Global Power Synergy Public Company Ltd · SET:GPSC
Global Power Synergy Public — Non-Deal Roadshow (September 2016)
82 slides from Global Power Synergy Public's roadshow presentation, Sep 1, 2016

Slide 1: Corporate Presentation Thailand Focus 2016
Corporate Presentation Thailand Focus 2016 1th September 2016 1

Slide 2: Agenda
Thailand Power Industry Overview P.2 Company Overview P.7 Q2 2016 Significant Events P.16 Project Update P.22 Financial Performance P.38 Key Takeaway P.54 2

Slide 3: Current Power Industry Structure in Thailand
Current Power Industry Structure in Thailand Click to edit Master title style • EGAT and IPPs dominate electricity generation market, with the combined market share 83%. • EGAT is the sole purchaser for almost all of the electricity generated, while VSPPs sell electricity directly to the MEA and PEA

Slide 4: Power Plant Definition and Revenue Structure
Power Plant Definition and Revenue Structure Click to edit Master title style IPP SPP VSPP Independent Power Small Power Producer (SPP): Very Small Power Producer Producer (IPP): (VSPP): • A small power producer who sell • A larger power producer their electricity no more than or • A very small gene

Slide 5: Natural gas and Renewable will be major fuel sources in 2036
Natural gas and Renewable will be major sources of fuel in Thailand in 2036, together accounted for over 70% Click to edit Master title style • According to Thailand’s Power Development Plan 2015 (PDP - by Energy Policy and Planning Office (EPPO), Ministry of Energy), power plant capacity in Thailan

Slide 6: Large opportunity for GPSC to tap in expected capacity
Large opportunity for GPSC to tap in those expected capacity Click to edit Master title style Projected Power Plant Capacity by producer type (MW) Thailand's power contract capacity during 2016-2036 (new and retired) 43,624 (100%) 80,000 Total capacity Unit: MW 70,335 MW 17.6% Imported 60,000 12,347

Slide 7: Company Overview
Thailand Industry Overview P.2 Company Overview P.7 Q2 2016 Significant Events P.16 Project Update P.22 Financial Performance P.38 Key Takeaway P.54 7

Slide 8: Introduction to GPSC, a PTT Group's Power Flagship
Introduction to GPSC, a “PTT Group’s Power Flagship” GPSC, PTT Group’s Power Flagship, has been founded to be the power flagship of PTT Group. In 2013-2014, PTT Group were restructured and transferred Power Assets to GPSC. The integration results in a total generating capacity of 1,851 MW of electri

Slide 9: Vision, Mission, and Goal
Vision, Mission, and Goal GPSC’s Shareholding Structure Vision Global Best Practice in Power Business Public 25.0% 22.7% Mission Being Power Flagship of PTT Group to Develop, Invest and Operate in Power Business Domestically and Internationally 8.9% 22.6% Goal 20.8% • Aims to reach secured capacity

Slide 10: GPSC's facilities produce electricity of 1,922 MW
GPSC’s facilities produce electricity of 1,922 MW BUSINESS PORTFOLIO Combined Cycle / Cogeneration Renewable Energy Hydroelectric Other Businesses • Electricity 1,517 MW • Electricity 58 MW • Electricity 347 MW • 24M Technologies, Inc. (USA) • Steam 1,582 T/H • Business Service Alliance Co.,Ltd. • I

Slide 11: GPSC's Business Portfolio
GPSC’s Business Portfolio Combined Cycle / Cogeneration Renewable Energy Combined Heat and Power 100% Thai Solar Renewable 40% Sriracha Power Plant (IPP) 100% Producing (VSPP) (VSPP) • Electricity: 700 MW • Electricity: 5 MW • Electricity: 80 MW • Industrial water: 80 Cu.m./h • Chilled water: 12,000

Slide 12: Majority of revenue is from electricity; PTT Group is major customer
Majority of GPSC’s revenue is from electricity, PTT Group is GPSC’s major customer Q2/16 Revenue by product Q2/16 Revenue by customer (THB million) (THB million) Industrial water Non PTT Group Others Chilled water 1% 1% 7% 1% Electricity (IPP) Steam 28% 33% Total Total 5,553 EGAT 5,553 37% PTT Group

