Kinder Morgan, Inc. · NYSE:KMI
Kinder Morgan — Kinder Morgan Energy Partners — Platts 2nd Annual Oil & Gas Conference (April 2008)
26 slides from Kinder Morgan's conference presentation, Apr 24, 2008

Slide 1: Platts 2nd Annual Oil & Gas Conference
Platts 2nd Annual Oil & Gas Conference KINDERMORGAN ENERGY PARTNERS, L.P. John Eagleton Vice President, Business Development West Region Gas Pipelines April 24, 2008

Slide 2: Forward Looking Statements
Forward Looking Statements This presentation contains forward looking statements, including these, within the meaning of Section 27A of the Securities Act of 1933, as amended and Section 21E of the Exchange Act of 1934, as amended. Forward looking statements are not guarantees of performance. They i

Slide 3: The Kinder Morgan Strategy
The Kinder Morgan Strategy Same Strategy Since Inception n Own and develop stable, feebased energy infrastructure in growing markets n Increase utilization of assets n Aggressively control cost n Gain economies of scale from acquisitions and expansions n Maximize benefit of MLP financial structure

Slide 4: Unmatched Asset Footprint
Unmatched Asset Footprint Trans Mountain n Largest independent transporter of 2 petroleum products in the U.S. Cochin n Transport more than 2 million 2 barrels per day (Bbl/d) Pacific n 2nd largest transporter of natural gas in U.S. (a) n Approximately 22,000 miles of Trailblazer 2 interstate / intr

Slide 5: On the Drawing Board
On the Drawing Board Over $10 Billion in New Projects (a) 9 Natural Gas 5 1. Northeast Express 10 2. Chicago Express/NGPL(b Express/NGPL(b)) 3. MEP Expansion 6 4. KMLP Expansion Oilsands 5. TMX2/TMX3 Expansions 2 1 6. Chinook Gulf Coast Pipeline CO2 7. Gulf Coast Pipeline Renewable Fuels 8. Batched/

Slide 6: Challenges
Challenges n Determining market needs & project scope n Forecasting market prices & response to new infrastructure n Determining intrinsic and extrinsic value n Accurately estimating project cost at the time of construction n Regulatory & permitting process and timeline n Material & equipment availa

Slide 7: The Uncontrollable
The Uncontrollable 7

Slide 8: Meeting the Challenges
Meeting the Challenges n Unsurpassed team n An average of over 30 years of experience held by the senior managers of the Business Development Engineering, Project Management, Operations, Regulatory, EH&S and Executive groups n Handson experience with large projects n Rockies Express n Midcontinent

Slide 9: Rockies Express Pipeline
Rockies Express Pipeline OVER ROCKIES EXPRESS PIPELINE THRUST CAPACITY LEASE Zone 1 REX WEST REX EAST 1,500,000 Dth/d 1,600,000 Dth/d 1/2009 1,800,000 Dth/d 6/2009 Opal Kanda Wamsutter Cheyenne Meeker Greasewood Lebanon Clarington Blanco PIPELINE – 1,679 MILES COMPRESSION – 460,000 Hp Rockies E

Slide 10: REX West In-Service Dates
REX WEST In–Service Dates n Interim Service n KMIGT, NNG, NGPL, ANR Jan ‘08 n Full Service n KMIGT, NNG, NGPL, ANR PEPL Apr ‘08 10

Slide 11: REX Throughput
REX Throughput Apr ‘08 1,350 1,300 1,250,000 Dth/d 1,250 1,200 1,150 1,100 1,050 1,000 950 900 850 800 750 Mdth/day 700 650 600 550 500 450 Jan ‘07 400 350 300 250 200 150 100 250,000 Dth/d 50 0 Jun07 Jul07 Nov07 Jan07 May07 Aug07 Jan08 Feb07 Mar07 Apr07 Sep07 Oct07 Dec07 Feb08 Mar08

Slide 12: REX East
REX East n Status n Pipe 77% Produced/58% Delivered n Major equipment 100% Complete n ROW acquisition 72% Complete n Timeline n FERC application Complete n Final EIS Issued n FERC issues certificate May, 2008 n FERC issues notice to construct May, 2008 n Commence construction June, 2008 n Inservice

Slide 13: Another Rocky Mountain Export Pipeline is Needed
Another Rocky Mountain Export Pipeline is Needed 14,000 Other 12,000 DJ Basin Powder River Pipeline Capacity Mdth/d (Dry) 10,000 Pipeline Export Capacity Wind River 8,000 6,000 Greater Green River 4,000 2,000 Uinta/Piceance 0 2000 2005 2010 2015 2020 2025 2030 Year Source: Wood Mackenzie 13

