AGL Energy Limited · ASX:AGL
AGL Energy — Corporate Update (November 2018)
37 slides from AGL Energy's corporate update, Nov 14, 2018
Slide 1: Silverton Wind Farm Community Consultative Committee
Silverton Wind Farm Community Consultative Committee Meeting No.CCC-030 Wednesday, 14 November 2018
Slide 2: Agenda
Agenda 1 2 3 4 5 6 Welcome Previous Project update Community Topics of Other minutes • Overview relations interest business • Wind Farm Works update • Wholesale Electricity Market • Commissioning • Night-time Generation • Progressive Rehabilitation • NSW Drought Silverton Wind Farm | 14 November 201
Slide 3: 1. Welcome
co) = fe) 2) O® =
Slide 4: 2. Previous minutes
2. Previous minutes
Slide 5: Action items
2. Previous minutes Action items Item Action Status Who 3.23.16 AGL to contact Rod Grenfell in relation to erecting a fence along Daydream Mine Road near the Open AGL – 1/18 Umberumberka pipeline access. 4.25.07 AGL to progress the 20m monopole with Telstra and Crown as part of the mobile reception
Slide 6: 3. Project update
• Overview • Wind Farm Works • Connection Works 3. Project update
Slide 7: Silverton Wind Farm
3. Project update Silverton Wind Farm Silverton Wind Farm • Located in the Barrier Ranges approximately 5km north of the Silverton township • Generation capacity of 200 MW • Wind turbines: 58 x GE 3.43-130 • Annual Energy Production (AEP) - ~780,000 MWh (capacity factor of 44.5%) - Powering more tha
Slide 8: Scope of works
3. Project update Silverton Wind Farm Scope of works • Silverton Wind Farm consists of two main scope of work: - Wind Farm Works (GE-CATCON) - Connection Works (TransGrid) • AGL has prepared an Overview Environmental Management Strategy (OEMS) in accordance with the project approval • Overview activ
Slide 9: Wind farm works and key milestones
3. Project update Silverton Wind Farm Wind Farm Works • GE-CATCON (joint venture) has been engaged to deliver the wind farm works - Engineer, Procure, Construct (EPC) Contract • Scope of works, includes - 58 x GE 3.43-130 wind turbines - 33kV electrical reticulation (underground and overhead) and 33
Slide 10: Connection Works
3. Project update Silverton Wind Farm Connection Works • TransGrid has achieved Practical Completion on 20 February 2018 - Existing Broken Hill 220kV substation (connection point) - 220kV transmission line - Wind farm 220kV substation • Connection works were successfully energised on 23 Feb 2018. •
Slide 11: Construction works
3. Project update Wind Farm Works Construction works • Civil works progress: - Access road clearance: 65/65km (100%) - Access road capping: 65/65km (100%) • Structural works progress: - WTG foundations excavated: 58/58 (100%) - WTG foundations poured: 58/58 (100%) • Electrical works progress: - 33kV
Slide 12: Construction works – Progress photos
3. Project update Wind Farm Works Construction works – Progress photos Silverton Wind Farm | 14 November 2018 12
Slide 13: Wind Turbine Deliveries
3. Project update Wind Farm Works Wind Turbine Deliveries • The last wind turbine was delivered to site week on Wednesday, 24 October 2018. - Image showing delivery of top tower section is shown below • Remaining onsite movements will be coordinated and complete as part of the remaining. Silverton W
Slide 14: Wind Turbine Erection
3. Project update Wind Farm Works Wind Turbine Erection • Cranes: - Sarens LR1650 (650 tonne crane) – operating - Boom Logistics LTM1750 (Blade only crane) – currently impacted by industrial action • Erection status - Down Tower Assembly (DTA): 57/58 (~98%) - WTG tower “stubs”: 57/58 (~98%) - Nacell
Slide 15: Wind Turbine Commissioning
3. Project update Wind Farm Works Wind Turbine Commissioning • The wind farm is currently being commissioned in accordance with the AEMO commissioning plan which involves coordination with AEMO and TransGrid (NSP). - AEMO – Australian Energy Market Operator - NSP – Network Service Provider • Commiss
Slide 16: Wind Turbine GE 3.43-130
3. Project update Wind Farm Works Wind Turbine GE 3.43-130 • GE 3.43-130 Power Curve - Cut in wind speed – 3 m/s - Rated wind speed – 13 m/s - Cut out wind speed – 25 m/s Silverton Wind Farm | 14 November 2018 16
Slide 17: First Generation
3. Project update Wind Farm Works First Generation • First generation occurred from the Silverton Wind Farm (STWF) on Saturday, 12 May 2018 at 23:30 hrs • Generation from the Silverton Wind Farm (STWF) as at Monday, 12 November 2018. - 68,500 MWh - Already powering more than 12,000 average Australia
Slide 18: Local Industry Participation
3. Project update Wind Farm Works Local Industry Participation • Currently ~80 construction workers with approximately 10% from the local area. - Reduced workers as the civil works and electrical works have progressed to completion. • High involvement of local suppliers. - Vertex Power & Process pro