Slide 13: Business portfolio located in Thailand, Lao PDR and Japan
Presently, GPSC’s business portfolio is located in Thailand, Lao PDR and Japan Japan Project under construction Ichinoseki Gas Power Plant Luangphabang Hydro Power Plant Lao PDR 500 KV Xayaburi Solar Power Plant Loei 2 Vientiane Lao PDR (A.Tha Li) Nam Lik 1 Khon Kaen 4 Ayutthaya Suphanburi BIC-1 TSR

Slide 14: GPSC will deliver outstanding growth during 2016-2019
GPSC will deliver outstanding growth during 2016-2019 Power Secured Electricity MW GPSC’s Committed Capacity Unit: Equity MW Completed projects Unit: Equity MW 321 Luangphabang 71 154 38 500 KV CUP-4 1,922 1,530 1,601 Loei 2 Vientiane 1,338 1,376 (A.Tha Li) Khon Kaen 4 (Solar) 2015 15 2016 16 2017 1

Slide 15: Summary of GPSC Power Plants Details
Summary of GPSC Power Plants Details GPSC’s Total capacity Equity capacity Steam Industrial Tenure/ Name Type Location Fuel Type Technology COD share % (MW) (MW) (T/h) water (Cu.m/h) Expiry year IN OPERATION Sriracha IPP Chonburi Natural gas Combined cycle 100% 700 700 - 80 2000 25/2025 CUP-1 SPP Ra

Slide 16: Q2 2016 Significant Events
Thailand Industry Overview P.2 Company Overview P.7 Q2 2016 Significant Events P.16 Project Update P.22 Financial Performance P.38 Key Takeaway P.54 16

Slide 17: Q2 2016 Highlights
Q2 2016 Highlights Click to edit Master title style 11.8% committed CAGR THB 686 Million in profit In Q2/16, GPSC has been recognizing more revenue Net profit of Q2/16 decreased by THB 185 million from from the SPPs and will gain more revenue from the Q1/16 mainly due to there was a dividend income

Slide 18: GPSC included in SET50 for 2H16
GPSC has been included in SET50 for 2H16 reflecting company’s performance Click to edit Master title style THB / Share GPSC’s Stock Price (May 15 – August 16) 45 SET50/SET100 Index Investors’ Choice Award Calculated from the stock price of the top 50 and top 100 (27 Jul 2016) listed companies on SET

Slide 19: GPSC's Awards and Recognitions
GPSC’s Awards and Recognitions Click to edit Master title style 14Jul16: “Best CFO” award from IAA 15Jul16: SET congratulates GPSC on being listed in SET50 27Jul16: Investors’ Choice Award from Thai Investor Association 29Apr16: Listed on 2016 ESG 100 Sustainable Business 19 2Q 2016 Significant Even

Slide 20: NNEG has started COD as planned
NNEG has started COD as planned with a promising revenue generating Click to edit Master title style Nava Nakorn Elecricity Generating Company Limited (NNEG) Pathumthani Province NNEG starts COD on 3 June 2016 as planned with operating capacity of 125 MW and steam capacity at 30 T/h In this Q2 2

Slide 21: 2016 Interim dividend payout ratio is 43% of 1H/2016 net income
2016 Interim dividend payout ratio is 43% of 1H/2016 net income Click to edit Master title style • On 18 August 2016, BOD approved a Unit: Baht per share Final Dividend resolution for the payment of interim Interim Dividend dividend for 1H/2016. • The dividend per share is 0.45 Baht which is higher

Slide 22: Project Update
Thailand Industry Overview P.2 Company Overview P.7 Q2 2016 Significant Events P.16 Project Update P.22 Financial Performance P.38 Key Takeaway P.54 22

Slide 23: Committed Projects to operate by 2019
7 Committed Projects to operate by 2019 GPSC’s Management team ensure efficient project management and high competent Click to edit Master title style staffs, both domestic and international projects in order to meet the construction schedule and COD according to predetermined schedule. L 500 KV GPS

Slide 24: IRPC Clean Power Phase 2
IRPC Clean Power Phase 2 (IRPC-CP Phase 2) Click to edit Master title style IRPC Clean Power Company Limited (IRPC-CP) In IRPC Industrial Zone at Choeng Noen, Rayong Province (118 Rai) Equity % Progress Type SPP Cogeneration Investment Capacity* • Electricity: 240 MW 2Q16 • Steam: 180-300 T/H 3,400

