PT Vale Indonesia Tbk · IDX:INCO

PT Vale Indonesia Tbk — Investor Presentation (November 2026)

26 slides from PT Vale Indonesia Tbk's investor presentation, Nov 19, 2026

  1. Slide 1: PT Vale Indonesia Tbk – Year-end Analyst Gathering

    PT Vale Indonesia Tbk A presentation for Year-end Analyst Gathering November 19, 2026 Public Inf ormat ion

  2. Slide 2: Table of Content

    Table of Content: 1. Culture Transformation 2. The Innovations and Continuous Improvement 3. Operational Update 4. 3Q26 Financial Highlights 5. Growth Projects Update 6. Market Outlook 7. 2027 Strategic Direction

  3. Slide 3: Cautionary Note & Disclaimer

    Cautionary Note & Disclaimer Cautionary Note on Forward-looking Statements This presentation may contain statements regarding the business of PT Vale Indonesia Tbk (the “Company” or “PT Vale”) that are of a forward- looking nature and are therefore based on management's assumptions about future deve

  4. Slide 4: Culture Transformation

    Culture Transformation Driving a high-performance culture through Compassion, Accountability, Resilience, Excellence, and Sustainability (CARES). Presented by Mr. Heriyanto A. Putra

  5. Slide 5: Culture Transformation, Target Culture and Desired Behaviors defined

    Culture Transformation, Target Culture and Desired Behaviors have been defined, with Culture Programs developed to embed Target Culture Why does the Company WHY: exist? Provides the Purpose foundation for the Purpose & vision and strategy Values Target Culture & One-liner Vision Where is the company

  6. Slide 6: PT Vale’s Transformation Journey

    PT Vale’s Transformation Journey... Business Process Organization & People Technology & Data • Leadership Role Modeling • Integrated HCIS • Simplify & Standardize HR Processes • LMS & Digital Learning • Continuous Improvement • Change Champions • Talent & Succession • Performance Management System •

  7. Slide 7: The Innovations and Continuous Improvement

    The Innovations and Continuous Improvement Presented by Mr. Slamet Sugiharto 7

  8. Slide 8: Technology of UAV mounted Ground Penetrating Radar (GPR)

    Technology of Unmanned Aerial Vehicle (UAV) mounted Ground Penetrating Radar (GPR) • To obtain information on subsurface lithology based on the physical properties of rocks and to determine the distribution of limonite, saprolite and bedrock. • This technology able to accelerate subsurface delineati

  9. Slide 9: 100T Battery Electric Truck: From Operational Trial to Fleet Scale

    100T Battery Electric Truck : From Operational Trial to Fleet Scale The BEV Truck reduced hauling costs by 50-60% Vs Diesel Truck — next : 15 BEV Trucks from mid-2027 Why We Started : 4 Reasons Behind the Trial HYDROPOWER DECA RB ON IZATION COST OPTI MI ZATION N EW TECHN OL OGY BEV 100- 365 MW 33% F

  10. Slide 10: Operational Update

    Operational Update Solid operational and financial performance supported by higher nickel in matte production and strong ore sales volumes 10 Presented by Mr. Abu Ashar

  11. Slide 11: Among the safest operators in global mining

    Among the safest operators in global mining PT Vale Indonesia's recordable injury rate is 78% below the global mining average — and still improving while we work more hours than ever Recordable injury rate 2025 — PTVI vs 24 ICMM member companies Injuries per 1,000 people, per year Alcoa 8.25 Same wo

  12. Slide 12: Nickel in Matte Production

    Continues growth platform across three mining blocks: Sorowako, Bahodopi, Pomalaa Key Highlights 67,645 Overall Performance in 3Q26: Nickel in Matte Production (in mt) 1 Nickel-in-matte output reached 18,341 t in 3Q26, the highest quarterly level recorded in 2026. 2 Ore sales broadened the Company’s

  13. Slide 13: 3Q26 Financial Update

    3Q26 Financial Update PT Vale continues to build its operational foundation for long-term growth Presented by Mr. Rizky A. Putra Public Inf ormat ion

