electricity 1,550 MW Steam 1,585 T/H Industrial Water 2,080 Cu.m./H COMBINED CYCLE / Chilled Water 12,000 RT COGENERATION Thai Oil Power is 73.9

Slide 9: GPSC Customers' Profile
GPSC Customers’ Profile 53% PTT Group 38% EGAT LONG TERM OFF TAKE CONTRACTS Guaranteed market and source of revenue 9% Industrial Users Guarantee a minimum level of profit in regards to *2018 Revenue by Customers their investment Price adjustment formula, varying with fuel price 9

Slide 10: Power Plant Definition and Revenue Structure
Power Plant Definition and Revenue Structure IPP SPP VSPP Small Power Producer (SPP): Very Small Power Producer Independent Power (VSPP): Producer (IPP): • A small power producer who sell their electricity no more than or • A very small generator whose • A larger power producer equal to 90 MW to EGA

Slide 11: GPSC's Business Portfolio: 11 Affiliates in 4 Countries
GPSC’s Business Portfolio : 11 Affiliates in 4 Countries Combined Cycle / Cogeneration Renewable Energy Combined Heat and Power 100% Sriracha Power Plant (IPP) 100% Producing (VSPP) Thai Solar Renewable (VSPP) 40% • Electricity: 700 MW • Electricity: 5 MW • Industrial water: 80 Cu.m./h • Chilled wat

Slide 12: Q4/2018 Highlights
Q4/2018 Highlights GROWTH • GLOW shares’ acquisition (2,771 MW) • Solar power plants shares’ acquisition (39.5 MW) • Energy Recovery Unit project (250 MW) • Rayong Waste to Energy (9.8 MW) PROFIT 2018 EBITDA Increased 30% and NI Increased 6% from 2017 ◊ The increase in electricity sales from the ful

Slide 13: GLOW Energy PLC. Acquisition
GLOW Energy PLC. Acquisition • Acquire 69.11% of GLOW’s shares (directly and indirectly) from Transaction Engie Global Developments B.V. • Mandatory offer for 30.89% of shares through Tender Offer Transaction Amount • Less than THB 140 Billion Condition Precedent • GLOW divests SPP1 to third party •

Slide 14: Energy Recovery Unit Project
Energy Recovery Unit Project • As a power and steam supporting unit of CFP Near Laem Chabang Port Project Description • The CFP project will improve effectiveness in the production process and transform fuel oil and bitumen into jet fuel and diesel Investment Cost • Approximately USD 757 mm Conditio

Slide 15: Strategic Position & Payment Term
Strategic Position & Payment Term Reduce overall CAPEX of CFP Project Expert and skillful in power business Reduce D/EBITDA ratio and increase Understands the operation of oil refinery liquidity to future investment petrochemical business Benefit from higher IRR for CFP Project Familiarity with the

Slide 16: Global Renewable Power Company Limited Transaction Overview
Global Renewable Power Company Limited Transaction Overview • GPSC has entered into SPA to acquire 100% shares from Brookfield Renewable Partners - The operating solar power plant of 3 companies (NPS Star Group Co., Ltd., World X Transaction Structure Change Asia Co., Ltd., and PP Solar Ltd.) togeth

Slide 17: Global Renewable Power Portfolio
Global Renewable Power Portfolio NP Star World Exchange Asia PP Solar TerraForm Operating 18 17.9 3.6 Capacity (MW) (6*3) (5.96*3) (1.2*3) Off-taker PEA PEA PEA Remaining PPA 22 22 22 Tenor (Years) N/A FiT at 5.66 FiT at 5.66 Adder at 8 THB/KwH (Service Company) Tariff Scheme THB/KwH THB/KwH (adder

Slide 18: GPSC Electricity Growth Pipeline
GPSC Electricity Growth Pipeline Operating Capacity (MWe) 5,026 +81% CAGR by 2023 Projects on Progress Future Growth +3,071 1,955 Operating Solar Project 39.5 MW Growth along with PTT Business expansion along with Expected closing in Q1/19 PTT Group 1,530 Glow Energy PLC. International Power P

