    Fourth quarter results 2022 3 Cautionary note Certain statements included in this announcement contain forward-looking information, Market 23 including, without limitation, information relating to (a) forecasts, projections and estimates, (b) statements of Hydro management concerning plans, objectiv

  3. Slide 3: Pål Kildemo, Chief Financial Officer

    Slide 3: Pål Kildemo, Chief Financial Officer

    Pål Kildemo Chief Financial Officer February 14, 2023

  4. Slide 4: Fourth quarter highlights

    Slide 4: Fourth quarter highlights

    Free cash flow NOK 5.8 billion (NOK 14 billion 2022) Adj. RoaCE 22% Strong results and aluminium margins, lower upstream prices and higher costs Focus on cash release and margin management in weaker markets Improvement program and commercial ambition delivered above target for 2022 Good progress on

  5. Slide 5: All-in metal prices and Platts alumina index

    Slide 5: All-in metal prices and Platts alumina index

    All-in metal prices Platts alumina index (PAX) USD/mt NOK/mt USD/mt % LME 4 600 38 000 600 20% 36 000 4 200 34 000 550 32 000 18% 3 800 500 30 000 3 400 28 000 450 16% 26 000 3 000 24 000 400 22 000 350 14% 2 600 20 000 18 000 2 200 300 16 000 12% 1 800 14 000 250 12 000 1 400 10 000 200 10% May-20

  6. Slide 6: Improved smelter margins still not attractive for restarts

    Slide 6: Improved smelter margins still not attractive for restarts

    Improved smelter margins still not seen as attractive for non-subsidized restarts Estimated global primary balance in 2023 European and US Gas prices European smelter margin1) per VAP (‘000 t) (EUR/MWh & USD/mbtu) (‘000 USD/t) 200 350 9 2 8 0 0 300 7 -2 -200 250 6 -4 -400 200 5 -6 -600 150 4 -8 3 -8

  7. Slide 7: Nordic spot power prices declined from Q3 peak

    Slide 7: Nordic spot power prices declined from Q3 peak

    • Nordic spot power prices have declined from the peak in third quarter 2022 • Declining Continental spot power prices following lower production costs in coal and gas power plants • Nordic hydrology remained negative in the fourth quarter • Price area differences in the Nordic region have narrowed

  8. Slide 8: Extrusion market volumes Q4 2022 vs Q4 2021

    Slide 8: Extrusion market volumes Q4 2022 vs Q4 2021

    Q4 2022 vs Q4 2021 Year over Year Hydro Extrusions segment sales volume Extrusion market growth per quarter Growth in % Growth in % 21 0 2 (5) (6) (8) -11 -12 -15 (16) -23 -27 (18) Distribution B&C Industrial HVAC&R Transport Automotive Total Q4 22 Q1 23 2023 11% 33% 21% 1% 19% 15% North America Eur

  9. Slide 9: Seizing opportunities where our capabilities match megatrends

    Slide 9: Seizing opportunities where our capabilities match megatrends

    Seizing opportunities where our capabilities match megatrends 1 2 9

  10. Slide 10: Improvement program and commercial ambition

    Slide 10: Improvement program and commercial ambition

    Improvement program and commercial ambition Improvement program Commercial ambition 2018 vs. 2022 vs. 2025 and 2027 target NOK billion Targeting NOK 14.0 billion in improvements by 20272),3) 1.5 2.9 0.7 1.0 0.5 39.7 2.2 11.0 1.8 15.4 3.3 4.6 7.8 3.6 1.8 Additional improvements of NOK 4.4 billion by

  11. Slide 11: Greener demand growth outpacing the rest of the market

    Slide 11: Greener demand growth outpacing the rest of the market

    Greener demand growth is outpacing the Ambition to more than double sales of greener products rest of the market ’22 -’30 CAGR Total EU / North America market ~3% Sales volume, tonnes (000s) ~3X ~140 100 40 50 55 20 Low-carbon primary (<4 t/t1)) ~20% 2020 2021 2022 2023e 2025e Mid-term capacity ~2X