Slide 14: Chicago Express/NGPL Project
Chicago Express/NGPL Project 14 14

Slide 15: Chicago Express Project Overview
Chicago Express Project Overview n 1.2 Bcf/d Capacity n Receipts at Meeker, Opal, Wamsutter, Chugwater n Chicago Express delivery into: n KMIGT, NNG, NBPL, NGPL n Natural Gas Pipeline Company delivery into: n NICOR n Peoples Gas Light and Coke n Guardian n Midwestern n NGPL n Vector 15

Slide 16: Why Chicago?
Why Chicago? n Access to huge upper Midwest markets n Extremely liquid trading point n Declining Canadian supply availability n Average daily demand almost 4 Bcf n Peak day demand exceeding 10 Bcf n Storage in market area of ~500 Bcf 16

Slide 17: Why Chicago Express/NGPL?
Why Chicago Express/NGPL? n Competitive Rates n Direct access to Chicago markets n Does NOT rely on securing space on downstream pipelines n Does NOT contemplate selling gas upstream of the markets n Access to NGPL city gates n Creates ~700,000 Dth/d of firm incremental capacity on the existing NGPL

Slide 18: Chicago Express/NGPL Rates
Chicago Express/NGPL Rates Meeker / Opal Receipts Powder River Receipts ($ per Dth) FL&U (1) ($ per Dth) FL&U (1) Chicago Express $1.124 2.58% (2) $0.974 1.32% (2) NGPL $0.375 0.66% (3) $0.375 0.66% (3) Total $1.499 3.24% $1.349 1.98% (1) Includes an assumed L&U of 0.15% (2) Tracked (90% Load Factor

Slide 19: NGPL Low Pressure Delivery Options
NGPL Low Pressure Delivery Options § Nicor, Nipsco, Peoples, MidAmerican § Chicago Express/NGPL rate plus tariff commodity rate § ANR, PEPL, MRT, Horizon, Crossroads, Ameren (IP, CIPS, CILCO) § Chicago Express/NGPL rate plus incremental reservation rate of $0.03 per Dth and tariff commodity rate § N

Slide 20: Chicago Express Timeline
Chicago Express Timeline n Secure shipper commitments July, 2008 n Conclude binding open season September, 2008 n Submit preNEPA application December, 2008 n Submit FERC application July, 2009 n Receive FERC approval May, 2010 n Commence project construction July, 2010 n Chicago Express upstream se

Slide 21: Northeast Express Map
Northeast Express Map Phase 2 Phase 2 Clarington to Princeton Princeton to Linden 300,000 Dth/d Up to 1,700,000 Dth/d REX Expansion Incremental Capacity Capacity (Up to a total 1,800,000 32 miles 30” pipeline + Booster Service Dth/dl) Head end Compression Up to 650,000 Dth/d Capacity Compression On

Slide 22: Northeast Express Overview
Northeast Express Overview n New infrastructure to serve Northeast markets n Expandable with additional compression n Lowest transportation cost n Receipts from Rockies, MidContinent, Gulf, Appalachia n Bidirectional capability at Steckman Ridge (Storage) & Chambersburg (Storage, LNG) n Delivery i

Slide 23: Value of Northeast Express
Value of Northeast Express n Direct link to reliable, longlived Rockies gas n Minimizes use of multiple pipes that creates ratestacking n Supply Diversification and Reliability n Domestic supply n No weather risk n Not subject to price driven market diversion (LNG) n Canadian and Gulf Coast suppli

Slide 24: Northeast Express Rates
Northeast Express Rates Firm Transportation Rate (1) Estimated Transportation Path ($ per Dth/$ per mo per Dth) FL&U (2) Phase 1 Lebanon to Princeton $0.6900/$20.9875 1.360% Clarington to Princeton $0.5900/$17.9458 1.360% Phase 2 Lebanon to Princeton $0.6900/$20.9875 1.360% Lebanon to Linden $0.7200

Slide 25: Northeast Express Timeline
Northeast Express Timeline n Pursue shipper commitments Ongoing n Commence prefiling process September 2008 n File FERC application April 2009 n FERC application approval March 2010 n Commence construction to Princeton Summer 2010 n Inservice to Princeton February 2011 n Commence construction to L

Slide 26: Platts 2nd Annual Oil & Gas Conference
Platts 2nd Annual Oil & Gas Conference KINDERMORGAN ENERGY PARTNERS, L.P. John Eagleton Vice President, Business Development West Region Gas Pipelines April 24, 2008
Source: Internet Archive copy of kindermorgan.com
More decks from Kinder Morgan, Inc.
Q4 2025 Earnings Presentation38 slides · Jan 21, 2026
Investor Presentation (January 2026)64 slides · January 2026
Investor Presentation (December 2025)24 slides · Dec 3, 2025
Q3 2025 Earnings Presentation36 slides · Oct 6, 2025
Corporate Update (September 2025)22 slides · Sep 17, 2025
Q2 2025 Earnings Presentation36 slides · Jul 16, 2025