Slide 19: Strategic Direction and Growth Strategy
Strategic Direction and Growth Strategy Strategic Direction The global leading innovative and sustainable power company Operational Excellence 3 Growth Engines New S-curve Maximize Core Growth along with Battery Business PTT Group Energy Storage System International market Integrator Manag

Slide 20: Investment in Affiliates
Industry Overview Company Overview Investment in Affiliates Financial Performance 20

Slide 21: Nam Lik 1 Power Company Limited (Lao PDR)
Nam Lik 1 Power Company Limited (Lao PDR) Q4/2018 Start: 96.5% Q2/2014 Q3/2018 95% SCOD: MAR/2019 Type: Run-of-River Hydropower Electricity: 64.5 MW Customer: EDL (25 years PPA) Shareholding: Progress update: EDL As of Q4/2018, the construction 10% progress of NL1PC as appraised by POSCO 40% techn

Slide 22: Xayaburi Power Company Limited (Lao PDR)
Xayaburi Power Company Limited (Lao PDR) Q4/2018 Start: 97.5% Q1/2012 Q3/2018 96% SCOD: OCT/2019 Type: Run-of-River Hydropower Electricity: 1,285 MW Customer: EGAT 1,220 MW, EDL 60 MW Shareholding: Progress update: PT The main construction tasks such as EGCO 5% power house, intermediate block, 12.

Slide 23: Central Utility Plant 4: CUP4 (Thailand)
Central Utility Plant 4 : CUP4 (Thailand) Start: Q4/2018 Q4/2017 Q3/2018 39.7% 60.3% SCOD: Q3/2019 Type: Gas-fired Cogeneration Electricity: 45 MW Steam: 70 T/h Customer: • PTT Group • Non-PTT Group • EGAT Shareholding: Progress update: As of Q4/2018, the progress of site construction was over 33%

Slide 24: Nava Nakorn Electricity Generation (NNEG) Expansion Project
Nava Nakorn Electricity Generation (NNEG) Expansion Project Q4/2018 Start: Q3/2018 12% SCOD: Q3/2020 Type: Gas-fired cogeneration Electricity: 60 MW Steam: 10 T/h Customer: • Non-PTT Group Shareholding: Progress update: NNCL As of Q4/2018, the project progress 30% has reached 12%. 30% Main tasks

Slide 25: Financial Performance
Industry Overview Company Overview Investment in Affiliates Financial Performance 25

Slide 26: Q4/2018 Financial Performance Summary (1/2)
Q4/2018 Financial Performance Summary (1/2) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M Revenue & Gross Profit Margin (THB Million,%) Rev. +988 /+20% Rev. -824 / -12% Rev. +4,860 / +24% GPM -5% GPM -2% GPM +2% 27% 29% 28% 24% 22% 24% 26% Gross profit margin Revenue: YoY, 12M: Higher rev

Slide 27: Q4/2018 Financial Performance Summary (2/2)
Q4/2018 Financial Performance Summary (2/2) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 EBITDA, Net Profit* and Net Profit Margin (THB Million,%) YoY QoQ 12M NPM -7% NPM -5% NPM -2% 16% 14% Net EBITDA -163 / -14% EBITDA -397 / -29% EBITDA +1,270 / +30% 15% 16% 16% 13% 8% Profit NP -236 / -33% Margin

Slide 28: Sriracha Power Plant: Revenue & Gross Profit
Sriracha Power Plant : Revenue & Gross Profit Revenue Gross Profit & Gross Profit Margin (THB Million, %) (THB Million, %) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M YoY QoQ 12M Rev. +17 / +5% Rev. -984 / -72% Rev. -630 / -14% GP -131 / -484% GP

Slide 29: Sriracha Power Plant: Availability Payment (AP)
Sriracha Power Plant : Availability Payment (AP) Revenue from AP (THB million) Availability Rate(%) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M YoY QoQ 12M AP -110 / -1,222% AP -242 / -197% AP -199 / -42% AR -24% AR -60% AR -6% 100% 470 91% 85% 6