  12. Slide 12: Adjusted EBITDA Q4 2022 vs Q3 2022

    Slide 12: Adjusted EBITDA Q4 2022 vs Q3 2022

    Q4-2022 vs Q3-2022 9.7 2.3 1.3 0.7 1.3 0.4 0.6 0.7 0.3 7.2 1.4 -0.8 Other & eliminations CO2 compensation Power sales Slovalco, Karmøy & Husnes Adj. EBITDA Q3 2022 Realized aluminium Raw materials Downstream margin Downstream volume Energy price Fixed cost Power sales, CO2 Adj. EBITDA Q4 2022 and al

  13. Slide 13: Key financial figures

    Slide 13: Key financial figures

    NOK million Q4 2022 Q4 2021 Q3 2022 Year 2021 Year 2022 Revenue 44 075 46 433 52 445 149 654 207 929 Reported EBITDA 3 930 12 462 9 828 26 050 39 536 Adjustment to EBITDA 3 254 (3 451) (108) 1 959 128 Adjusted EBITDA 7 184 9 011 9 721 28 010 39 664 Reported EBIT 1 405 10 086 7 670 17 887 30 715 Adju

  14. Slide 14: Bauxite & Alumina results

    Slide 14: Bauxite & Alumina results

    Implied alumina cost and margin USD/mt1) Results down on lower alumina prices and high raw 4 83 27 material costs, partly offset by positive currency effects 337 3104) 337 Key figures Q4 2022 Q4 2021 Q3 2022 Q4 22 Q4 21 Q3 22 Alumina production, kmt 1 559 1 600 1 579 342 393 364 Price3) Total alumin

  15. Slide 15: Aluminium Metal results

    Slide 15: Aluminium Metal results

    All-in implied primary cost and margin USD/mt1,4) 575 1075 950 Results slightly up from power sales and positive 2 25010) 2 175 2 3509,10) currency effects, partly offset by lower all-in-metal prices, lower volume and higher costs 1 650 1 600 1 550 Key figures Q4 2022 Q4 2021 Q3 2022 Q4 22 Q4 21 Q3

  16. Slide 16: Metal Markets results

    Slide 16: Metal Markets results

    Results down on lower results from sourcing and trading activities, negative currency and inventory effects, partly offset by higher recycling results Key figures Q4 2022 Q4 2021 Q3 2022 Recycling production, kmt 115 144 124 Metal products sales, kmt 1) 614 681 635 Adjusted EBITDA Recycling (NOK mil

  17. Slide 17: Extrusions results

    Slide 17: Extrusions results

    Results up on higher margins and sales premiums in recyclers, partly offset by lower sales volumes and higher costs Key figures Q4 2022 Q4 2021 Q3 2022 External sales volumes, kmt 265 301 301 Adjusted EBITDA, NOK million 939 665 1,385 Adjusted EBIT, NOK million 168 (122) 640 Adjusted RoaCE, % LTM1)

  18. Slide 18: Energy results

    Slide 18: Energy results

    Results down on internal contract, partly offset by higher prices Key figures Q4 2022 Q4 2021 Q3 2022 Power production, GWh 2 002 2 136 1 330 Net spot sales, GWh 511 305 (703) Southwest Norway spot price (NO2), NOK/MWh 1 719 1 271 3 519 Adjusted EBITDA, NOK million 1 542 1 723 321 Adjusted EBIT, NOK

  19. Slide 19: Net cash position and free cash flow

    Slide 19: Net cash position and free cash flow

    Continued strong earnings and release of NOC contributed a net cash position before adjustments in Q4 NOK billion Free cash flow NOK 5.8 billion 0.2 2.6 (4.2) Hedging collateral and other Pension assets/(liabilities) Other assets/(liabilities) (0.6) (0.7) 1.3 7.2 (2.6) (0.3) (3.1) (4.5) (7.3) (6.0)

