Chubu Electric Power Company,Incorporated · TSE:9502
Chubu Electric Power Company,Incorporated — Q3 FY2017 Earnings Presentation
51 slides from Chubu Electric Power Company,Incorporated's earnings presentation, February 2018

Slide 1: Presentation Materials for Investors 3rd Quarter FY2017
Presentation Materials for Investors 3rd Quarter FY2017 February, 2018

Slide 2: INDEX
INDEX 01 Outline of Financial Results for 03 Management Situation Nine-Months ended December 31, 2017 Mid-term Target toward the Achievement of Summary of Financial Results ҩҩҩҩ01 ‟What We Aim For“ (Initiatives for Management Issues) ҩҩҩҩ19 Electrical Energy Sold ҩҩҩҩ04 Development of High Efficienc

Slide 3: Outline of Financial Results for Nine-Months ended December 31, 2017
01 Outline of Financial Results for Nine-Months ended December 31, 2017 Note: The company’s fiscal year (FY) is from April 1 to March 31 of the following year. FY2017 represents the fiscal year begun on April 1, 2017, and ending on March 31, 2018. 3rd Quarter(3Q) represents nine months period ended

Slide 4: Summary of Financial Results <1>
01 Summary of Financial Results <1> Operating revenues (consolidated and non-consolidated) increased following 2014/3Q, for the first time in 3 years. Ordinary income (consolidated and non-consolidated) decreased for 2 consecutive years since 2016/3Q. We recorded increased sales and decreased

Slide 5: Summary of Financial Results <2>
02 Summary of Financial Results <2> <Consolidated Operating Revenues> Operating revenues increased by 164.0 billion yen compared with 2016/3Q, mainly due to an increase in fuel cost adjustment charge, and an increase in surcharge and grant based on Act on Special Measures Concerning Procurement of

Slide 6: Summary of Financial Results <3>
03 Summary of Financial Results <3> <Consolidated Ordinary Income> Consolidated ordinary income decreased by 41.2billion yen compared with 2016/3Q, mainly due to a conversion of income incurred by fuel cost adjustment system time lag into loss. [Factors contributing to change in consolidated ordin

Slide 7: Electrical Energy Sold
04 Electrical Energy Sold <Electrical Energy Sold> 凑 Dropped by 0.6% to 88.8TWh, compared with 2016/3Q, mainly due to an effect of switches made to other operators with the intensified competition , in spite of an increase of production in the automobile and semiconductor industry, in addition to a

Slide 8: Electric Power Supplied
05 Electric Power Supplied <Electric Power Supplied> Hydro : The flow rate fell short of 2016/3Q ; thus hydroelectric power output decreased by 0.2TWh. Interchanged, purchased power : Increased by 1.1TWh, mainly due to an increase in purchase of renewable energy. Thermal : As a result of a dec

Slide 9: (Reference) Impact of Accrued Income by Fuel Cost Adjustment System (Result)
06 (Reference) Impact of Accrued Income Incurred by Fuel Cost Adjustment System (Result) <FY2016/3Q> <FY2017/3Q> Income Loss 32.0 billion -12.0 billion Average Fuel price Fuel procurement price (basis of fuel cost adjustment charge) (basis of fuel cost) Copyright © CHUBU Electric Power Co.,Inc. All

Slide 10: Summary of Forecast for FY2017 <1>
07 Summary of Forecast for FY2017 <1> <Forecast>Revised Forecasts of Financial Results previously announced on October 27, 2017. ٹOperating revenues (consolidated) will increase mainly due to an increase in electricity sales volume and fuel cost adjustment charge. ٹOrdinary income (consolidate

Slide 11: Summary of Forecast for FY2017 <2>
08 Summary of Forecast for FY2017 <2> [Principal figures] (TWh,%) Current October 27 Change (Electrical energy sold) (A) (B) (A-B) (A-B)/B Low voltage 38.0 37.7 0.3 0.8 High voltage / Extra-high voltage 82.3 81.6 0.7 0.8 Total 120.3 119.3 1.0 0.8 (Other principal figures) Current October 27 CIF pric

Slide 12: (Reference) Impact of Fuel Cost Adjustment System in FY2017 (Forecast)
(Reference) 09 Impact of Accrued Income Incurred by Fuel Cost Adjustment System in FY2017 (Forecast) ٛFY2016ٜ ٛFY2017ٜ Income Loss 6.0 billion -25.0 billion Average Fuel price Fuel procurement price (basis of fuel cost adjustment charge) (basis of fuel cost) Copyright © CHUBU Electric Power Co.,Inc.

Slide 13: Reference Data(1): Financial Results
02 Reference Data(1): Financial Results Copyright © CHUBU Electric Power Co.,Inc. All Right Reserved.