Slide 30: Sriracha Power Plant: Energy Payment (EP)
Sriracha Power Plant : Energy Payment (EP) Revenue from EP (THB million) Average sales price & dispatch (Baht/kWh, GWh) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M EP +140 / +61% EP -733/ -67% EP -385 / -12% 2000 - 2.62 3.35 2.52 2.81 Average sales 0 price 1800 3,343 1,521 2,958 1600 -200

Slide 31: Rayong Power Plant (Cogeneration): Revenue & Gross Profit
Rayong Power Plant (Cogeneration) : Revenue & Gross Profit Revenue Gross Profit & Gross Profit Margin (THB Million, %) (THB Million, %) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M YoY QoQ 12M Rev. +152 / +4% Rev. 137 / 4% Rev. +877 / +7% GP -150

Slide 32: Rayong Power Plant (Cogeneration): Power Sales
Rayong Power Plant (Cogeneration) : Power Sales Power sales volume Average sales price & Ft rate (GWh) (THB/kWh, THB) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M Sales -10 / -2% Sales +18 / +3% Sales +60 / +2% 2,448 2,508 3.50 0.60 3.00 3.00 2.99 2.88 2.86 Average 3.00 0.40 sales price 0.

Slide 33: Rayong Power Plant (Cogeneration): Steam Sales
Rayong Power Plant (Cogeneration) : Steam Sales Steam sales volume Average sales price & (‘000 tons) Average natural gas price (THB/ton, THB/MMBTU) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M -64 / -4% +30 / +2% +128 / +2% 1,400 5,596 5,724 1,121 1,145 1,200 1,056 1,093 Average 1,035 sale

Slide 34: IRPC-CP Power Plant (SPP): Revenue & Gross Profit
IRPC-CP Power Plant (SPP) : Revenue & Gross Profit Revenue Gross Profit & Gross Profit Margin (THB Million, %) (THB Million, %) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M YoY QoQ 12M Rev. +703 / +74% Rev. +37 / +2% Rev.+4,224 / +202% GP +168 / +

Slide 35: IRPC-CP Power Plant (SPP): Power Sales
IRPC-CP Power Plant (SPP) : Power Sales Power sales volume Average sales price & Ft rate (GWh) (THB/kWh, THB) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M +192 / +82% -16% / -4% +1,332 / +341% 1,723 3.50 10.0000 3.10 3.21 3.06 Average 2.92 2.89 8.0000 3.00 sales price 6.0000 2.50 4.0000 44

Slide 36: IRPC-CP Power Plant (SPP): Steam Sales
IRPC-CP Power Plant (SPP) : Steam Sales Steam sales volume Average sales price & (‘000 tons) Average natural gas price (THB/ton, THB/MMBTU) Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 YoY QoQ 12M -17 / -7% +21 / +11% +15 / +2% 833 848 1,400 1,247 1,309 1,225 Average 1,145 1,156 sales price 1,200 1,00

Slide 37: Cost of Sales and Services
Cost of Sales and Services Q4/18 vs Q4/17 Q4/18 vs Q3/18 2018 vs 2017 Cost of sales and services* (THB Million) YoY QoQ 12M +1,041 /+29% -480 / -9% +3,379 / +22% YoY, 12M: Cost of sales and service 18,428 Others increased due to higher SPP natural gas 4% Maintenance consumption from full operation

Slide 38: Natural Gas Consumption vs Price Trend
Natural Gas Consumption vs Price Trend Quarterly natural gas consumption (‘000 MMBTU) vs. Monthly natural gas price (THB/MMBTU) SPP 288* W.A. 288* IPP 269* 12,178 12,431 12,268 12,468 11,247 9,424 9,146 8,893 8,831 8,577 8,265 7,768 Natural gas 6,264 SPP consumption volume: SPP 5,212 4,721 4,492 3,9