  14. Slide 14: Gaining momentum through optimum matte capacity and increased ore sales volume

    Gaining momentum through optimum matte capacity and increased ore sales volume Production and Sales o Nickel matte production and deliveries totaled 18,341 tons and 20,158 tons, respectively, in 3Q26, supported by full furnace capacity upon completion of rebuilt. Ore sales business continued to ramp

  15. Slide 15: 9M26 Key Financial Highlights

    9M26 Key Financial Highlights Revenue EBITDA Net Profit Cash & Cash Equivalent Production US$ 896 Mn US$ 297 Mn US$ 147 Mn US$ 247 Mn 48,114 tNi +27% vs 9M25 +79% vs 9M25 +181% vs 9M25 -50% vs 9M25 -12% vs 9M25 Sales Volume UCC of Sales Price Nickel Matte Bahodopi Ore Pomalaa Ore Sales Ore Sapro & L

  16. Slide 16: Capital expenditures profile 2026 to 2028

    PT Vale Navigating Challenges and Strategic Priorities for 2026 Capital expenditures profile 2026 to 2028 2026 Strategic Priorities Recap Peaked capex and equity participations occur in 2027 as Preserve The Core while Scaling Growth mines complete and two HPALs start production Sorowako Production C

  17. Slide 17: Growth Projects Update

    Growth Projects Update Strategic downstream projects continued to progress, highlighted by the 1st mechanical completion of Lines 1 & 2 of the Pomalaa HPAL project Presented by Mr. Rizky A. Putra

  18. Slide 18: PT Vale strategic investment program in mining and downstreaming

    PT Vale strategic investment program in mining and down streaming processing Mine HPAL - JV Project Value Production Progress Timeline Production Ownership Progress Partner Timeline 100% 5.5 Mio phase phase 1 FIDa 42% Construction 2 – 36% Sapro 3Q22 2Q25 IGP US$ 1.9 B 1,731 60-ktpa Milestone 2,246 W

  19. Slide 19: Three growth projects in our pipeline are making progress

    Three growth projects in our pipeline are making progress Morowali Project Pomalaa Project Sorowako Project Reclamation Limonite Transfer Point Mine Office Extension Jetty Expansion Workshop & Office In-mine Stockpile Mine | Jetty expansion and offshore port construction Mine | Workshop Pad-1 contin

  20. Slide 20: Market Outlook

    Market Outlook Nickel demand growth and disciplined supply continue to support market fundamentals 20 Presented by Mr. Rizky A. Putra

  21. Slide 21: Navigating the Cycle, Building for the Long Term

    Navigating the Cycle, Building for the Long Term The market still faces oversupply, but demand keeps growing. Stainless steel remains the foundation, and batteries keep adding volume, with Europe as a new source of growth. 01 Projects built for the life of the mine 03 High-nickel batteries keep thei

  22. Slide 22: 2027 Strategic Direction

    2027 Strategic Direction The Company is well positioned to benefit from a stronger and more diversified production platform Presented by Mr. Bernardus Irmanto

  23. Slide 23: Continue optimizing nickel in matte production, expanding ore sales

    PT Vale Continue optimizing nickel in matte production, expanding ore sales contributions from its growth areas Production and Sales o Securing RKAB approval to unlock full mining capacity o Sorowako smelter (nickel matte) producing at full capacity o Ore sales volumes from Bahodopi and Pomalaa cont

  24. Slide 24: Our strategy to navigate 2027

    Strategic Direction: In 2027, PT Vale aims to further optimize its cost structure while supporting operational growth and transformation initiatives Our strategy to navigate 2027 ▪ Steady Matte Production: Building on 2026 maintenance completion to sustain ~73kt output in 2027. ▪ New Ore Revenue: Ad

  25. Slide 25: Creating long-term value through responsible mining practices

    “Creating long-term value through responsible mining practices and sustainable growth”

  26. Slide 26: Contact us

    Contact us: Investor Relations PT Vale Indonesia Tbk +62 21 - 524 9000 www.valeindonesia.com [email protected]

PT Vale Indonesia — Investor Presentation (November 2026) on 6ix