Slide 25: Bangpa-In Cogeneration Phase (BIC-2)
Bangpa-In Cogeneration Phase 2 (BIC-2) Click to edit Master title style Bangpa-In Cogeneration Company Limited (Phase 2) Ayutthaya Province Equity % Progress Type Gas-Fired Power Plant Investment Capacity • Electricity: 117 MW (gross) 1,335 THB million • Steam: 20 T/h Customer • Electricity: EGAT 90

Slide 26: Ichinoseki Solar Power (ISP1)
Ichinoseki Solar Power (ISP1) Click to edit Master title style Ichinoseki Solar Power (ISP1) Ichinoseki City, Japan Equity % Progress Type Solar Investment Site preparation Capacity • Electricity: 20.8 MW ~2,080 YEN Million 1% Others Customer • Tohoku Electric Power (20 years) SCOD Q42017 2Q16 57% T

Slide 27: Nam Lik Power Company Limited (NL1PC)
Nam Lik 1 Power Company Limited (NL1PC) Click to edit Master title style Nam Lik 1 Power Company Limited (NL1PC) Lao PDR Equity % Progress Type Run-of-River Hydropower Investment Capacity • Electricity: 65 MW ~37 USD Million Customer • Electricity: EDL 63.8 MW (30 years PPA) SCOD 2018 60% Others 2Q1

Slide 28: Central Utility Plant Project 4 (CUP-4 Ph1)
Central Utility Plant Project 4: Phase 1 (CUP-4 Ph1) Click to edit Master title style Central Utility Plant Project 4 (CUP-4) PTT’s WEcoZi, Asia Industrial Estate (AIE) Rayong Province Equity Investment Type Gas-fired Cogeneration Power <4,000 THB Million Plant/Utilities Capacity • Electricity: 390

Slide 29: Xayaburi Power Company Limited (XPCL)
Xayaburi Power Company Limited (XPCL) Luangphabang Click to edit Master title style Xayaburi Power Company Limited (XPCL) 500 KV Xayaburi, Lao PDR Luangphabang Type Run-of-River Hydropower Equity Loei 2 Vientiane % Progress Investment Capacity • Electricity: 1,285 MW 500 KV (A.Tha Li) 28,821 THB Mil

Slide 30: XPCL receives subsidies from Lao PDR's Government
XPCL receives subsidies from Lao PDR’s Government to compensate for higher cost for environmental Luangphabang concerns Click to edit Master title style Xayaburi Power Company Limited (XPCL) Xayaburi, Lao PDR 500 KV Fish passing facilities The additional Vientiane Loei 2 requirements from Lao PDR’s

Slide 31: CHPP Solar Cooperatives
CHPP Solar Cooperatives Click to edit Master title style CHPP Solar Cooperatives Chanthaburi Province Area 65 rai Type Solar Capacity • Electricity: 5 MW Customer • PEA SCOD December, 2016 Total Investment 244 THB million Contract • FiT THB 5.66/unit • 25 years • End 2041 Progress update Shareholdin

Slide 32: 24M Technologies, Inc. (24M)
24M Technologies, Inc. (24M) Click to edit Master title style 24M Technologies, Inc. (24M) Cambridge, Massachusetts (MA), USA Business Lithium‐Ion Battery (LFP) technology Application • Energy Storage System (ESS) Status • Series C Next Step High Volume Manufacturing Total Investment ~21.67 USD mill

Slide 33: Growth Strategy
Growth Strategy Click to edit Master title style Growth on Equity MW GPSC’s Target Growth Big Win Unit: Secured MW Quick Win International Biomass Solar Coal Gas • Investment in international mega Growth along with PTT Group WTE M&A projects 1,922 CUP-4 and Expansion • Renewable business • Acquisiti

Slide 34: Target 10% Renewable and 30% International projects in 2019
Target 10% of Renewable energy and 30% of International projects in 2019 GPSC’s Portfolio Click to edit Master title style 2016 Committed Portfolio (MW) 2019 Committed Portfolio (MW) Other Renew Solar Biomass 2% Coal 3% 2% 12% Waste to energy Solar Hydro 1% 5% 18% Total Hydro 2,800 MW Natural 12% ga

Slide 35: Strategic Country Selection
Strategic Country Selection Click to edit Master title style Laos “Battery of ASEAN” Myanmar “Gas to Power” Investment focus: Investment focus: • Both conventional and renewable • Hydro power plant energy sources are promoted • Transmission Line GPSC focus: GPSC focus: • Control committed project to

