    Pyrum Innovations AG Eigenkapitalforum Pyrum Innovations AG November 2023

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer This presentation contains statements about future developments based on current expectations, assumptions, estimates and predictions by management and on information currently available. Various known and unknown risks, unforeseeable developments, changes in the economic and political en

  3. Slide 3: Global End-of-Life-Tire (ELT) market accounts for approx. 30.9 mt p.a.

    Slide 3: Global End-of-Life-Tire (ELT) market accounts for approx. 30.9 mt p.a.

    Global End-of-Life-Tire (ELT) market accounts for approx. 30.9 mt p.a. … as the tightening of the regulatory environment forces countries and corporates to take action Global ELTs in 2019 Tightening regulatory environment Kuwait’s tire graveyard with over 7 million dead tires is frequently on fire L

  4. Slide 4: Pyrum offers patented technology with strong value proposition

    Slide 4: Pyrum offers patented technology with strong value proposition

    Pyrum offers patented technology with strong value proposition… … converting rubber into several high value chemical products – thermolysis oil, carbon and gas How Pyrum creates value NEW NEW 4

  5. Slide 5: Our history in short

    Slide 5: Our history in short

    Our history in short Key milestones Phase 4: Industrial Phase 2: Industrialisation Phase 3: Problem Solving Phase 1 : Prototype Production Phase5: Roll – Out and new Constuction 1ST Industrial Solving all the issues of a new developments Scale 1:3 Building and testing Beginning of 24/7 operation Pla

  6. Slide 6: LCA: Life Cycle Assessment

    Slide 6: LCA: Life Cycle Assessment

    LCA: Life Cycle Assessment Results better than expected Explanation LCA graph Fraunhofer • The LCA has been made by Fraunhofer Institute between May and September 2022 • The results come from the Pyrum pyrolysis process only and cannot be compared to other pyrolysis processes • Comparison of the CO2

  7. Slide 7: The last important Milestone to close the loop: rCB

    Slide 7: The last important Milestone to close the loop: rCB

    The last important Milestone to close the loop: rCB No rCB can be sold to the market without those certificates Usually it takes years to get all these certificates • Received certificates in the last 12 months: • Ecovadis: Silver Status • VDA 6.3: Continental, Pirelli, Hankook, Mercedes, BMW • ISCC

  8. Slide 8: Real applications of circularity

    Slide 8: Real applications of circularity

    Real applications of circularity … areas of use that are already in operation VAUDE Outdoor Equipment and Clothing Source: https://www.vaude.com/de-DE/Herren/Beliebt-Neu/Altreifen-Recycling/ Source: https://www.vaude.com/de-DE/Herren/Beliebt-Neu/Altreifen-Recycling/ 8

  9. Slide 9: Real applications of circularity

    Slide 9: Real applications of circularity

    Real applications of circularity … areas of use that are already in operation Schwalbe Recycing System and „THE GREEN MARATHON“ • Already 2.100 bike stores in Germany are participating = almost 1/3 of German market. • The first 100% Pyrum rCB tire was released at the EUROBIKE in June 2023 9

  10. Slide 10: Real applications of circularity

    Slide 10: Real applications of circularity

    Real applications of circularity … areas of use that are already in operation Mercedes-Banz door handles Source: Mercedes Benz Group AG 10

  11. Slide 11: Real applications of circularity

    Slide 11: Real applications of circularity

    Real applications of circularity … areas of use that are already in operation Continental Tires since September 2023 • Solid tires from Continental’s tire plant in Korbach now contain recovered carbon black from end-of-life-tires • By 2050 at the latest, Continental aims to use 100 percent sustainab

  12. Slide 12: Dillingen plant was one industrial production line for end-of-life-tires

    Slide 12: Dillingen plant was one industrial production line for end-of-life-tires

    Dillingen plant was one industrial production line for end-of-life-tires… … and has been running on industrial scale since May 2020 with commercial sales Overview of the operational unit1 Comments 1  Feedstock (end-of-life-tires) and shredding unit: granulating whole tires and separating rubber fro