  20. Slide 20: Working capital development and capex overview

    Slide 20: Working capital development and capex overview

    NOC release Q4 2.6 Build (-) / release (+) Q4-22 NOK billion 0.4 1.9 Working capital development • NOK 2.6 billion cash effective NOC release in Q4 0.3 • NOK 1.7 billion in expected receivables delayed into Q1-23 Inventory Trade receivables Other Cash effective • Inventory levels coming down, despit

  21. Slide 21: Shareholder distribution proposal

    Slide 21: Shareholder distribution proposal

    To be paid in 20231) • Strong cash generation and a robust balance sheet Dividend yield4) 3.2 % 3.8 % 3.1 % 9.9 % 7.7 % enables another year of solid shareholder distribution 240% 15 250 200 Shareholder distribution proposal 116% • NOK 5.65 cash dividend per share 95% 10 62% 100 • Representing payou

  22. Slide 22: Capital returns, balance sheet and capex summary

    Slide 22: Capital returns, balance sheet and capex summary

    Capital employed1) 9% Bauxite & Alumina Capital returns Balance sheet Free cash flow 27 % 22 24 % % Aluminium Metal adj. RoaCE adj. ND/EBITDA 2022 Metal Markets 23 % Extrusions ~106 BNOK Energy 22.2% 2) 0.23) 4) 13 % 4% 36 % 10% target over the cycle adj. ND/EBITDA < 2x 14.0 BNOK 40 % target over th

  23. Slide 23: Market

    Slide 23: Market

  24. Slide 24: Aluminium's qualities and versatility versus other materials

    Slide 24: Aluminium's qualities and versatility versus other materials

    Hydro’s strategic direction aims to realize full potential of aluminium’s strong qualities and versatility Aluminium Steel Copper Composites PVC Lightness and strength Strength and durability Conductivity Lightness Lightness and formability Durability and formability Recyclability Corrosion resistan

  25. Slide 25: Aluminium's role in green transition technologies

    Slide 25: Aluminium's role in green transition technologies

    Importance of aluminium within key green transition technologies1 PV Electric vehicles Key properties of aluminium match requirements – lightweight, conductive, corrosion resistance Wind power Electricity networks Infinitely recyclable with very low energy need and high resource efficiency Concentra

  26. Slide 26: Global semis demand 2022

    Slide 26: Global semis demand 2022

    Global semis demand 2022: ~96 million tonnes Per segment Per product form Per region 6% 22% 2% 1% 2% 11% 9% 24% 14% 1% 2% 6% 48% 15% 14% 22% 34% 32% 9% 18% Extrusions 9% per segment Transport Construction 14% China Packaging 3% Rolled products Asia ex. China Foil stock Extrusions Europe 13% Electric

  27. Slide 27: Semis demand growth driven by transport and electrical

    Slide 27: Semis demand growth driven by transport and electrical

    Semis demand growth driven by transport and electrical Global semis demand 2022-2030 In million tonnes ~122 3 8 Transport 3 0 1 6 3 Construction Additional aluminium demand from green transition1) In million tons 2 Packaging 16 +24 14 2 Foil stock 13 12 4 Electrical 11 10 10 Consumer durables 2 8 Ma

  28. Slide 28: New primary capacity still necessary to balance markets

    Slide 28: New primary capacity still necessary to balance markets

    Majority of announced primary growth based on high carbon energy sources In million tons 35.2 t CO2e per t Al 12.1 6.2 2.1 New primary capacity still necessary to balance markets 0.5 1.8 Global aluminium consumption In million tonnes 1.7 29.1 140 CAGR CAGR World. Ex Creep/ Likely Probable Additional

  29. Slide 29: Low-carbon and recycled aluminium to make up majority of market by 2030

    Slide 29: Low-carbon and recycled aluminium to make up majority of market by 2030