Slide 36: Future project: Waste Management Project
Future project: Waste Management Project Click to edit Master title style Waste Management Project Rayong Province Type RDF Waste to energy Power Plant Capacity Treat MSW at least 500 ton/day Electricity 8 MW Customer RDF Power Plant/ Cement Plant PEA SCOD 2018 2019 Total ~600 Million THB ~1600 Mill

Slide 37: Future project: Myanmar projects
Future project: No significant update due to the restructuring of Ministry. However, GPSC carefully monitors new energy policies to assess projects’ development Click to edit Master title style Project Project Project Thanlyin Project Myeik Project Ayeyarwady Project Location Yangon Region, Myanmar

Slide 38: Financial Performance
Thailand Industry Overview P.2 Company Overview P.7 Q2 2016 Significant Events P.16 Project Update P.22 Financial Performance P.38 Key Takeaway P.54 38

Slide 39: Q2/16 Revenue of THB 5,553 million, increased 1% QoQ
Q2/16 Revenue of THB 5,553 million, increased 1% QoQ Click to edit Master title style Quarterly revenue (THB million) Q2/16 VS Q1/16 (QoQ) • Operating revenue in Q2/16 increased by THB 69 million or 1%. • The increase were mainly caused by higher sales -16% YoY -15% volume from the company’s operati

Slide 40: Sriracha plant revenue breakdown & GPM (1/3)
Sriracha plant revenue breakdown & GPM (1/3) Click to edit Master title style Quarterly revenue & gross profit margin (THB million, %) Q2/16 VS Q1/16 (QoQ) • Total revenue in Q2/16 decreased by THB 51 million or 3% due to lower selling price resulted from lower gas price than in Q1/16. • Gross profi

Slide 41: Sriracha Power Plant (IPP): Power (2/3)
Sriracha Power Plant (IPP): Power (2/3) Click to edit Master title style Quarterly Availability Payment Rate (%) Q2/16 VS Q1/16 (QoQ) • Availability payment rate in Q2/16 increased to Combustion inspection almost 100% thanks to an improvement in plant & Reserved shutdown management. Availability • R

Slide 42: Sriracha Power Plant (IPP): Power (3/3)
Sriracha Power Plant (IPP): Power (3/3) Click to edit Master title style Quarterly average sales price & dispatch (Baht/kWh, GWh) Q2/16 VS Q1/16 (QoQ) Q1/16 VS Q4/15 (QoQ) • Average sales price in Q2/16 decreased by 0.20 • In BahtQ1/16, thefrom per kWh, average sales price the lowering of gas decrea

Slide 43: Rayong plant revenue breakdown & GPM (1/3)
Rayong plant revenue breakdown & GPM (1/3) Click to edit Master title style Quarterly revenue & gross profit margin (THB million, %) Q2/16 VS Q1/16 (QoQ) 26% • Total revenue in Q2/16 increased by THB 121 25% 26% 20% 20% 20% 17% million or 4% from higher sales volume from the increases in the demands

Slide 44: Rayong Power Plant (SPP): Power (2/3)
Rayong Power Plant (SPP): Power (2/3) Click to edit Master title style Quarterly power sales volume (GWh) Q2/16 VS Q1/16 (QoQ) +10% YoY • Volume : increased by 51 GWh or 9% due to +8% Customers +9% QoQ higher demands from EGAT and one customer maintenance 1,19 started commissioning in Feb 2016. shut

Slide 45: Rayong Power Plant (SPP): Steam (3/3)
Rayong Power Plant (SPP): Steam (3/3) Click to edit Master title style Quarterly steam sales volume (‘000 tons) Q2/16 VS Q1/16 (QoQ) +18% YoY +12% • Volume : increased by 155 thousand tons or 12% +12% QoQ in Q2/16 resulted from higher demands from 2,795 2,487 existing customer who started commission

Slide 46: Decrease in cost of sales and services
Decrease in cost of sales and services YoY mainly from lower gas price and plant optimization Click to edit Master title style Quarterly cost of sales and services* (THB million) Q2/16 VS Q1/16 (QoQ) • Cost of sales and services in Q2/16 was approximately the same as in Q1/16. • While the sales volu

