NorNickel GMK · RUS:GMKN

NorNickel GMK — Norilsk Nickel — Technical Presentation (2018)

9 slides from NorNickel GMK's technical presentation, 2018

  1. Slide 1: 1H 2018 Financial Results: Tailings Storage Facilities Disclosure

    1H 2018 FINANCIAL RESULTS Norilsk Nickel 1 Tailings Storage Facilities Disclosure

  2. Slide 2: Disclaimer

    Disclaimer The information contained herein has been prepared using information available to PJSC MMC Norilsk Nickel (“Norilsk Nickel” or “Nornickel” or “NN”) at the time of preparation of the presentation. External or other factors may have impacted on the business of Norilsk Nickel and the content

  3. Slide 3: Norilsk Nickel Tailings Facilities Overview

    Norilsk Nickel Tailings Facilities Overview • The disclosure contained herein has been certified by Sergey Diachenko, Chief Operating Officer of MMC Norilsk Nickel Key Facts: Kola MMC Location: Kola Peninsula • Norilsk Nickel operates 6 tailing dams (1 in operation/1 idled) (5 upstream, 1 downstream

  4. Slide 4: Overview of Norilsk Nickel's Operating Tailing Facilities

    Overview of Norilsk Nickel’s Operating Tailing Facilities Most recent Tailing storage Hazard Class Launch into Status Raising method independent facility (facility(1)/waste(2)) operation expert review Talnakh Concentrator’s Hazard Class 2/5 Operating Upstream 2017 2019 tailings facility Nadezhda Pha

  5. Slide 5: Tailings Monitoring System/ Safety Management System

    Tailings Monitoring System/ Safety Management System Tailing dams’ integrity has been always at the forefront of the Company’s safety agenda. Nornickel regularly monitors its tailings facilities to ensure their safe operation, aiming to prevent any adverse environmental impact Norilsk Nickel dams’ s

  6. Slide 6: Emergency Plans for Tailing Dams

    Emergency Plans for Tailing Dams • As required by the Russian law, contingency (emergency) plans (ERP) have been developed for all operating tailings storage facilities • The assessment of potential damage, which is conducted as part of safety declaration prepared for each tailings dam, suggests tha

  7. Slide 7: Appendix (1/2)

    Appendix (1/2) Talnakh Concentrator’s tailings facility Nadezhda Metallurgical Plant’s tailings facility Lebyazhye tailings facility Tailings Facility No. 1 Source: Company data 7

  8. Slide 8: Appendix (2/2)

    Appendix (2/2) Zapolyarny Concentrator’s tailings facility Bystrinsky GOK’s tailings facility Source: Company data 8

  9. Slide 9: IR Contact Details

    IR Contact Details Vladimir Zhukov Mikhail Borovikov Vice-President Investor Relations Head of Investor Relations Department Deputy Head of Investor Relations MMC Norilsk Nickel MMC Norilsk Nickel Tel: +7 495 797 8297 Tel: +7 495 787 7662 E-mail: [email protected] E-mail: [email protected] 9

Norilsk Nickel — Technical Presentation (2018) on 6ix