    Low-carbon and recycled aluminium to make up majority of EU and North America market by 2030 Greener demand growth is outpacing the Estimated demand from currently stated company emissions reduction rest of the market targets – demand upside as new targets are expected ’22 -’30 CAGR Low-carbon Recyc

  30. Slide 30: Estimated demand based on currently stated ambitions

    Slide 30: Estimated demand based on currently stated ambitions

    Estimated demand based on currently stated ambitions Examples of front runners with ambitious 2030 targets Scope 3 reduction targets Specific aluminium commitments Europe and North America low-carbon1) and recycled GAGR Share of low-carbon1) aluminium demand by sector (million tonnes) - estimate (’2

  31. Slide 31: LME and SHFE prices, premiums and alumina index

    Slide 31: LME and SHFE prices, premiums and alumina index

    LME and SHFE aluminium prices Regional standard ingot premiums Platts alumina index (PAX) USD/mt NOK/mt USD/mt USD/mt % LME 3M 1 000 600 20% 900 550 800 18% 500 700 450 600 16% 500 400 400 14% 350 300 300 200 12% 250 100 0 200 10% Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22 Jan-23 US Mid West J

  32. Slide 32: Raw material price indications

    Slide 32: Raw material price indications

    0.0 0.5 1.0 1.5 2.5 0.0 0.5 1.0 1.5 2.0 2.5 2.0 Q4-18 Q4-18 Q1-19 Q1-19 Q2-19 Q2-19 Q3-19 Q3-19 Q4-19 Q4-19 Q1-20 Q1-20 Q2-20 Q2-20 Q3-20 Q3-20 Q4-20 Q4-20 Q1-21 Q1-21 Indication of current market prices Q2-21 Q2-21 Q3-21 Q3-21 Caustic soda (indexed) Q4-21 Q4-21 Q1-22 Q1-22 Source: Thomson Reuters,

  33. Slide 33: Guinea stands out as a long-term bauxite source

    Slide 33: Guinea stands out as a long-term bauxite source

    Guinea stands out as a long-term source Bauxite resources billion mt Guinea 40.0 China 3.1 Jamaica Vietnam 2.0 India 5.8 3.5 Big-league (Top 4) Cameroon Mid-league (each > 1 Bt) 1.1 Indonesia Less significant bauxite resources Brazil 1.2 Total bauxite resources 4.3 Australia 8.8 Atlantic Pacific Sou

  34. Slide 34: Position

    Slide 34: Position

    ») Hydro Position

  35. Slide 35: Built on market understanding, customer closeness and competence

    Slide 35: Built on market understanding, customer closeness and competence

    Built on market understanding, customer closeness and competence The complete North America Europe aluminium company Aluminium Metal • High-quality bauxite and alumina 9.4 TWh in Energy #1 position #1 position #1 position production in Brazil extrusion extruded the Nordic extruded Bauxite & Alumina

  36. Slide 36: Bauxite & Alumina and Aluminium Metal cost curve positions

    Slide 36: Bauxite & Alumina and Aluminium Metal cost curve positions

    Bauxite & Alumina Aluminium Metal Alumina Business Operating Cost curve (2022) Smelter Business Operating Cost curve1) (2022) 5000 750 Alunorte back in 1st 4000 quartile after fuel switch ~2300 ~200 USD/mt, 3000 USD/t 500 ~245 USD/mt post fuel switch ~1000 ~115 USD/t, 2000 ~140 USD/t USD/t 250 post

  37. Slide 37: Power sourcing for smelters

    Slide 37: Power sourcing for smelters

    Power sourcing for smelters Power sourcing for Hydro smelters in Norway1) TWh in Europe 18 Total consumption 16 14 12 Smelter business operating cost 10 curve 2022 8 USD/tonne 6 4 3 200 2 3 000 0 2 800 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 2 600 Spot/Short-term Captive Wind power Hydropo

