Suncor Energy Inc. · TSX:SU

Suncor Energy — Corporate Update (May 2014)

21 slides from Suncor Energy's corporate update, May 8, 2014

  1. Slide 1: Adelaide Wind Project Community Liaison Committee

    Due to changes to the Competition Act, pending regulatory guidance, this document is provided for historical En raison des changements apportés à la Loi sur la concurrence, en attendant l'orientation réglementaire, ce document information purposes only and does not constitute an active or current re

  2. Slide 2: Agenda

    Adelaide Wind Project Community Liaison Committee Agenda • Safety Moment (Jason Weir) • Project Team Review • Contact Information • Project Map and Transportation Plan • Project Schedule • Construction Details 2

  3. Slide 3: Safety Moment – Construction Traffic

    Adelaide Wind Project Community Liaison Committee Safety Moment – Construction Traffic 3

  4. Slide 4: Project Team

    Adelaide Wind Project Community Liaison Committee Project Team: • Suncor • Development Team is responsible for site development, permitting and regulatory compliance • Major Projects Group is responsible for managing detailed engineering and construction • Operations Group is responsible for long te

  5. Slide 5: Contact List

    Adelaide Wind Project Community Liaison Committee On Site Contact Information Contact List Suncor contacts Suncor Project Contact Email [email protected] Toll Free Phone 1-866-344-0178 SITE EMERGENCY AMEC HSE Manager 1-647-328-4142 5

  6. Slide 6: Construction Arrangement

    Adelaide Wind Project – Construction Arrangement Direct Contract Suncor AMEC Supervision Contract Graham Eptcon Site Site Civil Turbine Collection Substation Works Erection System 6

  7. Slide 7: Site Map

    Adelaide Wind Project Community Liaison Committee - Site Map 7

  8. Slide 8: Project Schedule

    Adelaide Wind Project Community Liaison Committee Project Schedule Jan 2014 Activity May June July August September October November December Project Survey Mobilization & Start Construction Construct Entrances & Access Roads Construct Turbine Foundations Construct Substation Install Collection Syst

  9. Slide 9: Project Schedule

    Adelaide Wind Project Community Liaison Committee Project Schedule Jan Civil Works Electrical Works Turbine Supply Main Component Transportation Turbine Installation 9

  10. Slide 10: Construction Activities

    Adelaide Wind Project Community Liaison Committee Construction Activities • First activity will be creating entrances off of road right of ways Jan • Access Road and turbine foundations will be next 10

  11. Slide 11: Access Road

    Adelaide Wind Project Community Liaison Committee Access Road Jan 11

  12. Slide 12: Turbine Foundation

    Adelaide Wind Project Community Liaison Committee Turbine Foundation Jan 12

  13. Slide 13: Collection System Installation

    Adelaide Wind Project Community Liaison Committee Collection System Installation Jan 13

  14. Slide 14: Collection System Installation

    Adelaide Wind Project Community Liaison Committee Collection System Installation Jan 14

  15. Slide 15: Collection System Installation

    Adelaide Wind Project Community Liaison Committee Collection System Installation Jan 15

  16. Slide 16: Turbine Transportation

    Adelaide Wind Project Community Liaison Committee Turbine Transportation Jan 16

  17. Slide 17: Turbine Installation

    Adelaide Wind Project Community Liaison Committee Turbine Installation Jan 17

  18. Slide 18: Turbine Installation

    Adelaide Wind Project Community Liaison Committee Turbine Installation Jan 18

  19. Slide 19: Site Reclamation

    Adelaide Wind Project Community Liaison Committee Site Reclamation Jan 19

  20. Slide 20: SuNcoR )

    SuNcoR )

  21. Slide 21: Appendix

    Appendix FCCC“ CCC eee . SUNCoR)