Production and Sales (Quantity) Quarter ended Six Months Ended Year Ended Particulars Unit 30.09.2018 30.06.2018 30.09.2017 30.09.2018 30.09.2017 31.03.2018 Urea‐ Production Lakhs/ MT 5.31 5.53 5.59 10.84 9.84 20.93 Urea‐ Sale Lakhs/ MT 5.66 6.41 5.62 12.07 10.70 20.74 DAP / NPK Sale Lakhs/ MT 2.43
Slide 5: Financial Performance from Continuing Operations
Financial Performance from Continuing Operations * * After considering Rs.392 Crore towards provision for diminution in value of investment. Page 4 of 9 www.chambalfertilisers.in
Slide 6: Subsidy Receipt
Subsidy Receipt (Rs. in Crores) Six Months Ended Year Ended Particulars 30.09.2018 30.09.2017 31.03.2018 Urea 1672.75 972.26 2,811.71 P&K # 808.97 1016.69 1397.01 Other Misc 0.05 11.62 18.83 Total 2,481.78 2,000.57 4,227.55 # This includes Rs.383.73 crores received during the financial year 2017-18
Slide 7: Subsidy Outstanding
Subsidy Outstanding (Rs. in Crores) As at As at As at Particulars 30.09.2018 30.09.2017 31.03.2018 Urea 1852.88 1335.89 1,464.30 P&K 658.52 785.49 868.72 Other Misc. 32.08 36.39 30.65 Total 2,543.49 2,157.77 2,363.67 Page 6 of 9 www.chambalfertilisers.in
Slide 8: Loan Outstanding
Loan Outstanding (Rs. in Crores) As at As at Particulars 30.09.2018 30.09.2017 31.03.2018 Long term Loan ‐ Fertilisers 175.00 ‐ 175.00 Long term Loan ‐ new Urea Project 3,868.52 2,007.59 2,981.48 Working Capital Loan 3,065.41 2,848.48 2,452.18* Total 7,108.93 4,856.08 5,608.66 *After exclusion of Rs
Slide 9: New Urea Project – Progress Status
New Urea Project – Progress Status Pre-commissioning activities like cooling water flushing, air blowing and steam blowing are complete. Commissioning of Urea and Ammonia Plant is in progress. Offsite and utility facilities have been commissioned and are operational. New gas metering station a
Slide 10: Thank You
Thank You Page 9 of 9 www.chambalfertilisers.in
Source: NSE filing, Oct 29, 2018