Slide 1: Northwestern Energy ETAC Meeting #8 – 2025 MT IRP Planning Cycle
Northwestern Energy ETAC Meeting # 8 2025 MT IRP Planning Cycle August 28th, 2025
Slide 2: Agenda
Thank you Agenda
Slide 3: Agenda
Agenda Introductions/Welcome (15 min) Asset Management VP Comments (30 min) Stake Holder Working Group (15 min) Scenario/Sensitivity Updates (15 min) PowerSimm ARS Preliminary Results (90 min) Questions/Comments (15 min)
Slide 4: Timeline – High Level
Timeline – High Level (see detailed workplan) Modeling Inputs Preliminary Modeling Draft IRP ETAC Modeling Input Final Modeling IRP Today Aug 28th Oct.2025
Slide 5: Asset Management VP Comments
Thank you Asset Management VP Comments
Slide 6: Stakeholder Working Group
Thank you Stakeholder Working Group
Slide 7: Stakeholder Working Group
Stakeholder Working Group Meeting Date: 07/10/2025 10:00 AM – 4:00 PM Location: Butte General Office Building: 11 E Park Street, Butte MT 59701 Participants Olson, Megan (Meeting Organizer, NWE) Shafer, Jon (NWE) Stajcar, Matthew (NWE) Barnheiser, Quintin (NWE) Seitz, Brandt (NWE) Fitzmaurice, Nicho
Slide 8: Stakeholder Working Group
Stakeholder Working Group Balanced Portfolio Discussed different scenarios and data in the Vibrant Clean Energy (VCE) study. NWE Comments: VCE considered all Montana generation, not just NWE owned generation. Transmission Stakeholder Comments: Transmission should be considered in how it could contri
Slide 9: Scenarios/Sensitivities Updates
Thank you Scenarios/Sensitivities Updates
Slide 10: Scenarios for 2026 MT IRP (as understood today)
Scenarios for 2026 MT IRP (as understood today) A. Base Case – Colstrip retires December 31, 2042. B. Colstrip retires June 30, 2029, according to MATS. C. Colstrip complies with MATS using baghouse on July 1, 2030. Colstrip retires December 31, 2042. D. Colstrip retires December 31, 2031, according
Slide 11: Sensitivities for 2026 MT IRP
Sensitivities for 2026 MT IRP F. 50% power costs. M. Allow carbon emitting resources after 2035 (PSC request from 2023 IRP) G. 150% power costs. N. Only allow carbon free resources to be H. 50% natural gas costs. selected in ARS I. 150% natural gas costs. O. Simulate no Colstrip acquisition from Pug
Slide 12: PowerSIMM Example Portfolios for discussion
Thank you PowerSIMM Example Portfolios for discussion
Slide 13: Resource Comparison Methodology in ARS
Resource Comparison Methodology in ARS $ : ! "# $ : •
Slide 14: Example Portfolio for a 2042 retirement w/ 2035 Net Zero Goal
Example Portfolio for a 2042 retirement w/ 2035 Net Zero Goal Capacity of Winter Season 2,500 Accredited Capacity (MW) 2,000 1,500 1,000 500 Candidate Resource Additions 1,600 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 1,400 Coal Petro Coke
Slide 15: Example Portfolio for a 2031 Colstrip retirement w/ 2035 Net Zero Goal
Example Portfolio for a 2031 Colstrip retirement w/ 2035 Net Zero Goal Capacity of Winter Season 2,500 Accredited Capacity (MW) 2,000 1,500 1,000 500 Candidate Resource Additions 800 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 700 50 Coal Pet
Slide 16: Questions/Comments?
Thank you Questions/Comments?