  38. Slide 38: Leadership in health and safety and sustainability ratings

    Slide 38: Leadership in health and safety and sustainability ratings

    • Transparent and consistent reporting approach for more than three decades Leadership in health and safety, social responsibility • Sustainability is fully integrated in Hydro’s strategy and compliance as a license to operate • Further improvements on several ratings in 2022 • Sustainalytics: From

  39. Slide 39: Aluminium hedges and BRL/USD hedge

    Slide 39: Aluminium hedges and BRL/USD hedge

    Aluminium hedges of 100-460 kt/yr 2023-25 in place • 2023: 460 kt hedged at a price of ~2200 USD/t • 75 kt call-options as liquidity measure • 2024: 440 kt hedged at a price of ~2500 USD/t • 2025: 100 kt hedged at a price of ~2550 USD/t • Pricing mainly in NOK, with USD hedges converted to NOK via U

  40. Slide 40: Equity alumina production 2022

    Slide 40: Equity alumina production 2022

    Equity production in 2022 in aluminium equivalents, thousand tonnes Alumina 10 000 9 000 8 000 7 000 6 000 5 000 4 000 3 000 2 000 1 000 0 China Hongqiao Aluminum Xinfa Group Co., United Company Rio Tinto PLC Alcoa Corp Norsk Hydro State Power Emirates Global East Hope Yunnan Vedanta Ltd Hindalco Ji

  41. Slide 41: Hydro's competitive strengths

    Slide 41: Hydro's competitive strengths

    • Global, highly • Leading innovation • Close customer • Comprehensive low- skilled workforce throughout value chain collaboration and carbon aluminium • Strong focus on • Product development in partnerships offerings development, diversity, collaboration with • Integrated value chain • Renewable en

  42. Slide 42: Strategy and Ambitions

    Slide 42: Strategy and Ambitions

    ») Hydro Strategy and Ambitions

  43. Slide 43: Profitability and sustainability ambitions

    Slide 43: Profitability and sustainability ambitions

    Profitability Sustainability ROACE > 10% CO2 - 30% 43

  44. Slide 44: Seizing opportunities where our capabilities match megatrends

    Slide 44: Seizing opportunities where our capabilities match megatrends

    Seizing opportunities where our capabilities match megatrends 1 2 44

  45. Slide 45: Improvement program and commercial initiatives raised

    Slide 45: Improvement program and commercial initiatives raised

    Strengthening future competitiveness and positioning with additional NOK 0.8 and 1.5 billion in 2023 and 2025. Further stretched with additional NOK 1.5 billion by 2027 Improvement program Ambitions increased in 2023 and 2025, and extended with additional NOK 1 billion until 2027 Fixed cost 11.0 10.

  46. Slide 46: Leveraging strong platform and capabilities in Energy

    Slide 46: Leveraging strong platform and capabilities in Energy

    Leveraging strong platform and capabilities • Approx 3.5 BNOK earnings “platform” (LTM adjusted to normal production and no area price Energy Operations gain) & Energy Markets • In addition, commercial contribution of approx. 400 MNOK average last 3 years • USD 2.7 billion contracted revenues1) • NO

  47. Slide 47: Delivering on recycling ambition

    Slide 47: Delivering on recycling ambition

    • Delivering on our recycling ambition - several investment decisions made, IRR 15-30% • Increasing ambitions to use PCS by 140kt, lifting EBITDA ambitions by NOK 1 billion All approved project pipeline Attractive RoaCE in our AM recycling portfolio PCS usage and ambition EBITDA Seizing the market o

  48. Slide 48: Extrusions profitability ambition

    Slide 48: Extrusions profitability ambition

    • Automotive, systems business and Portfolio commercial transport restructuring • Exited non-attractive operations and segments • Dedicated improvement program for Cost procurement and operational excellence reductions (EBS) Extrusions EBITDA • Capacity and capabilities in attractive NOK billions 14

