Slide 3: Wyoming Operations
Wyoming Operations 3

Slide 4: Building Shareholder Value
Building Shareholder Value Building Shareholder Value 4 Niobrara Shale Play Midstream Pipeline Atlantic Rim CBM and Pinedale Anticline

Slide 5: Niobrara Shale Acreage
5 Niobrara Shale Acreage Powder River Basin Greater Green River Basin DJ Basin WR Basin 20+ miles of 3D Seismic reprocessed in Catalina Unit + acquired 2 D Heavy natural fracturing based on well data Existing historical Niobrara production adjacent to Atlantic Rim Approximately 18.9% of Atlantic Rim

Slide 6: Niobrara Shale Central Wyoming & Colorado
6 Niobrara Shale Central Wyoming & Colorado Recent Activity Quicksilver and Shell establish an AMI in Sand Wash Basin to develop ~850,000 acres of Niobrara potential. Three wells have been permitted Entek and East Resources establish an AMI in Sand Wash Basin of Wyoming to develop ~ 87,000 acres of

Slide 7: Niobrara Shale Central Wyoming & Colorado
7 Niobrara Shale Central Wyoming & Colorado Source: Entek Energy

Slide 8: Niobrara Shale-Atlantic Rim Appraisal Well
Niobrara Shale-Atlantic Rim 8 Niobrara Shale Play-Appraisal Well * Initial test well completed in Q1 2013 * 24 hour IP rate of 467 BOE * API density consistent with WTI * Significant amount of Atlantic Rim acreage HBP * 1,500' of pay; Multiple Benches * DBLE has 95 % WI in well * 825 Potential Drill

Slide 9: Proven Execution Cont. Cost Control
9 Proven Execution Cont. Cost Control Low cost growth through the drill bit F&D Costs three year weighted average of $ 0.87 Mcfe; 2012 Production Costs, including taxes--$ 1.46 per Mcfe G&A Costs equals 16 % of revenues; among lowest of peer group with revenues < $150 million Based upon the Global H

Slide 10: Building Shareholder Value
Building Shareholder Value Building Shareholder Value 10 Pinedale Anticline * Interest in 184 producing wells * 26% of proved reserves * 260+ future potential wells * Operated by QEP Midstream Pipeline * 12.5 miles of transportation assets * 20% utilized * Ability to expand North to WIC Atlantic Rim

Slide 11: Atlantic Rim Project in the Greater Green River Basin
Atlantic Rim Project in the Greater Green River Basin 11 270,000 Acres 1,800 CBM and 200 conventional wells approved by BLM for development over a 20 year program Project is in its early life with 283 wells drilled since 2007 Over pressured, high gas content distinguishes it over other CBM projects

Slide 12: Historical drilling activity and 2013 planned activity
12 Historical drilling activity Catalina Unit 83 gross (64 net) wells ~175 total potential future drilling locations 52.6 Bcfe net proved reserves (based upon forward strip pricing at 12/31/2012) Spyglass Hill Unit (including former Sun Dog/Doty Mnt Units) 200 gross (46.9 net wells) ~1,225 total pot

Slide 13: Pinedale Anticline
13 Pinedale Anticline

Slide 14: Midstream Infrastructure
Midstream Infrastructure Growing source of fee-based revenue that is independent of gas prices Connects Catalina Unit to interstate pipeline 100% owned by Double Eagle 125 MMcf/d capacity; currently at ~30 MMcf/d Tie-in to third party production and transportation agreement in place Own permits to e

Slide 15: Proven Execution Reserve Growth 2003-2012
15 Proven Execution Reserve Growth 2003-2012 Reserves Prepared by Netherland, Sewell & Associates, Inc. as of December 31 for each respective year. Reserves based upon forward strip pricing as of 12/31/2012 Reserve Replacement Reserve Replacement 2004 2005 2006 2007 2008 2009 2010 2011 2012 2012 (2)

Slide 16: Hedge Contracts
Hedge Contracts 16 Double Eagle Petroleum Double Eagle Petroleum Double Eagle Petroleum Double Eagle Petroleum Double Eagle Petroleum Double Eagle Petroleum Current Hedging Positions Current Hedging Positions Current Hedging Positions Current Hedging Positions Current Hedging Positions Current Hedgi

Slide 17: Summary of Double Eagle Value Proposition
Summary of Double Eagle Value Proposition 17 Reserves (1) Reserves (1) Bcfe $ PV-10 Proved 132.5 162.7 Probable 40.0 23.2 Possible 100.8 118.0 Total 3P Total 3P 273.25 303.9 Gross Locations Gross Acreage Additional Potential Drilling (2) Additional Potential Drilling (2) Additional Potential Drillin

Slide 18: Senior Management
Senior Management Senior Management 18
Source: SEC EDGAR · 8-K filed Aug 14, 2013
More decks from Escalera Resources Company
EnerCom: The Oil & Gas Conference 201420 slides · Aug 20, 2014
IPAA OGIS Toronto 201421 slides · Jun 5, 2014
IPAA Oil & Gas Conference April 201426 slides · Apr 9, 2014
Double Eagle Petroleum — Euro Pacific Global Investment Conference 201318 slides · Sep 3, 2013
Double Eagle Petroleum — OGIS Conference New York 201316 slides · Apr 15, 2013
Double Eagle Petroleum — Investor Presentation (August 2012)18 slides · Aug 14, 2012