Slide 47: Natural gas price and consumption
Natural gas price and consumption Click to edit Master title style Quarterly natural gas consumption (‘000 MMBTU) vs. Monthly natural gas price (THB/MMBTU) Apr-15 Jun-16 SPP* 247 Natural gas consumption W.A. Q IPP Q SPP 241 IPP 229 8,944 8,893 7,702 7,768 6,675 6,914 4,492 4,721 3,850 3,952 Q2/15 Q3

Slide 48: Gross profit improved 25% YoY
Gross profit improved 25% YoY, GPM improved to 23% from plant optimization and higher SPP’s sales volume Click to edit Master title style Quarterly gross profit and gross profit margin* (THB million, %) Q2/16 VS Q1/16 (QoQ) • Gross profit in Q2/16 was THB 1,251 million increased by THB 63 million or

Slide 49: Q2/16 EBITDA increased 23% YoY
Q2/16 EBITDA strongly increased by 23% YoY with better EBITDA margin of 19% Click to edit Master title style Quarterly EBITDA and EBITDA margin (THB million, %) Q2/16 VS Q1/16 (QoQ) • EBITDA in Q2/16 was THB 1,056 million increased 19% by THB 17 million or 2% mainly due to the 13% 19% 19% increase i

Slide 50: Net profit for 1H16 increased outstandingly
Net profit for 1H16 for the company increased outstandingly from better operating results and dividend income Click to edit Master title style Quarterly net profit and net profit margin (THB million, %) Q2/16 VS Q1/16 (QoQ) • Net profit for the company in Q2/16 was THB 686 15% million decreased by T

Slide 51: Summary of financial position of GPSC and its subsidiaries
Summary of financial position of GPSC and its subsidiaries Click to edit Master title style Total Assets (THB million) Total Liabilities & Shareholders equity (THB million) +3% +3% 55,983 57,415 55,983 57,415 2,923 Other current 5% 2,958 5% liabilities 14,514 25% Current assets 28% 15,784 27% 14,989

Slide 52: Well-managed debt profile and continuous deleveraging
Well-managed debt profile and continuous deleveraging Click to edit Master title style Debt profile Debt repayment plan Total interest-bearing debt: THB 15,503 million Current portion THB 1,595 million Current portion of long-term loan 10% Jul’16- Jun’17 10% Jul’17-Jun’21 From Jun’21 48% 42% THB 100

Slide 53: Key financial ratios support strong financial position
Key financial ratios support GPSC’s strong financial position Click to edit Master title style Total D/E and Net Debt/ Equity DSCR Earning per share (EPS) ratio (Times) (Times) (Baht/share) 3 2.5 2.13x 2.75x* 2.00x 2.5 2 1.76x 0.58 2 1.5 0.46 1.5 1.05x* 0.39 1 1 0.50x 0.48x 0.50x 0.5 0.5 0.05x 0.09x

Slide 54: Key Takeaway
Thailand Industry Overview P.2 Company Overview P.7 Q2 2016 Significant Events P.16 Project Update P.22 Financial Performance P.38 Key Takeaway P.54 54

Slide 55: Key Takeaway
Key Takeaway Click to edit Master title style GPSC is PTT Group’s Power Flagship. GPSC’s portfolio is mainly in Thailand (one of the current largest consumers), Laos PDR, and potential projects in Myanmar (the emerging and potential consumers of the region) • Reliability Manage • Balance Growth

Slide 56: Thank You
THANK YOU Global Power Synergy Public Company Limited IR Contact 555/2 Energy Complex, Building B Sukittee Chaiyarak Vibhavadi Rangsit Rd. Chatuchak, Bangkok 10900 Pimploy Wichienprakarn Juthamas Singanurak [email protected] Tel. +662 140 4628, +662 140 4691, +662 140 4712 www.gpscgroup.com Disclaime

Slide 57: Appendix
Appendix • Thailand Power Industry Overview o Government Policy & Key Power Authorities • GPSC’s Overview • Other Countries’ Electricity Overview 57

Slide 58: Thai government policy advocates growth of energy and electricity sectors
Thai government policy advocates growth of energy and electricity sectors • Ensure consistency and security of • Improve electricity and energy electricity and energy supply by seeking infrastructure to enhance competitiveness energy from neighboring countries especially in transmission line in regi

Slide 59: Roles and Authorities in Energy Sector in Thailand
Roles and Authorities in Energy Sector in Thailand Ministry of Energy The most significant government energy authority in Thailand. MOE is responsible for energy policy-making as well as overseeing the government agents under related to energy and power industries Energy Policy and Planning Office E