Slide 39: Financial Position of GPSC and Affiliates
Financial Position of GPSC and Affiliates Total Assets Total Liabilities & Shareholders Equity (THB Million) (THB Million) YTD YTD 64,439 +4,471 / +7.4% 64,439 59,968 +4,471 / +7.4% 59,968 3,675 6% Other current liabilities 6% 3,097 4,995 11,463 18% 8% Debentures Current assets 16% 9,313 9% 4,993 18

Slide 40: Well-managed debt profile and continuous deleveraging
Well-managed debt profile and continuous deleveraging Debt Profile Debt Repayment Plan Total interest-bearing debt : THB 17,504 million Current portion due within 1 year THB 1,052 million Current portion of 6% 11% JPY long-term loan Jan - and debentures Dec 19 6% Non-current Jan 20 – Dec 23 89% port

Slide 41: Key Financial Ratios
Key Financial Ratios Total D/E and Net Debt/ Equity ratio (Times) Earning per share (EPS) (Baht/share) 2.24 Total D/E 2.12 Net D/E 0.54x 0.52x 0.49x 0.29x 0.29x 0.27x 0.60 0.48 0.32 31Q4/17 Dec 17 30 Q3/18 Sep 18 31 Dec 18 Q4/17 Q3/18 Q4/18 2017 2018 Book value per share (BVPS) (Baht/share) ROE (%)

Slide 42: Thank You
THANK YOU IR Contact Sukittee Chaiyarak Pimploy Wichienprakarn Janthakarn Chanhorm +662 140 4628 +662 140 4691 +662 140 5318 [email protected] www.gpscgroup.com 42

Slide 43: Appendix
APPENDIX Global Power Synergy Public Company Limited 555/2 Energy Complex, Building B Vibhavadi Rangsit Rd. Chatuchak, Bangkok 10900 Disclaimer The information contained here is being furnish on a confidential basis for discussion purposes only and only for the use of the recipient, and may be subje

Slide 44: Power Plants Portfolio of GPSC
Power Plants Portfolio of GPSC Equity GPSC’s Total capacity Steam Industrial water Name Type capacity COD Tenor (MW) (Cu.m/H) share % (MW) (T/H) IN OPERATION Sriracha IPP 100% 700 700 - 80 2000 25/2025 CUP-1 SPP 100% 226 226 890 720 2006 10-15/2021++ CUP-2 SPP 100% 113 113 170 510 2008 15/2022++ CUP

Slide 45: Investment in Associates and joint ventures
Investment in Associates and joint ventures Proportion of GPSC’s investment in associates and joint ventures at Q3/18 and Q4/18 (THB Million, %) NL1PC NL1PC NNEG 4.6% NNEG 4.4% 6.0% 6.2% TSR TSR 17.4% 16.8% BIC XPCL BIC XPCL 9.0% 63.1% 9.1% 63.6% Q3/2018: Total of THB 9,472 million Q4/2018: Total of

Slide 46: 2019 Maintenance schedule: Sriracha and Rayong plants
2019 Maintenance schedule: Sriracha and Rayong plants 2019 Plant Tag no. Description Q1 Q2 Q3 Q4 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec CUP-1 15 3Y 28 H-13701 Aux. Boiler.11 N-13901 GTG11 12 MI 5 H-13702 HRSG11 12 3Y 5 N-13902 GTG12 07 1Y 17 H-13703 HRSG12 07 1Y 17 12 1Y 22 N-13903 GTG13 H-

Slide 47: 2018-2019 Maintenance schedule: IRPC-CP
2018-2019 Maintenance schedule: IRPC-CP 2018 2019 Plant Unit Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 (A) (A) (A) (A) (F) (F) (F) (F) IRPC-CP Block 1 CTG 21 E A 1 1 1 1 HRSG 21 E A 1 1 1 1 CTG 22 E A 1 1 1 1 HRSG 22 E A 1 1 1 1 STG 23 Block 2 CTG 31 E A 1 1 1 1 HRSG 31 E A 1 1 1 1 CTG 32 B 1 1 6 1 HRSG 32 B 1 1 6 1