Slide 1: The Oil & Gas Conference EnerCom Denver August 2010
The Oil & Gas Conference EnerCom Denver 25 August 2010

Slide 2: Forward-looking statements and SEC reserves cautionary note
2 This is an oral presentation which is accompanied by slides. Investors are urged to review our SEC filings. This presentation contains certain forward-looking statements regarding various oil and gas discoveries, oil and gas exploration, development and production activities, anticipated and poten

Slide 3: Endeavour at a Glance
3 Endeavour at a Glance Endeavour Acreage Endeavour Production Endeavour Developments Significant US position in unconventional shale plays Excellent results from first US wells More in process Four valuable development projects in the UK North Sea West Rochelle appraisal to spud end of month at no

Slide 4: Reserves
4 Reserves Source: Prepared by Netherland, Sewell & Associates, Inc. in 2007 & 2008; Audited by Netherland, Sewell & Associates, Inc. in 2009 2009 reserve replacement is 980% on 2P basis Extensions, discoveries and upward revisions to prior estimates and purchases added 13.7 MMBOE during 2009, prima

Slide 5: Existing Opportunities Have Potential to Deliver Strong Production
Existing Opportunities Have Potential to Deliver Strong Production 2009 2015 Potential Production Growth 5

Slide 6: Endeavour Assets - US Portfolio
Montana Frontier Marcellus Haynesville & Cotton Valley Alabama Frontier New Mexico South Texas 6 Endeavour Assets - US Portfolio

Slide 7: Shale Gas Plays are lower cost & more sustainable
Shale Gas Plays are lower cost & more sustainable 7 "Breakeven" defined as realized wellhead price where NPV10% = 0 (ROR = 10%) Source: BENTEK Energy LLC

Slide 8: The Haynesville Project - Overview
The Haynesville Project - Overview Acquired five distinct prospects - Four in Haynesville / One in Cotton Valley 18,450 gross acres (7,790 net acres) 200 + future drilling locations Avg Well Cost: $ 8-9 million gross Avg EUR per Well: 7-8 BCF gross Avg IP per Well: 15 MMCFD gross Produced nearly 1,7

Slide 9: Cohort / END Joint Acreage
Cohort / END Joint Acreage 9 Source: EOG Resources Haynesville/Bossier Potential

Slide 10: Haynesville Shale - Louisiana
Area operators have reported very robust well results from Haynesville Shale completions 13,500 acres well positioned in the most prolific area of the Haynesville play First two wells at Woodardville Prospect are outstanding successes Initial rates ~ 21 MMCFD (Indigo Minerals & Batchelor) Indigo Min

Slide 11: Distribution of Initial Potential Flow Rates
Distribution of Initial Potential Flow Rates 11 Our two Haynesville completions are in the top 10-percentile of productivity!

Slide 12: The Marcellus Project - Overview
The Marcellus Project - Overview END acquired 50% in Cohort 48,300 gross acres over six Marcellus prospects in western Pennsylvania 300+ future drilling locations All Cohort operated END prospects are well situated Gas transmission lines near each project area Proximity to East Coast markets yields

Slide 13: Western PA Area - Industry Highlights
Western PA Area - Industry Highlights Isaiah Prospect Jonah Prospect Daniel Prospect Malachi Prospect Samuel Prospect Ruth Prospect EXCO Resources Drilled 2 horizontal wells 1.0 to 2.6 MMCFD IP (Centre Co.) Acreage is beginning to increase in activity (currently bracketed by most active parts of the

Slide 14: Alabama Frontier Gas Shale Play - Overview
Greene County After Pashin, 2008 Alabama Frontier Gas Shale Play - Overview 14 Paleozoic Shale Conasauga Shale (Cambrian) Neal (Floyd) Shale (Mississippian) 50/50 "heads up" venture with Hillwood effective January 5, 2010 "First Mover" position in frontier gas shale play 50% interest in 160,000 gros

Slide 15: Montana Frontier Oil Shale Play - Overview
Montana Frontier Oil Shale Play - Overview 25% "heads up" working interests with two independent Montana producers 300,000 gross acres (75,000 net to END) Frontier oil shale play - multiple targets 900 potential drilling locations Initial cost of entry $4 million JV Area 15

Slide 16: Endeavour Assets - UK North Sea
Endeavour Assets - UK North Sea 16 Rubie Renee

Slide 17: Current North Sea Developments
17 Current North Sea Developments Name Current Working Interest Estimated Reserves (gross) Development Plan First Production Bacchus 10.0% 15 - 20 MMBOE FDP Approved. Three well sub-sea tieback to Forties Alpha. 2011 Greater Rochelle 55.6% 50 - 70 MMBOE FDP filed. Appraisal drilling at West Rochelle

Slide 18: Bacchus Development - UK Block 22/6a
18 BACCHUS DEVELOPMENT Operator: Apache 70% Partner: Endeavour 10% Shell 20% FDP: Approved June 2010 Online: 2011 Discovery well 22/6a-14 was drilled in 2005, followed by a downdip sidetrack 22/6a-14Z, which tested at 1000 BOPD from upper part of the reservoir. In 2006, 22/6a-15 was drilled in the w

Slide 19: West Rochelle - Significant Expansion Potential
West Rochelle - Significant Expansion Potential 10km N West Rochelle 19 Exploration well 15/26b-M to spud Q3 2010 Endeavour retains 50% of 15/26c Fully carried for cost of appraisal well Could add significant reserves to Rochelle development

Slide 20: Cygnus Expansion: 2009 - 2010
Appraisal well 44/12a-5 drilled in Q2 2010 Flowed at 29MMCFD Leman came in better than predicted Appraised areas in red Cygnus Expansion: 2009 - 2010 2009 Cygnus Field Appraisal well 44/11a-4 drilled in Q1 2010 Field boundary extended to the north and west Common field-wide gas water contact establi

Slide 21: Columbus Development - UK Block 23/16f
21 Columbus Development - UK Block 23/16f COLUMBUS DEVELOPMENT Operator: Serica 50% Partners: Endeavour 25% EOG 25% FDP: Filed October 2008 Online: 2012 Columbus has gas trapped stratigraphically in a Paleocene channel on the western flank of the Magellan structure. The prospect was identified using

Slide 22: Financing Strategy
Never take on more capital at a higher cost than absolutely needed Phased approach New facility is step one One more step puts all the necessary capital in place to turn all the projects on Likely high-yield next year mid-year Developments improve metrics and reduce capital costs Bacchus comes on an

Slide 23: Conclusion
23 Balanced strategy with experienced global team in place - UK North Sea and US Onshore US portfolio success gives attractive near-term production growth Significant value exists in UK assets- Greater Rochelle and Cygnus keep growing Disciplined management with prudent development strategy Multiple
Source: SEC EDGAR · 8-K filed Aug 26, 2010
More decks from Endeavour International Corp
Presentation (May 2015)5 slides · May 7, 2015
Corporate Update (February 2015)23 slides · Feb 27, 2015
Debt Investor Presentation (October 2014)16 slides · Oct 14, 2014