Slide 60: Thailand is the second largest electricity consumer in ASEAN
Thailand is the second largest electricity consumer in ASEAN, with energy consumption growth of 3.3% CAGR in next 20 years • Thailand is the second largest consumer of electricity in ASEAN, second only to Indonesia. • Considering GPSC profile, whose portfolio is mainly in Thailand, Laos PDR, and pot

Slide 61: Thailand's electricity consumption grows with economic growth
Thailand's electricity consumption grows in tandem with economic growth • Historically, Thailand’s electricity power consumption has been driven by economic growth • Thailand’s GDP and Energy Consumption has expanded in tandem, it is forecasted that GDP will grow at 3% CAGR (2016 onwards) and Electr

Slide 62: Roles and Authorities in Energy Sector in Thailand
Roles and Authorities in Energy Sector in Thailand Ministry of Energy The most significant government energy authority in Thailand. MOE is responsible for energy policy-making as well as overseeing the government agents under related to energy and power industries Energy Policy and Planning Office E

Slide 63: Relationship among Energy Authorities
Relationship among Energy Authorities Ministry of Energy Ministry of Finance (MOE) (MOF) While PTT and Department of EGAT are Alternative Energy Policy and Department of Department of State Own under Ministry Energy Planning Office Mineral fuel Energy Business Enterprise (SOE) of energy, Development

Slide 64: Thai government policy advocates growth of energy and electricity sectors
Thai government policy advocates growth of energy and electricity sectors • Ensure consistency and security of • Improve electricity and energy electricity and energy supply by seeking infrastructure to enhance competitiveness energy from neighboring countries especially in transmission line in regi

Slide 65: Most new and retired capacity 2015-2036 from EGAT and IPP
Most of total new and retired power capacity during 2015-2036 are from EGAT and IPP, respectively 6,011 6,133 Total New Capacity 57,459 MW EGAT IPP SPP VSPP Import Unit: MW Thailand's power new capacity 1,843 2,377 4,073 3,949 during 2015-2036 338 271 532 3,339 3,381 700 277 988 1,240 2,774 30 2,823

Slide 66: Appendix
Appendix • Thailand Power Industry Overview o Government Policy & Key Power Authorities • GPSC’s Overview • Other Countries’ Electricity Overview 66

Slide 67: Pricing structure for each type of GPSC's power plant
Pricing structure for each type of GPSC’s power plant GPSC’s Business Portfolio Luangphabang Pricing Structure IPP/Import = Availability Payment + Energy Payment 500 KV Sriracha Investment • Equity Return • Fuel Cost Rachaburi Xayaburi cost • Financing Cost • Variable O&M Power Power Vientiane • Fix

Slide 68: Current Operating Asset (IPP): Sriracha
Current Operating Asset (IPP): Sriracha Sriracha Power Plant Chonburi Province (40 Rai leasehold land) Type Combined cycle Capacity • Electricity: 700 MW • Industrial water: 80 Cu.m/h Customer • Electricity: EGAT 700 MW • Industrial water: Thaioil Power 50 Cu.m/h • Natural Gas – PTT Shareholding Sup

Slide 69: Current Operating Asset (SPP): Rayong CUP1-3
Current Operating Asset (SPP): Rayong – Central Utility Plant 1-3 (CUP1-3) Rayong Power Plant Rayong Province Type Cogeneration Capacity CUP-1 CUP -1 • Electricity: 226 MW • Steam: 890 T/h • Industrial water: 720 Cu.m/h CUP-2 • Cu.m/H Shareholding • Industrial water: 510 Cu.m/h CUP-3 • Steam: 280 T/

Slide 70: Current Operating Asset: CHPP and IRPC-CP Phase 1
Current Operating Asset: Combined Heat and Power Producing IRPC Clean Power Company Limited Co., Ltd. (IRPC-CP Phase 1) Bangkok Province Rayong Province (118 Rai) Type Combined heat and power with district cooling Type Cogeneration (SPP) (VSPP) Capacity* • Electricity: 240 MW Capacity • Electricity:

Slide 71: Current Operating Asset: Thai Solar Renewable and NNEG
Current Operating Asset: Thai Solar Renewable Company Limited Nava Nakorn Elecricity Generating Kanchanaburi and Suphanburi Province Company Limited (NNEG) Pathumthani Province Type Solar Type SPP Cogeneration Capacity • Electricity: 80 MW Capacity • Electricity: 125 MW • Steam: 30 T/h Customer • PE