  49. Slide 49: Profitability roadmap

    Slide 49: Profitability roadmap

    Profitability roadmap AEBITDA Q3-2022 LTM - 2027 BNOK, excluding new energy RoaCE 27% 41.5 • Recycling: Double PCS and EBITDA by 20251) increased • By 40 kt PCS by 2025 and additional 100 kt PCS by 2027 • Lifting EBITDA by additional NOK 1 billion RoaCE • Extrusion: Increase EBITDA to NOK 8 billion

  50. Slide 50: Sustainability ambitions on track

    Slide 50: Sustainability ambitions on track

    • On track to meet 30 percent reduction • 1:1 reforestation on track • On track to deliver on target of in scope 1 and 2 CO2e by 2030 empowering 500,000 people with • No net-loss biodiversity ambition for • Net-zero by 2050 or earlier new projects skills and education by 2030 • Reduce specific scope

  51. Slide 51: On track to achieve 30% carbon emissions reduction by 2030

    Slide 51: On track to achieve 30% carbon emissions reduction by 2030

    On track to achieve 30% carbon emissions reduction by 2030 and net-zero by 2050 or earlier GHG emissions – ownership equity Million tonnes CO2e (% of 2018 baseline emissions) 2018 2025 2030 2050 Fuel switch, Renewable power, green or earlier Electrifying coal boilers, grid electrical boilers, hydrog

  52. Slide 52: Technology roadmap to zero carbon aluminium by 2030

    Slide 52: Technology roadmap to zero carbon aluminium by 2030

    Clear technology roadmap to deliver industrial volumes of zero carbon aluminium by 2030 New process technology for decarbonizing Technologies for decarbonizing existing Technologies for more PCS-use and new capacity smelters casthouse decarbonization 3.2 ~1.4 3.2 ~1.4 ~6.9 4.8 CO2e emissions per yea

  53. Slide 53: Integrated value chain drives decarbonization capabilities

    Slide 53: Integrated value chain drives decarbonization capabilities

    Hydro’s control of integrated value chain drives key decarbonization capabilities Business Bauxite & Alumina Aluminium Metal Recycling Energy Extrusions World’s largest extrusion Primary production with Leading in PCS recycling for Strong starting Captive renewable power company with integrated 1st

  54. Slide 54: Carbon footprint of Hydro low-carbon products

    Slide 54: Carbon footprint of Hydro low-carbon products

    20.3 Primary aluminium produced on renewable energy 16.6 lower than the world global primary average 8.6 Recycled aluminium from Hydro 6.7 More than 5.7 4.0 3.0 2.3 0.5 lower than the world global primary Hydro Hydro Hydro Hydro Hydro Primary Primary Primary Primary average CIRCAL CIRCAL REDUXA REDU

  55. Slide 55: Ambition to grow greener product sales

    Slide 55: Ambition to grow greener product sales

    ~3X Sales volume, tonnes (000s) ~140 100 40 50 55 20 2020 2021 2022 2023e 2025e Mid-term capacity ~2X ~1000 Sales volume, tonnes (000s) 650 420 450 250 75 2020 2021 2022 2023e 2025e Mid-term capacity 55 1) Post-consumer scrap > 75%. 2) Footprint < 4.0

  56. Slide 56: Differentiated suite of low-carbon products

    Slide 56: Differentiated suite of low-carbon products

    • Strong scale position within recycling and low carbon aluminium Near-zero • Ambitious, yet concrete, decarbonization roadmap across aluminium e.g., 100% entire value chain PCS uniqueness/ pricing • Delivering pilot volumes of ultra low carbon and 100% PCS to Advanced low-carbon frontrunner partner

  57. Slide 57: Capitalize on circularity while decarbonizing primary value chain

    Slide 57: Capitalize on circularity while decarbonizing primary value chain

    Capitalize on market demand through circularity while decarbonizing primary value chain XX t CO2e/t in progress / achieved XX t CO2e/t spearheads XX t CO2e/t first commercially available volumes XX t CO2e/t pilot volumes Current emission levels Further use of PCS and green sourcing Further implement