Slide 14: Consolidated Statements of Income
10 Consolidated Statements of Income (Rounded down to nearest 100 million yen.) (Billion yen,%) 2017/3Q 2016/3Q Change (A) (B) (A-B) (A-B)/B Operating revenues 2,062.7 1,898.7 164.0 8.6 Non-operating revenues 16.0 13.9 2.0 15.0 Ordinary revenues 2,078.7 1,912.6 166.1 8.7 Operating expenses 1,937.8 1

Slide 15: Non-consolidated Statements of Income <1>: Operating Revenues
11 Non-consolidated Statements of Income <1>: Operating Revenues (Rounded down to nearest 100 million yen.) (Billion yen,%) 2017/3Q 2016/3Q Change 岧Major factors for change岨 (A) (B) (A-B) (A-B)/B 凑 An increase in fuel cost adjustment Electricity sales revenues 1,564.5 1,488.0 76.4 5.1 charge 凑 An in

Slide 16: Non-consolidated Statements of Income <2>: Operating Expenses
12 Non-consolidated Statements of Income <2>: Operating Expenses (Rounded down to nearest 100 million yen.) (Billion yen,%) 2017/3Q 2016/3Q Change 岧Major factors for change岨 (A) (B) (A-B) (A-B)/B Salaries and employee benefits 135.7 131.2 4.5 3.4 凑 An increase in fuel price Fuel 514.3 416.5 97.8 23.

Slide 17: Non-consolidated Statements of Income <3>: Net Income
13 Non-consolidated Statements of Income <3>: Net Income (Rounded down to nearest 100 million yen.) (Billion yen,%) 岧Major factors for change岨 2017/3Q 2016/3Q Change (A) (B) (A-B) (A-B)/B Operating income 111.9 155.3 (43.4) (28.0) 凑 Electricity business : -38.7 凑 Incidental business : -4.7 Non-opera

Slide 18: Consolidated and Non-consolidated Financial Standing
14 Consolidated and Non-consolidated Financial Standing (Rounded down to nearest 100 million yen.) (Billion yen) 2017.12 2017.3 Change (A) (B) (A-B) 5,423.3 5,412.3 11.0 Assets <4,922.9> <4,956.5> <(33.5)> 3,619.7 3,687.5 (67.8) Liabilities <3,454.7> <3,535.9> <(81.2)> 1,803.6 1,724.7 78.8 Net asset

Slide 19: Electricity Business Operating Expenses (Non-consolidated)
15 Electricity Business Operating Expenses (Non-consolidated) قBillion yenك Salaries and employee benefits Fuel Purchased power Maintenance Depreciation Other 3,000.0 2,709.7 2,638.2 (6%) 2,457.1 (7%) 2,500.0 2,297.3 (7%) 2,317.3 2,231.7 2,136.8 (9%) (8%) 2,037.3 1,982.9 (8%) 2,000.0 (9%) (7%) 1

Slide 20: Cash Flow (Consolidated)
16 Cash Flow (Consolidated) ق%LOOLRQ\HQك Cash Flows from Operating Activities Cash Flows from Investing Activities FCF 800.0 600.0 562.4 539.1 471.9 449.7 476.8 400.0 358.8 335.0 254.4 227.6 194.0 200.0 113.6 176.8 203.7 296.7 199.2 143.7 0.0 (25.1) (70.2) (102.9) (62.8) (200.0) (215.1) (272.7)

Slide 21: Fund Raising
17 Fund Raising We raised total approximately 1,500 billion yen in long-term funding for 3 years since the shutdown of Hamaoka Nuclear Power Station. We raised 390 billion yen in long-term funding in FY2016. We forecast to raise approximately 300 billion yen in long-term funding in FY2017. 900

Slide 22: Financial Ratio, Credit Ratings
18 Financial Ratio, Credit Ratings [Shareholders’ equity ratio] [Debt-Equity ratio] Times 35.0 3.0 Non-Consolidated Consolidated Non-Consolidated Consolidated 30.0 31.1% 2.5 (Consolidated) 25.0 2.0 1.9 Times 20.0 (Non-Consolidated) 28.7% 1.5 15.0 (Non-Consolidated) 1.0 10.0 1.6 Times 0.5 (Consolidat

Slide 23: Management Situation
03 Management Situation Copyright © CHUBU Electric Power Co.,Inc. All Right Reserved.