Slide 72: Current Operating Asset: BIC-1 and RPCL
Current Operating Asset: Bangpa-in Cogeneration Company Ratchaburi Power Company Limited Limited Ratchaburi Province Ayutthaya Province Type Cogeneration (SPP) Type Combined Cycle (IPP) Capacity • Electricity: 117 MW Capacity • Electricity: 1,400 MW • Steam: 5 T/h Customer • EGAT Customer • Electric

Slide 73: Electricity: Operating capacity of 1,376 MW, 546 MW in pipeline
Electricity: Operating capacity of 1,376 MW, with another 546 MW in pipeline Operating MW Under Construction MW Combined heat: Renewable Renewable VSPP 5% 2.3% 0.4% Cogeneration: SPP Combined cycle/ 32% Cogeneration: SPP 1,376 MW 546 MW Hydroelectric 31.2% 63% Combined cycle/ Cogeneration: IPP 66.1%

Slide 74: Operate 1,441 T/h of Steam and 2,080 Cu.m./h of Industrial Water
Operate 1,441 T/h of Steam and 2,080 Cu.m./h of Industrial Water Steam Industrial Water BIC-1 IRPC-CP Sriracha 6.0% NNEG 0.4% 4% 0.6% CUP-3 19.4% CUP-1 CUP-3 35% 37% 1,440.7 T/h 2,080 Cu.m/H CUP-1 CUP-2 61.8% 11.8% CUP-2 24% Operating capacity Under construction Operating capacity Name Name (T/h) Ca

Slide 75: Maintenance schedule: Sriracha and Rayong plants
Maintenance schedule: Sriracha and Rayong plants 2016 Plant Tag no. Description Q1 Q2 Q3 Q4 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec CUP-1 H-13701 Aux. Boiler.11 15 3Y 27 N-13901 GTG11 5 HG 18 H-13702 HRSG11 5 3Y 18 N-13902 GTG12 1 FO 31 H-13703 HRSG12 26/06 1Y 02/07 N-13903 GTG13 H-13704 HRS

Slide 76: Maintenance schedule: IRPC-CP
Maintenance schedule: IRPC-CP 2016 Plant Unit Q1 Q2 Q3 Q4 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec IRPC-CP CTG 2B 26/09 A 30/09 HRSG2B 26/09 YI 30/09 Aux. Boiler 23/05 YI 27/05 Notes A Level A inspection 5 days YI Yearly inspection 5 days 76

Slide 77: Ratio Formula
Ratio Formula Ratios Formula Gross profit Gross profit margin Revenue from sales of goods and service + Revenue from finance lease Net profit Net profit margin Total Revenue Total Debt to Equity Total liabilities Total shareholder’s equity Interest bearing debts – (Cash and cash equivalents + Restri

Slide 78: Appendix
Appendix • Thailand Power Industry o Government Policy & Key Power Authorities • GPSC’s Overview • Other Countries’ Electricity Overview 78

Slide 79: Myanmar's electricity consumption expected to grow at 13% CAGR
Myanmar’s electricity consumption is expected to grow at 13% CAGR, in line with its growing GDP • Myanmar’s electricity power consumption has historically increased in line with the GDP; the forecasted electricity power consumption of 13% CAGR (2016-2031) is therefore driven by the forecasted GDP gr

Slide 80: Myanmar: Hydro increasingly essential in electricity generation
Myanmar: Hydro will be increasingly essential in electricity generation, followed by Natural Gas and Coal • According to Myanmar’s Power Development Plan (2016-2031,) it is anticipated that Myanmar will be able to generate 29,189MW of electricity by 2031, which accounts for 7.4% CAGR from current ca

Slide 81: Lao's electricity consumption expected to grow at 8% CAGR
Lao’s electricity consumption is expected to grow at 8% CAGR • Historically, Lao’s electricity power consumption grew at 14% CAGR, resulting from the high economic growth. • Given higher economic growth in the future, It is expected that the consumption of electricity will continue to increase at 8%

Slide 82: Lao: Hydro will continue to dominate electricity generation
Lao: Hydro will continue to dominate the electricity generation, while overall concentration is towards renewable energy • According to Lao’s Power Development Plan (2015-2025,) it is obvious that the country will expand the electricity generation towards renewable energy sector. • The capacity is e