CAT Strategic Metals — Chamber of Mines Annual General Meeting 2018
12 slides from CAT Strategic Metals's conference presentation, May 17, 2018
Slide 1: Presentation to the Chamber of Mines
Presentation to the Chamber of Mines Annual General Meeting Victoria Falls – Thursday 17th May 2018 John McTaggart (Managing Director)
Slide 2: Kamativi Lithium Project
Kamativi Lithium Project 17th May 2018 C.O.M. Presentation
Slide 3: Beneficiation of 23Mt Tailings Dump
Beneficiation of 23Mt Tailings Dump
Slide 4: Background
Background Company Founders - involved in the beneficiation of Zimbabwean waste dumps, last five years, using sensor based sorting technologies – namely: ✓ Zimbabwe Alloys Ferrochrome – ferro alloy ✓ Maranatha Ferrochrome – ferro alloy ✓ Alaska Copper Smelter & Refinery – copper matte ✓ Bindura Nick
Slide 5: Initial Grab Sample Campaign
Initial Grab Sample Campaign Zimbabwe Lithium Company (Mauritius/Zimbabwe) MSA Samples Description All data 2017 2016 2015 2017 Number of samples 28 8 8 2 10 Minimum 0.29 0.32 0.38 0.74 0.29 Maximum 1.13 1.13 0.99 0.76 0.75 Mean 0.62 0.61 0.66 0.75 0.56 17th May 2018 C.O.M. Presentation
Slide 6: Heavy Liquid Separation Test Work
Heavy Liquid Separation Test Work ✓ Spodumene is well liberated in the HLS sinks fraction: ✓ +/- 95% of the particles are more than 80% liberated ✓ Relatively large component of HLS floats are well liberated in the floats fraction: ✓ +/- 61% of the spodumene particles characterised by liberation in
Slide 7: Objectives – Phase 1 & 2
Objectives – Phase 1 & 2 Phase 1 Phase 2 ✓ NI 43 – 101 Resource Statement – commenced ✓ Install, commission and operate 2nd 200 tph DMS plant March 2018 / completed by June 2018 ✓ Install, commission and operated 400 tph flotation plant ✓ Bulk test work – finalise flow sheet for 200 tph DMS – produc
Slide 8: Phase 1 - Current Drilling Campaign
Phase 1 - Current Drilling Campaign ✓ Commenced auger drilling March 2018 under supervision of MSA ✓ On completion MSA will issue NI43-101 Resource Statement compliance ✓ Planned 1,500 metres – hole depth 5m to 35m ✓ Revised to 1,900 metres ✓ Completion end of May 2018 ✓ Auger Samples to SGS in SA ✓
Slide 9: Phase 1 – Pilot Plant
Phase 1 – Pilot Plant • Pilot Plant Production starting Q4 2018 (revenue generation): • Dense media separation (DMS) plant • Capacity of ± 55,000 tpa of concentrate • Concentrate +6% Li2O (95% spodumene mineralization) • Concentrate export via road and rail 17th May 2018 C.O.M. Presentation
Slide 10: Phase 2 – Main Plant
Phase 2 – Main Plant • Main Plant Production starting Q1 2020: • 2 x Dense media separation (DMS) plants • 400 tph Flotation Plant with capacity of ± 169,000 tpa* of concentrate • Concentrate +6% Li2O* (95%* spodumene mineralization) • Concentrate export via road and rail 17th May 2018 C.O.M. Presen
Slide 11: Project Summary
Project Summary • +/- 23 Million tonne lithium bearing tailings dump on surface grading 0.50% to 0.84% Li2O; professionally built tailings stockpile. • Already mined, crushed and milled – mitigates operating risk, reduced operating costs. • Simple metallurgical recovery process. • Brownfield site be