  1. Slide 1: Ramelius Resources Limited - Positioned for Growth

    RAMELIUS RESOURCES LIMITED ASX: RMS Positioned for Growth Paydirt Gold Conference March 2010 Ian Gordon CEO

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS This presentation contains certain forward looking statements with respect to Ramelius’ financial position, results of operations and other matters that are subject to various risks and uncertainties. Actual results, performance or achievements could be significantly diffe

  3. Slide 3: Corporate Structure

    Corporate Structure DIRECTORS: Bob Kennedy Chairman Reg Nelson Non-Executive Director Kevin Lines Non-Executive Director Joe Houldsworth Non Executive Director Ian Gordon Executive Director CEO 3

  4. Slide 4: Strategy

    Strategy ƒ Build a profitable gold company ƒ Maximise cash flow from Wattle Dam ƒ Significant drilling to extend Wattle Dam mine life ƒ Explore for large >1m oz deposits in known gold belts ƒ Look for quality acquisitions to grow the Company ƒ Focus on increasing long term shareholder value 4

  5. Slide 5: Results Summary

    Results Summary ƒ Three years of Net Profit 2007-2009 ƒ Net Profit after tax of A$4.97m in 2008/09 ƒ Production of 16,283 ounces of gold in 2008/09 ƒ Commenced underground May 2010 ƒ First underground production December 2009 ƒ Record production in December of > 20,000 ounces ƒ NPAT of A$10.1m for D

  6. Slide 6: Wattle Dam Underground Mine

    Wattle Dam Underground Mine ƒ HWE Mining appointed as underground contractor April 09 ƒ Portal and decline commenced in May 2009 ƒ First ore block development completed end of November 2009 ƒ First development ore processing completed December 2009 ƒ Stoping commenced January 2010 6

  7. Slide 7: Stoping Blocks January to March 2010

    Stoping Blocks January to March 2010 ~Ramping up 10,000t per month Open Pit 241 RL STOPING MARCH 225 RL MINED JAN-FEB 205 RL WATTLE DAM UNDERGROUND DEVELOPMENT LOOKING WEST 7

  8. Slide 8: Wider Ore Zone

    Ore Zone Wider Ore Zone ƒ Underground drilling demonstrates ore zone up to 10m wide ƒ Currently mining the eastern half of this zone ƒ New results in western 241 RL half of the zone increases tonnes and grade ƒ Best ever RC assay of 6770 g/t Au plus many assays over of 1000 g/t Au in western half of

  9. Slide 9: Wattle Dam Grades

    Wattle Dam Grades ƒ Abundant coarse gold in ore ƒ Extremely difficult to estimate grade ƒ Expected grade from mine plan is 16 g/t ƒ Production to date over 30,000oz at > 33 g/t Au ƒ Grades will fluctuate with coarse gold content in individual parcels ƒ Continued overcall in grade and gold production

  10. Slide 10: Significant visible gold in underground ore drives

    Significant visible gold in underground ore drives 10

  11. Slide 11: Visible Gold

    Visible Gold Sediment Face on 225 RL Ore Drive (Cut 6) 11

  12. Slide 12: Ore body strike length and high grade core

    ƒ Ore body has a strike length of 50m with a core of high grade 20-30m in strike by 10m wide ƒ Extensive gold veins in core of high grade zone ƒ Grade difficult to estimate and milling is the only accurate determination 12

  13. Slide 13: Wattle Dam Gold Mine Resource Upgrade

    South North Wattle Dam Gold Mine Resource Upgrade 241 Level ƒ Resource upgraded to 225 Level 226,500 tonnes at 18.0g/t 205 Level gold for 131,000 ounces ƒ Excludes development and stoping ore mined up to the end of Feb 10 est. at 30,000 oz Au Grade (ppm) ƒ Wider interpreted lode based on improved ge

  14. Slide 14: Wattle Dam Deep Drilling

    Wattle Dam Deep Drilling ƒ Deep diamond drilling completed in 2009 ƒ This drilling has defined gold mineralisation and the “mine geology” to a depth of 350m below surface ƒ Target has a small strike extent and requires high density drill pattern due to high nugget gold ƒ Significant results received

  15. Slide 15: Showing Selected High Grade Drill Intersections

    15 Showing Selected High Grade Drill Intersections

  16. Slide 16: Exploration

    Exploration ƒ Drilling targeting contacts along strike from Wattle Dam ƒ Gravity survey to further define controlling structures ƒ Trial SAM Geophysical survey completed north of Wattle Dam pit to identify prospective sediment horizon Wattle Dam ƒ Drilling underway north and south of Wattle Dam ƒ Ne

  17. Slide 17: Where are we now?

    Where are we now ? ƒ Strong board with growth strategy focussed on gold ƒ Supportive major shareholders ƒ No debt, cash and gold of approx. A$70m ƒ Milling of high grade stoping ore underway ƒ Resource upgrade delivered ƒ Cash flow positive from December 2009 ƒ No significant capital requirements mo

  18. Slide 18: Looking Forward

    Looking Forward ƒ Strong cash flows from Wattle Dam into second half 2011 ƒ Substantial drilling at Wattle Dam focussed on extending mine life ƒ Costs will be kept low, with year to date expenditure in line with our low cost strategy and budget ƒ Well positioned for growth with cash and gold of A$70

  19. Slide 19: Competent Person Statement

    The Information in this report that relates to Exploration Results is based on information compiled by Matthew Svensson. Matthew Svensson is a Member of the Australian Institute of Geoscientists and has sufficient experience which is relevant to the style of mineralisation and type of deposit under