Slide 24: Mid-term Target toward the Achievement of "What We Aim For"
Mid-term Target toward the Achievement of ‟What We Aim For” 19 (Initiatives for Management Issues) Chubu electric 凑 As a leading company that provides services that exceed expectations to Power Group customers ahead of our competitors, we will aim to become a ‟total “What We Aim For ” energy service

Slide 25: Development of High Efficiency Thermal Power Plants
㻝㻡 20 Development of High Efficiency Thermal Power Plants [Outline of development of Nishi-Nagoya (Reference) Development schedule (FY) Thermal Power Plant Unit No.7] Output (at the generation end) 2,376 MW 2013 2014 2015 2016 2017 2018 ҩҩҩҩҩ 2021 Thermal efficiency (LHV basis) Approx. 62% ٽMar.-1

Slide 26: Business Expansion of JERA
21 Business Expansion of JERA TEPCO Fuel & Power, Incorporated and Chubu Electric established “JERA Co., Inc.”, as a new company that implements “a comprehensive alliance covering the entire energy supply chain, from upstream fuel and procurement through power generation.” After establishing JERA,

Slide 27: Expansion of Total Energy Services
22 Expansion of Total Energy Services Taking full liberalization of entry to gas business from April 2017 as an opportunity, gas has begun to be sold to household customers in addition to conventional customers for industrial use and business use. With competitive procurement capacity of JERA as

Slide 28: Safety Improvement Measures on Hamaoka Nuclear Power Station <Onsite>
23 Safety Improvement Measures on Hamaoka Nuclear Power Station <Onsite> Major construction works at Unit 4 have been completed excluding some construction works including re-examination of construction work details based on the situation in the field. We are presently undergoing inspections by th

Slide 29: Safety Improvement Measures on Hamaoka Nuclear Power Station <Offsite>
24 Safety Improvement Measures on Hamaoka Nuclear Power Station <Offsite> Offsiteقoutside of the power plant siteك Mutual cooperative systems On March 7, 2017, Chubu Electric Power concluded an agreement As preparation for nuclear disasters, coordination with the on mutual technical cooperation

Slide 30: Efforts for Development of Business Structure that can Adapt to Change of Environment
Efforts for Development of Business Structure that can Adapt to Change 25 of Environment [Reinforcement of business foundation utilizing ICT and expansion of business areas] ICT such as IoT, big data and AI will be utilized for reinforcement of business foundation, and examinations will be made fo

Slide 31: Reference Data (2): Management Information
04 Reference Data (2) : Management Information Copyright © CHUBU Electric Power Co.,Inc. All Right Reserved.

Slide 32: Schedule of the Electricity and Gas System Reform
26 Schedule of the Electricity and Gas System Reform [Schedule of the electricity system reform] Schedule for Schedule for implementing the measures Enacted the bill 3rd phase: Enacted on Further securing the neutrality of the power transmission/distribution In April 2020 June 17, 2015 sector throug

Slide 33: Initiatives of JERA <1>
27 Initiatives of JERA <1> JERA will expand business based on investment profits from each business and profits generated from the optimization of the value chain. ¾ We will divide the value chain from the securing of interests of energy resources to procurement, transportation, gas supply and pow

Slide 34: Initiatives of JERA <2>: Type of Business
28 Initiatives of JERA <2> : Type of Business [Fuel business (Upstream, procurement, transportation, trading)] Optimum portfolio is create using the world’s largest procurement scale and trading, and fuel procurement that can flexibly respond to change of business environment in the future is realiz

Slide 35: (Reference) Overseas IPP and Fuel Projects of JERA Group
29 (Reference) Overseas IPP and Fuel Projects of JERA Group (As of January, 2018) Canada • Goreway Gas Thermal IPP Netherlands • Rietlanden Coal Terminal Oman US U.A.E. • Sur Gas Thermal IPP • Tenaska Gas Thermal IPP • Umm Al Nar Gas Thermal IWPP Taiwan • Carroll County Gas Thermal IPP India • Chang

Slide 36: Sales Strategy <1>: Optimum Proposal of Gas & Electric Power
30 Sales Strategy <1> : Optimum Proposal of Gas & Electric Power We arranged seven gas tariff menus, i.e. the KatEne Gas Plan for households and the BizEne Gas Plan geared toward businesses. They have been set at prices lower than the gas tariff menu offered by Toho Gas*. * There are some cases th

Slide 37: Sales Strategy <2>: Gas Sales Framework
31 Sales Strategy <2> : Gas Sales Framework In 2001, Chubu Electric Power launched a natural gas sales operation geared towards large factories, harnessing its own pipelines. The company has since then been taking incremental steps to strengthen and expand its gas business. We started to sale ga

Slide 38: Sales Strategy <3>: Electricity Sales Framework in the Tokyo Metropolitan Area
32 Sales Strategy <3> : Electricity Sales Framework in the Tokyo Metropolitan Area [Electricity tariff menu in the Tokyo metropolitan area (KatEne Plan) ] ⋇ Top-class low price ¾ Discount rate is 5-10% (KatEne point included) compared with TEPCO Energy Partner’s existing menu. Features ⋈ Benefit ari