Slide 19: Local suppliers
3. Project update Wind Farm Works Local suppliers • Delivery of the Silverton Wind Farm to date has involved the following local suppliers / contractors - Attards Transport - Interhealth Broken Hill - Barrier Daily Truth - Judd Plumbing - Boss Construction - Lawrence Engineering - Broken Hill City C
Slide 20: 4. Community relations update
4. Community relations update
Slide 21: Community enhancement program
4. Community relations update Community enhancement program Community Enhancement Program The Community Enhancement Program for the Silverton Wind Farm is progressing, in accordance with condition 18 (schedule 2) of the project approval. We are implementing the program to give effect to the commitme
Slide 22: Silverton Solar Program
4. Community relations update Community enhancement program Silverton Solar Program • To date, AGL has provided solar panels to 24 property owners and 13 of these properties have received their smart meters. Installers will visit Silverton to complete the remaining installations and share operations
Slide 23: Water Tank Program
4. Community relations update Community enhancement program Water Tank Program • AGL has started work on the supply, installation and connection of a domestic sized water tank (10,000L) - Water tank supply Landmark - Installation and connection Broken Hill Plumbing Services • Rolling installatio
Slide 24: Mobile Reception Program
4. Community relations update Community enhancement program Mobile Reception Program • AGL is progressing an Enterprise Work Agreement (EWA) with Telstra in relation to the proposed 4GX solution developed with Telstra for the mobile reception program - Installation of a 20m monopole at Telstra’s Sil
Slide 25: Mobile Reception Program coverage
4. Community relations update Community enhancement program Mobile Reception Program • The coverage predications below provide and indicative view of the coverage the proposed 4GX small cell would provide - Proposed 4GX solution would require a 4G 700 MHz compatible device to benefit from the improv
Slide 26: Visual Impact Mitigation
4. Community relations update Visual impact mitigation Visual Impact Mitigation AGL issued notification to the Silverton residents in accordance with condition 2 (schedule 3) of the project approval in relation to the visual impact mitigation measures outlined in condition 1 (schedule 3). • Owners w
Slide 27: Community events
4. Community relations update Community events Silverton Wind Farm | 14 November 2018 27
Slide 28: Community information
4. Community relations update Community engagement Community information AGL contact details for community and project information are shown below: • P: 1800-039-600 • E: [email protected] • W: agl.com.au/silverton Construction information GE-CATCON will provide contact details on the project
Slide 29: 5. Topics of interest
• Wholesale Electricity Market • Night-time Generation • Progressive Rehabilitation • NSW Drought 5. Topics of interest
Slide 30: Wholesale Electricity Market
5. Topics of interest Wholesale Electricity Market National Electricity Market (NEM) • The NEM is comprised of five physically connected regions on the east coast of Australia: Queensland, New South Wales, Victoria, Tasmania and South Australia. • The NEM is managed by the Australian Energy Market O
Slide 31: Night-time Generation
5. Topics of interest Night-time Generation AEMO commissioning process • AEMO and TransGrid provided approval to increase generation during the night-time period. • Last night the number of wind turbines in service increased from 13 (45* MW) to 18 (62* MW) (*subject to wind conditions). - Voltage an
Slide 32: Progressive Rehabilitation
5. Topics of interest Progressive Rehabilitation Wind Farm Works • GE-CATCON is completing progressive rehabilitation in accordance with condition 36 (schedule 4) of the project approval. • Works are being undertaken in accordance with the construction phase rehabilitation management plan specific t
Slide 33: Progressive Rehabilitation – Permanent Drainage Works
5. Topics of interest Progressive Rehabilitation Installation of Permanent Drainage Works (Above) Installed spoon drains (Right) Installed cross drain (Far Right) Installed spoon drains Silverton Wind Farm | 14 November 2018 33
Slide 34: NSW Drought
5. Topics of interest NSW Drought NSW Drought • A total of 77% of the state is in drought or drought affected, while 23% is experiencing intense drought. Silverton Wind Farm | 14 November 2018 34
Slide 35: 6. Other business
6. Other business
Slide 36: Next meeting
Silverton Wind Farm Community Consultative Committee (CCC) • Next meeting (TBC) - CALQ1 2019 (Thursday) - Time: 3pm - Silverton Municipal Chambers, Silverton Next meeting
Slide 37: Contact
Contact AGL Energy Silverton Wind Farm 1800-039-600 [email protected]