Elia Group SA/NV — Technical Presentation (October 2018)

21 slides from Elia Group SA/NV's technical presentation, Oct 10, 2018

  1. Slide 1: Backup flexibility for winter 2018-19

    Backup flexibility for winter 2018-19 Working Group Balancing 10/10/2018 Preliminary slides

  2. Slide 2: Introduction

    Introduction • Recent unavailability of nuclear power plants causes Security of Supply concerns in the Belgian Control Area. • Relying on Strategic Reserve is excluded, as legal framework does not allow anymore its contractualization for the coming winter period. • Elia has recently been approached

  3. Slide 3: Assumptions and constraints

    Assumptions and constraints • Existing Framework for Demand Side Flexibility : SDR As from Dec As from Dec As from Winter Jun 2018 2018 2018 2019-20 - Procedure to change ToE rules is, as foreseen by the law, complex and long not an option • Timing very limited: solution should be operational by No

  4. Slide 4: Assumptions and constraints

    Assumptions and constraints Variable per industrial site • Stakeholders’ constraints: - Long Lead Time; min/max duration ; min down time between two consecutive activations; max # of activations per winter - ToE is a pre-condition for some of them • Targeted flexibility is flexibility that has not f

  5. Slide 5: Proposed approach

    Proposed approach e approach?  Extend the existing non CIPU Free bids (“bids on Bidladder”) with a new SLA (Service Level Agreement) - This SLA is activated with a longer lead time and allows constraints - Those “slow non CIPU bids”, are assimilated to slow start CIPU units, and used according to B

  6. Slide 6: Framework

    Framework • The proposed solution may be considered as an extension of existing non CIPU Free bids Ibids  so that ToE can be applicable  so that the Imb. Price is linked to the Ibid price • Those bids from non CIPU units are used in the same way as “slow start CIPU Units” or CIPU units with constr

  7. Slide 7: Product Design

    CRTia Product Design

  8. Slide 8: Product Design

    Product Design As already applicable for non CIPU I bids on Bidladder • BSP - Conditions for participation to R3 NR 1. Open qualification procedure (prior to signature of the GFA): administrative and financial checks http://www.elia.be/en/suppliers/purchasing-categories/energy-purchases/Ancillary-se

  9. Slide 9: Product Design

    Product Design As already applicable for non CIPU I bids on Bidladder • Delivery Point - Conditions for participation 1. GU declaration (including the maximal tertiary control power for the DP) 2. Regime for all offtake common DP’s for each couple BSP – supplier as well as associated documents/proof

  10. Slide 10: Main product characteristics

    Main product characteristics - No capacity reservation - Bidding characteristics - Volume [MW] (non divisible) for the requested period - Applied on 1rst hour of activation (similar - Fixed price [€/MW] approach as for CIPU start costs) - Variable price [€/MWh] - Remunerated even if “PREPARATION” is

  11. Slide 11: Main product characteristics

    Main product characteristics - Activation: Fixed in ToE Rules - Baseline: Last qh before Activation Request (step 6 in operational process, see slide 16 ) New: baseline check: in case Baseline value (last qh before ACTIVATION) > 20% value resulting from X high of Y calculation, a penalty is applied.

  12. Slide 12: Operational Process

    Operational Process

  13. Slide 13: Operational process

    Operational process 2) Call for bids Activation Period 1) Scarcity Risk Identification - Based on Technical Trigger - Info available starting from DA 18h - Elia calls for bids for the Activation Period - Two fixed timeslots : - 19 pm DA for morning peak - 8 am D for evening peak - Publication: Call

  14. Slide 14: Operational process

    Operational process 2) Call for bids Activation Period 1) Scarcity Risk 3) Gate Closure Time for Identification Free bids with constraints - Two Time slots - @ 20:00 D-1 for morning peak - @ 10:00 D for evening peak - Bids are sent by email (with template provided by Elia) - Bid characteristics are

  15. Slide 15: Operational process

    Operational process 2) Call for bids 4) SELECTION Activation Period 1) Scarcity Risk 3) GATE Closure Time for Identification Free bids with constraints - After GCT following actions are executed : - Slow non CIPU I Bids are registered - Slow non CIPU I Bids are flagged in order not to be activated b

  16. Slide 16: Operational process

    Operational process 2) Call for bids 4) SELECTION Activation Period 1) Scarcity Risk 3) GATE closure time for 5) PREPARATION Identification Free bids with constraints - 5 hours before Activation Period - Elia sends a preparation message towards selected BSPs - This preparation message is not a guara

  17. Slide 17: Operational process

    Operational process 2) Call for bids 4) SELECTION 6) ACTIVATION Activation Period 1) Scarcity Risk 3) GATE closure time for 5) PREPARATION Identification Free bids with constraints - 1 hour before Activation Period - Elia sends an activation message per email towards selected BSPs - After this stage

  18. Slide 18: Operational process

    Operational process 2) Call for bids 4) SELECTION 6) ACTIVATION Activation Period 1) Scarcity Risk 3) GATE closure time for 5) PREPARATION 7) PROBID Activation msg Identification Free bids with constraints - 2nd activation request via Probid (=Bidladder tool) 15’ before Activation Period - Purpose i

  19. Slide 19: Planning and Next Steps

    CRTia Planning and Next Steps

  20. Slide 20: Tentative Planning

    Tentative Planning Bal Rules proposal to CREG 24/10/2018 WG Bal 1 WG Bal 2 Decision Bal. Rules 10/10/2018 16/10/2018 31/10/2018 Ready to be In Operation 2/11/2018 2018 08/10 11/10 14/10 17/10 20/10 23/10 26/10 29/10 01/11 2018 Today Draft Bal. Rules 11/10/2018 - 12/10/2018 Public consultation Balanc

  21. Slide 21: Many thanks for your attention!

    Many thanks for your attention! Anna Tsiokanos ELIA SYSTEM OPERATOR Boulevard de l'Empereur 20 1000 Brussels +32 2 546 70 11 info@ elia.be www.elia.be An Elia Group company