Slide 1: Nyngan Solar Plant Community Consultative Committee
Nyngan Solar 1 Plant Community Consultative Committee August 2014 Date: 1 August 2014
Slide 2: Agenda
2 Agenda 1 Welcome August CCC 2 Review previous minutes 3 Overview of project status (AGL and First Solar) 4 Project planning 5 Construction community fund 6 Next meeting and close > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 3: Review of previous minutes
3 Review of previous minutes > Presentation title > Author > Date (Verdana 10pt)
Slide 4: Review actions from previous meeting
4 2. Review actions from previous meeting Action item CCC meeting Status AGL to send an example application form to June 2014 Closed CCC. AGL to progress the shopfront display June 2014 Open AGM to provide more information about using June 2014 Closed the land acquired for native vegetation preserva
Slide 5: Confirmation of June 2014 minutes
5 2. Confirmation of June 2014 minutes › Any comments to the June minutes? › Accept as accurate record of meeting? > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 6: Overview of project status
6 Overview of project status • Adam Mackett (AGL) • Bruce Smith (First Solar) > Presentation title > Author > Date (Verdana 10pt)
Slide 7: AGL overview of project status
7 2. AGL overview of project status Current progress on the Nyngan Solar Plant: › Project on track for completion in June 2015 › Solar Plant launch on Wednesday, 30 July 2014 › Ten times bigger than the current largest solar PV plant in Australia. › 250 hectares 134 SCGs › 1.35 millions modules ›
Slide 8: AGL overview of project status: plant connection
8 2. AGL overview of project status Current progress on the Nyngan Solar Plant connection: › Connection works are mechanically complete. » 132kV transmission line (Essential Energy) » 132kV Switchyard (Essential Energy » 132kV Substation (AGL) › Energisation of the 132kV transmission line has been m
Slide 9: First Solar overview of project status
9 2. First Solar overview of project status Current progress on the Nyngan Solar Plant › 40,000 of the 140,000 steel posts have been installed › 19,000 of the 140,000 tilt brackets have been installed › Table installation underway › 250,000 of the 1,350,000 panels have been delivered › 18 of the 77
Slide 10: First Solar overview of project status
10 2. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 11: First Solar overview of project status
11 2. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 12: First Solar overview: local community and employment
12 2. First Solar overview of project status Local community and employment As of end of July 2014, the Joint Venture between WBHO and Probuild Civil has approximately 110 personnel on site – of which 1/3 are local/regional (35) ›First Solar Contacts: ›Bruce Smith Michael Law ›Project Manager Constr
Slide 13: First Solar overview of project status
13 2. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 14: First Solar overview of project status
14 2. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 15: First Solar overview of project status
15 2. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 16: Project Planning
16 Project Planning • Adam Mackett (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 17: Project planning
17 4. Project planning First Module Installation event, 30 July 2014 Attendees included: › The Hon, Kevin Humphries MP (NSW), Minister for Natural Resources, Lands & Water › Mark Coulton MP, Federal Member for Parkes › Leslie Williams MP, NSW Parliamentary Secretary for Renewable Energy › Ray Donald
Slide 18: Landscape plan
18 4. Landscape plan > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 19: Construction Community Fund
19 Construction Community Fund • Helena Orel (AGL)
Slide 20: Community Fund
20 5. Community Fund Update on the Community Fund AGL is finalising details Applicants will be notified of the outcome of their applications in week commencing 11 August Community Fund Panel process Any feedback on the process? > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 21: Next meeting and close
Energy in action? Since 1837
Slide 22: Any other business
22 6. Any other business › Questions from observers? › AGL and First Solar will be at the Nyngan Ag Expo this Saturday, so feel free to drop by for a chat. > Nyngan Solar Project > AGL Energy > 1 August 2014
Slide 23: Next meeting
23 6. Next meeting › Agenda – is there anything that you would like to discuss? Date: Wednesday 1 October TBC (this is the last week of October school holidays) Time: 6pm – 8pm Venue: CWA Hall > Nyngan Solar Project > AGL Energy > 1 August 2014