Avista Corporation · NYSE:AVA

Avista — Technical Presentation (June 2024)

32 slides from Avista's technical presentation, Jun 4, 2024

  1. Slide 1: 2025 Electric Integrated Resource Plan TAC Meeting No. 8 Agenda

    2025 Electric Integrated Resource Plan Technical Advisory Committee Meeting No. 8 Agenda Tuesday, June 4, 2024 Virtual Meeting – 8:30 am to 10:00 am PTZ Topic Staff Introductions John Lyons Electrification Scenarios James Gall New Resources Options Costs and Assumptions Michael Brutocao 2030 Loss of

  2. Slide 2: 2025 IRP TAC 8 Introductions

    2025 IRP TAC 8 Introductions John Lyons, Ph.D. Technical Advisory Committee Meeting No. 8 June 4, 2024

  3. Slide 3: Today's Agenda

    Today’s Agenda Introductions, John Lyons Electrification Scenarios, James Gall New Resources Options Costs and Assumptions, Michael Brutocao 2030 Loss of Load Probability Study, Mike Hermanson Load & Resource Balance and Methodology, Lori Hermanson (Will be covered in TAC 9 meeting) 2

  4. Slide 4: Remaining 2025 Electric IRP TAC Schedule

    Remaining 2025 Electric IRP TAC Schedule • TAC 9: June 18, 2024: 8:30 to 10:00 (PTZ) o Load & Resource Balance and Methodology o IRP Generation Option Transmission Planning Studies o Distribution System Planning within the IRP & DPAG update • Technical Modeling Workshop: June 25, 2024: 9:00 am to 12

  5. Slide 5: Remaining 2025 Electric IRP TAC Schedule

    Remaining 2025 Electric IRP TAC Schedule • TAC 12: August 13, 2024: 8:30 to 10:00 (PTZ) o Preferred Resource Strategy Results (continued) o Portfolio Scenario Analysis (continued) o LOLP Study Results (continued) o QF Avoided Cost • September 2, 2024- Draft IRP Released to TAC. • Virtual Public Meet

  6. Slide 6: 2025 IRP Portfolio Scenario Update (DRAFT)

    2025 IRP Portfolio Scenario Update (DRAFT) James Gall Technical Advisory Committee Meeting No. 8 June 4, 2024

  7. Slide 7: High Electric Transportation Scenario

    High Electric Transportation Scenario 450 2025 IRP EV Forecast 400 2025 IRP EV High Scenario 2023 IRP EV Forecast 350 2023 IRP EV High Scenario 300 250 aMW 200 150 100 50 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2

  8. Slide 8: State Electric Vehicle Load Projections

    State Electric Vehicle Load Projections Idaho Washington 300 300 Idaho- Expected Case Washington- Expected Case 250 Idaho- High Scenario 250 Washington- High Scenario 200 200 aMW aMW 150 150 100 100 50 50 0 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2

  9. Slide 9: Space Heat Assumptions for Building Electrification

    Space Heat Assumptions for Building Electrification Space Heating Efficiency Curve 4.00 3.50 For homes with central heating, the homeowner 3.00 may find efficiency, cost, equipment longevity 2.50 challenges when Heat Pump Lockout Point for Gas Coupled Systems w/o retrofitting to fully electric due t

  10. Slide 10: Building Electrification Electric Impacts

    Building Electrification Electric Impacts 80% Reduction in WA/ID System Natural Gas Usage by 2045 500 Load Forecast Impact (Energy) 450 Assumes 75% of WA 400 and 90% of ID 350 natural gas 300 customers use Avista electric aMW 250 200 Load impact is close 150 to even between 100 states 50 - 2026 2027

  11. Slide 11: Load Forecast Comparison

    Load Forecast Comparison January Peak Forecast 3,500 3,000 Megawatts 2,500 2,000 1,500 1,000 Expected Case Energy Forecast 80% Washington Building Electrification by 2045 500 80% Washington Building Electrification by 2045 & High Transportation Electrification Scenario 3,500 Extreme Building/Transpo

  12. Slide 12: Load Forecast Scenarios Still Under Development

    Load Forecast Scenarios Still Under Development • Load forecast data will be posted on Teams site once finalized • Remaining scenario update: – Maximum Washington Customer Benefits: EV/Solar penetration to be increased in Named Communities – Data Center in 2030: Assume 200 MW in Idaho service area –

  13. Slide 13: Supply Side Resource Options

    Supply Side Resource Options 2025 Electric IRP, 8th Technical Advisory Committee Meeting June 4, 2024 Michael Brutocao, Natural Gas Analyst 1 DRAFT

  14. Slide 14: Overview and Considerations

    Overview and Considerations • IRP supply-side resources are near commercially available technologies with potential for development within or near Avista’s service territory. • Resource costs vary depending on location, equipment, fuel prices and ownership; while IRPs use point estimates, actual cos

  15. Slide 15: IRA Details

    IRA Details • Production Tax Credits ($2022 USD) – Geothermal, Solar, Wind and Biomass – $0.026 per kWh tax credit – Nuclear – $0.015 per kWh tax credit plus $0.003 base credit ($0.018 total per kWh credit) • Investment Tax Credit (Battery Storage, Pumped Hydro, Solar) – Costs incurred thru 2032 qua