  58. Slide 58: Delivering decarbonization to industry front runners

    Slide 58: Delivering decarbonization to industry front runners

    Utilizing integrated value chain and trusted partner position to deliver decarbonization to industry front runners Unlocking commercial and technological solutions Enabling decarbonization journey transition Driving demand Access to full suite of greener aluminium solutions Support in making the rig

  59. Slide 59: Shareholder returns and dividend yield versus peers

    Slide 59: Shareholder returns and dividend yield versus peers

    Stock price index / TSR 1st 400 quartile cost position AM 350 300 Low 250 carbon footprint 200 150 Long-term 100 50 renewable power contracts 0 Increased Jan-19 Jan-20 Jan-21 Jan-22 Apr-19 Jul-19 Oct-19 Apr-20 Jul-20 Oct-20 Apr-21 Jul-21 Oct-21 Apr-22 Jul-22 Oct-22 Peer range NHY improvement ambitio

  60. Slide 60: Business overview

    Slide 60: Business overview

    ») Hydro Business overview

  61. Slide 61: Hydro Group

    Slide 61: Hydro Group

    Hydro — Group

  62. Slide 62: World class assets, high-end products and leading market positions

    Slide 62: World class assets, high-end products and leading market positions

    World class assets, high-end products and leading market positions Raw materials Primary aluminium production, Aluminium in products processing and energy marketing and recycling Bauxite & Alumina Energy Aluminium Metal Metal Markets Extrusions • High quality Gibsite bauxite • Long-term power supply

  63. Slide 63: Group key figures

    Slide 63: Group key figures

    Adjusted EBITDA Free cash flow1) Adjusted RoaCE2) NOK million NOK billion 12-month rolling % 9 721 5.8 26.9% 9 011 4.7 22.2% 7 184 18.6% 2.0 4Q21 3Q22 4Q22 4Q21 3Q22 4Q22 4Q21 3Q22 4Q22 Upstream costs3,4) Extrusion volumes Improvement program status5) USD per tonne Thousand tonnes NOK millions 2 350

  64. Slide 64: Improvement program, capital allocation and growth priorities

    Slide 64: Improvement program, capital allocation and growth priorities

    • Increasing improvement program target for 2025 and extending Strategic program to 2027 Improvement Improvement growth program and New strategic • Setting ambitious operating capital ambitions for 2023 program and commercial initiatives growth • Contingency measures in place commercial ambition ini

  65. Slide 65: Strategic modes reflect global megatrends

    Slide 65: Strategic modes reflect global megatrends

    Strategic modes reflect global megatrends and high-return opportunities Safe, compliant and efficient operations – The Hydro Way Businesses Bauxite & Alumina Aluminium Metal Recycling Energy Extrusions Strategic mode Sustain and improve Sustain and improve Selective growth Selective growth Selective

  66. Slide 66: Indicative profitability in return-seeking and growth portfolio

    Slide 66: Indicative profitability in return-seeking and growth portfolio

    Indicative profitability in current return-seeking and growth portfolio • Increase proportion of post consumer scrap (PCS), lowering metal cost • Improved economies of scale in brownfield expansions • Sorting technology and equipment standardization CoC: ~7% IRR 15- 30% • New presses with improved c

  67. Slide 67: Dividend policy and risk policy

    Slide 67: Dividend policy and risk policy

    • Aiming for competitive shareholder returns and dividend yield compared to • Overall risk policy alternative investments in peers • Remain exposed to the inherent cash flow volatility related to Hydro’s business • Dividend policy • Fluctuating with the market - volatility mitigated by strong balanc

  68. Slide 68: Sustainability-linked bonds and capital structure

    Slide 68: Sustainability-linked bonds and capital structure

    10% • Framework published to facilitate issuance of green and sustainability linked bonds carbon 660 000 emission Linked Sustainability mt Bonds PCS • Linked to Hydro’s sustainability ambitions reduction by 2025 • CICERO Shades of Green provided Second Party Opinion allocating medium green by 2025 s