  13. Slide 13: Dillingen plant consists today of 3 industrial production lines

    Slide 13: Dillingen plant consists today of 3 industrial production lines

    Dillingen plant consists today of 3 industrial production lines for end-of-life-tires… … and here we have the two new lines at the Headquarter in Dillingen/Saar called TAD 2+3 Overview of the new operational unit1 Comments 1  Feedstock (end-of-life-tires) and shredding unit: granulating whole tires

  14. Slide 14: Building Site of Pyrum Unit 2 and 3 in Dillingen

    Slide 14: Building Site of Pyrum Unit 2 and 3 in Dillingen

    Building Site of Pyrum Unit 2 and 3 in Dillingen Impressions Status quo lines 2 + 3 (22.11.2023) 1 year ago 14

  15. Slide 15: Building Site of Pyrum Unit 2 and 3

    Slide 15: Building Site of Pyrum Unit 2 and 3

    Building Site of Pyrum Unit 2 and 3 Impressions New Power Plant and Pyrolysis Unit Details about Pyrum Unit 2 and 3 • Start of Building : November 2021 • Size of Building site: 8.000 m² • Production Capacity: up to 6 Tons of used tires per hour (10.000 tires per day) • Finished Parts of the Consturc

  16. Slide 16: Research & Development

    Slide 16: Research & Development

    Research & Development Result overview from completed projects Funded by Bicycle tire Fahrradreifen recycling Recycling CFRP Recycling Funded by Project: Infinity The project aims at creating, developing, and optimizing a full value chain: Setup of the first collection system for bicycle tires Optim

  17. Slide 17: Extensive project pipeline due to attractive framework conditions

    Slide 17: Extensive project pipeline due to attractive framework conditions

    Extensive project pipeline due to attractive framework conditions Demand is higher than capacity; projects are partly far advanced or have been started procedurally Project status Project General Terms Contract / Pre- Building site Authorisation in Operative Company Country Partner/Site 20% Capital

  18. Slide 18: Attractive plant economics is the enabler for the rapid roll-out

    Slide 18: Attractive plant economics is the enabler for the rapid roll-out

    Attractive plant economics is the enabler for the rapid roll-out Estimated plant economics – operating at 20,000 tonnes p.a. capacity Roll Out breakthrough: 1 Total revenues, end-products and gate fee EUR ~ 11.5 m NEWS: NEW CONTRACT WITH BASF signed 15.11.2023 Gate fee EUR 110/ton x 20,000 tons EUR

  19. Slide 19: Pyrum Consolidated Income Statement 1st January – 30th September 2023

    Slide 19: Pyrum Consolidated Income Statement 1st January – 30th September 2023

    Pyrum Consolidated Income Statement 1st January – 30th September 2023 Overview KPI 9M 2023 9M 2022 ∆ EUR PL ∆ % PL Revenues 842 714 128 17.89% Increase/decrease of finished goods 52 271 -219 Other own work capitalised 9,828 13,171 -3,343 -25.38% Total output 10,722 14,156 -3,434 -24.26% Other operat

  20. Slide 20: Pyrum Consolidated Balance Sheet (short) 1st January – 30th September 2023

    Slide 20: Pyrum Consolidated Balance Sheet (short) 1st January – 30th September 2023

    Pyrum Consolidated Balance Sheet (short) 1st January – 30th September 2023 Share in capital 9M TEUR 9M 2023 2022 2023 Non-current assets Non-current intangible assets 5,864 6,492 11.8% Property, plant, and equipment 37,821 28,759 76.3% Non-current financial assets 31 37 0.1% 43,716 35,288 Current as

  21. Slide 21: Financial highlights of the growth plan upon implementation of the planned roll-out

    Slide 21: Financial highlights of the growth plan upon implementation of the planned roll-out

    Financial highlights of the growth plan upon implementation of the planned roll-out Economies of scale drive earnings and cash flow Explanation 2022 2028 • Income (gross profit + sale of assets + income from investments) increases from EUR 1 million in 2022 to over EUR 50 million in 2028. Increase i

  22. Slide 22: Investment highlights

    Slide 22: Investment highlights

    Investment highlights Pyrum addresses global environmental problems with revolutionary scalable technology Addressing the global tire waste problem with a patented pyrolysis solution, recycling I rubber into high value products – oil, carbon, gas The Dillingen Plant running on an industrial scale si