Slide 1: R3DP 2015 – Qualification & Contrat BSP-DSO
R3DP 2015 – Qualification & Contrat BSP-DSO Elia Expert Working Group – 19.3.2014
Slide 2: Structure of the documents
Structure of the documents Contract BSP-DSO R3DP 2014 1 document (incl. Qualifi- cation) Synergrid Contract R3DP 2015 2 documents C8-01 BSP-DSO (Qualifi- cation) Applies to : “Candidates-BSP” “Selected BSP” Réunion EWG du 19/3/2014 2
Slide 3: Contract
Contract Main change : deletion of the prequalification conditions and process (replaced by references towards the Synergrid C8-01) Explicit ‘new’ requirement that the activated volume cannot exceed the qualified volume Réunion EWG du 19/3/2014 3
Slide 4: C8-01: overview
C8-01 : overview Critères et procédure de qualification pour participation au produit R3 DP 2015 Réunion EWG du 19/3/2014 4
Slide 5: C8-01: a few important provisions (1/5)
C8-01 : a few important provisions (1/5) Validity of the qualification “Les EAN ayant déjà été pré-qualifiés en vue de participer au produit R3DP 2014 ne bénéficient d’aucune priorité et ne sont pas exemptés de la procédure décrite dans le présent document s’ils souhaitent participer au produit R3DP
Slide 6: C8-01: a few important provisions (2/5)
C8-01 : a few important provisions (2/5) Compatibility with the connection agreement “Un URD doit légalement introduire une demande d’étude lorsqu'une modification envisagée de ses installations ou de leurs modes d'exploitation peut perturber de façon non négligeable le fonctionnement du réseau de d
Slide 7: C8-01: a few important provisions (3/5)
C8-01 : a few important provisions (3/5) Eligibility & Compliance check - Connection agreement > 100 kVA (i.o. 250 kVA in 2014) - For production units : clear distinction between - Units which are designed to work in parallel with the network : compliancewith C10/11 is mandatory - Units which are de
Slide 8: C8-01: a few important provisions (4/5)
C8-01 : a few important provisions (4/5) Result of the prequalification - If the acceptable volume for a specific EAN is lower than the requested volume 2 codes : green for the acceptable volume, red for the volume in excess - Orange color : only if the volume of several EAN > acceptable volume fo
Slide 9: C8-01: a few important provisions (5/5)
C8-01 : a few important provisions (5/5) Final Qualification “Pour que le BSP puisse activer en 2015 la flexibilité d’un EAN pré-qualifié, cet EAN doit être qualifié. Cette qualification est obtenue si les conditions suivantes sont satisfaites : -• Le BSP doit avoir été sélectionné dans le cadre du
Slide 10: Next steps
Next steps Public Consultation - Both documents (Contract & C8-01) will be published on Synergrid website - Period : approx. 21/3 – 20/4 - Please use the standard Reply Form and make counter-proposals ! Treatment of the remarks & Submission to the regulators - All remarks received shall be sent to t