Slide 39: Sales Strategy <4>: Enhancement of Points of Contact with Customers
33 Sales Strategy <4> : Enhancement of Points of Contact with Customers ٛLow voltage ٜ Various services with high added values that contribute to convenient and comfortable life as “daily-life coordinator” are developed and provided. ٛHigh voltage嵣Extra-high voltage ٜ Total energy solution is pr

Slide 40: Hamaoka Nuclear Power Station <1>: The State of Power Station
34 Hamaoka Nuclear Power Station <1> : The State of Power Station For Unit 4, application for review for checking conformity to New Regulatory Standards was submitted on February 14, 2014. For Unit 3, application for review for checking conformity to New Regulatory Requirements was submitted on Ju

Slide 41: Hamaoka Nuclear Power Station <2>: Progress of NRA Review
Hamaoka Nuclear Power Station <2> : Progress of the Nuclear Regulation 35 Authority’s Review to Verify Compliance with the New Regulatory Standards As to Unit No.4, the application form for Change in reactor establishment permission that we submitted has been reviewed by the Nuclear Regulation Aut

Slide 42: Hamaoka Nuclear Power Station <3>: Seawater Inflow via Damaged Tubes
Hamaoka Nuclear Power Station <3> : Seawater Inflow via Damaged Tubes 36 in the Main Condenser for Hamaoka Reactor No.5 [Fact] - On May 14, 2011, when preparing for cold shutdown after reactor No. 5 was suspended, a portion of the tubes in the main condenser, through which seawater flowed to cool st

Slide 43: Hamaoka Nuclear Power Station <4>: Dialogue with Local Residents
Hamaoka Nuclear Power Station <4> : 37 Activities to Take Part in Dialogue with Local Residents On the Hamaoka Nuclear Power Station, we have been steadily promoting further safety measures including facilities measures and disaster prevention measures together with gaining public understanding as

Slide 44: Composition of Power Sources and Electric Power Output (FY2016)
38 Composition of Power Sources and Electric Power Output (FY2016) Based on energy mix of Japan, aim for optimum composition of power sources by combining various types of power source, such as nuclear power, thermal power and renewable energy, in a well-balanced manner from the standpoint of “S+3

Slide 45: Responses to Global Warming ~ Reduction of CO2 Emissions ~
39 Responses to Global Warming ~ Reduction of CO2 Emissions ~ Japanese government set up the target of reducing greenhouse gas emissions (26% reduced by FY2030) as Japan’s goal of the Paris Agreements, and decide the proportion of nuclear power generation and renewable energy(Non-fossil energy sou

Slide 46: Renewable Energy <1>: Our Efforts toward Promotion
40 Renewable Energy <1>: Our Efforts toward Promotion (As of the end of December, 2017) (Reference) Development locations of hydroelectric power station Chubu Electric Chubu Electric Group Conventional hydro operating 196 Site : 5,455MW Akigami : 0.29MW(FY2016) Generation with minimum water level Pa

Slide 47: Renewable Energy <2>: Actions for Expansion of Introduction of Renewable Energy
Renewable Energy <2>: 41 Actions for Expansion of Introduction of Renewable Energy To realize energy mix of Japan, take actions for expansion of introduction of renewable energy such as efforts for adjusting supply and demand in a wide range for change of output of renewable energy and efforts for

Slide 48: Reinforcement of the Frequency Converter (FC)
42 Reinforcement of the Frequency Converter (FC) In order to stably supply electricity when power outage occurs in a wide range due to stoppage of large-scale power source, efforts will be made to increase FC by 900 MW to a total of 2,100 MW in FY2020 so that lending of electricity between regions

Slide 49: Reinforcement of Business Foundation Utilizing ICT and Expansion of Business Areas
Reinforcement of Business Foundation Utilizing ICT and 43 Expansion of Business Areas ICT such as IoT, big data and AI will be utilized for reinforcement of business foundation, and examinations will be made for provision of new services. [Main efforts utilizing IoT] Power network Communications n

Slide 50: DISCLAIMER
DISCLAIMER This presentation contains assumptions and forward-looking statements with respect to the financial conditions, and forecasts of the company, which are based on information currently available. These assumptions involve certain risks and uncertainties, and may cause actual results materia

Slide 51: Copyright © CHUBU Electric Power Co.,Inc. All Right Reserved.
Copyright © CHUBU Electric Power Co.,Inc. All Right Reserved.
Source: Internet Archive copy of chuden.co.jp
More decks from Chubu Electric Power Company,Incorporated
Q2 FY2026 Earnings Presentation59 slides · Oct 29, 2026
H1 FY2026 Earnings Presentation26 slides · Oct 29, 2026
Q2 FY2026 Earnings Presentation26 slides · Oct 29, 2026
Q1 FY2026 Earnings Presentation44 slides · Jul 29, 2026
Q1 FY2026 Earnings Presentation21 slides · Jul 29, 2026
FY2025 Earnings Presentation21 slides · Apr 28, 2026