  16. Slide 16: Resources Not Modeled

    Resources Not Modeled • Carbon Sequestration • Coal • RNG except as fuel for Frame CT • Sodium, Vanadium, and Zinc Bromide Batteries • Wave 4 DRAFT

  17. Slide 17: Resources Modeled

    Resources Modeled Resource Fuel Source MW Capacity Factor Capital $/kW (2026) Frame CT Natural Gas 180 $831 Frame CT Ammonia 90 $1,079 Frame CT RNG 90 $831 Reciprocating Engine Natural Gas 185 $1,272 Combined Cycle Natural Gas 312 $1,271 Small Nuclear Modular Reactor Uranium 100 93% $8,224 Wind (On

  18. Slide 18: Resources Modeled (continued)

    Resources Modeled (continued) Resource Fuel Source MW MWh Capacity Factor Capital $/kW (2026) Residential PV (New Construction) Solar 0.006 16% $3,810 Residential PV Solar 0.006 16% $4,141 Commercial PV Solar 1 17% $2,297 Low-Income Community PV Solar <1 30% $369 Utility PV (Fixed) Solar 5 30% $1,84

  19. Slide 19: Solar PPA Price/Implied Energy Payment

    Solar PPA Price/Implied Energy Payment $350 $300 $250 $200 $/MWh $150 $100 $50 $- 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Residential PV (New Construction) Residential PV Commercial PV Low-Income Community PV Utility PV (Fixed) Utility PV (

  20. Slide 20: Wind PPA Price/Implied Energy Payment

    Wind PPA Price/Implied Energy Payment $200 $180 $160 $140 $120 $/MWh $100 $80 $60 $40 $20 $- 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 On System Off System Montana Off Shore/System 8 DRAFT

  21. Slide 21: Baseload Clean Energy

    Baseload Clean Energy $250 $200 $150 $/MWh $100 $50 $- 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Small Nuclear Modular Reactor Geothermal (Off System) 9

  22. Slide 22: Energy Storage PPA Price/Implied Capacity Payment

    Energy Storage PPA Price/Implied Capacity Payment $800 $700 $600 $500 $/kW-year $400 $300 $200 $100 $- 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Distribution Scale 4hr Lithium-ion Distribution Scale 8hr Lithium-ion 4hr Lithium-ion 8hr Lithium

  23. Slide 23: Dispatchable Resource Variable vs Fixed Cost

    Dispatchable Resource Variable vs Fixed Cost Resources with lighter and darker shades indicate costs in Washington and Idaho, respectively 11 DRAFT

  24. Slide 24: NEI Cost Studies to be Added

    NEI Cost Studies to be Added • Avista obtained licenses to run the IMPLAN model for Washington and Oregon to be able to run our own economic impact studies for each of the new resource types • Still learning and configuring the model as this time and will report back to the TAC as the studies are co

  25. Slide 25: 2030 Loss of Load Probability Study (DRAFT)

    2030 Loss of Load Probability Study (DRAFT) Mike Hermanson Technical Advisory Committee Meeting No. 8 June 4, 2024

  26. Slide 26: Topics

    DRAFT Topics • LOLP Purpose • Study Methodology • Reliability Metrics • Results • Planning Margin

  27. Slide 27: Purpose of Loss of Load Study

    DRAFT Purpose of Loss of Load Study • Determine the ability of our system to meet load and reserves each hour when subjected to 1,000 iterations with different combinations of: – Water years – Load – Temperature – Maintenance – Forced outages – VER production • Utilized currently expected portfolio

  28. Slide 28: Modeling Framework

    DRAFT Modeling Framework • Avista Reliability Assessment Model (ARAM) - Excel based model with VBA code and linear optimization Excel Add-in What’s Best! Renewable generation based on wind speed that is random Run of river generation number that is auto correlated based on hydro year and influenced

  29. Slide 29: Reliability Metrics

    DRAFT Reliability Metrics • Studies are conducted with 1,000 iterations of the ARAM Model • Model metrics provide insights and targets to achieve a reliable system • Metrics – LOLP – Loss of Load Probability: Calculated by counting the number of iterations where there is unserved load or unmet reser

  30. Slide 30: Reliability Metrics

    DRAFT Reliability Metrics Metric Use LOLP Can be used to determine the probability or likelihood of events due to insufficient capacity. LOLE The majority of entities conducting LOLE studies primarily use it to establish resource adequacy criteria. Industry standard is 0.1 days per year LOLE. LOLH T

  31. Slide 31: 2030 Existing Portfolio 12x24 Resource Deficiency

    DRAFT 2030 Existing Portfolio 12x24 Resource Deficiency • The following chart presents the sum of the hourly average of loss of load over 1,000 iterations by month and hour in MWhs: Hour 2030 No Additional Resources Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 10.2 11.5 13.

  32. Slide 32: Summary of metrics

    DRAFT Summary of metrics • Planning margin determined by running model with increasing values of additional dispatchable resource Additional Dispatchable Resources LOLP – Loss of Load Probability Metric Target LOLE – Loss of Load Expectation Base 50 MW 100 MW 150 MW 200 MW LOLH – Loss of Load Hours