  69. Slide 69: Price and currency sensitivities

    Slide 69: Price and currency sensitivities

    Aluminium price sensitivity +10% Currency sensitivities +10% NOK million Sustainable effect: 3 110 NOK million USD BRL EUR 2 180 Adj. EBITDA 3,740 (840) 10 One-off reevaluation effect: Adj EBITDA Adjusted Net Income Financial items (990) 1,040 (4,050) Other commodity prices, sensitivity +10% NOK mil

  70. Slide 70: Bauxite & Alumina

    Slide 70: Bauxite & Alumina

    Bauxite & Alumina

  71. Slide 71: MRN, Paragominas and Alunorte

    Slide 71: MRN, Paragominas and Alunorte

    MRN bauxite mine Paragominas bauxite mine Alunorte alumina refinery • Top 3 bauxite mine in the world • 100% ownership • 92% ownership • 2021 production 6.3 • 5% ownership • Nameplate capacity of 9.9 million tonnes • World’s largest alumina million tonnes • Volume off-take agreement for Vale’s 40% s

  72. Slide 72: Paragominas bauxite mining costs

    Slide 72: Paragominas bauxite mining costs

    • Energy cost - Power and fuel Indicative Paragominas bauxite mining costs • Large fixed cost base Labor 16% Energy • Labor cost 25% Support & infrastructure • Influenced by Brazilian wage level Maintenance/consumables Other costs • Maintenance and consumables • Mainly influenced by Brazilian inflat

  73. Slide 73: Implied alumina cost composition

    Slide 73: Implied alumina cost composition

    • Implied alumina cost 2022 - USD 345 per mt1) Indicative implied alumina cost composition • Alunorte, Paragominas and external alumina sourcing for resale • Bauxite 11% 17% Bauxite • Internal bauxite from Paragominas at cost, sourced bauxite from MRN Caustic soda • External bauxite sales 13% Energy

  74. Slide 74: External alumina sourcing and bauxite and alumina positions

    Slide 74: External alumina sourcing and bauxite and alumina positions

    External alumina sourcing Long positions in bauxite and alumina • 2.0-2.5 million mt of external alumina sourced annually • Pricing should reflect bauxite and alumina market fundamentals • Long term off-take agreement with Rio Tinto • Selling surplus MRN bauxite externally • ~900 000 mt annually fro

  75. Slide 75: Annual EBITDA sensitivities for alumina

    Slide 75: Annual EBITDA sensitivities for alumina

    Annual sensitivities on adjusted EBITDA if +10% in price Revenue impact NOK million • Realized alumina price lags PAX by one month 1 720 Cost impact Bauxite • ~2.45 tonnes bauxite per tonne alumina • Pricing partly LME-linked Caustic soda (30) (150) • ~0.1 tonnes per tonne alumina (250) (630) • Pric

  76. Slide 76: Alunorte CO2e emissions per tonne of alumina

    Slide 76: Alunorte CO2e emissions per tonne of alumina

    CO2e per ton of Alumina (scope 1 and 2) CRU Global Alumina 2022 Alunorte Fuel Switch Alunorte today Electrical boilers by 2025 • 1st quartile on CO2e • 1st decile on CO2e (0.65t CO2e) • Reduce 25%, 0.45t CO2e • 46% below the industry by 2025 average • 63% below the industry average 2022 Industry avg

  77. Slide 77: Alunorte fuel switch and electrical boilers

    Slide 77: Alunorte fuel switch and electrical boilers

    Tonnes CO2e / tonne aluminium Scope 1 and 2 emissions 3,2 ~1.4 • Replacing heavy fuel oil with natural gas • Reducing annual CO2e emissions by 700,000 tonnes 2025: Fuel Switch • Cost BRL ~1.3 billion (NOK ~2 billion) & elBoilers • First gas consumption in Q2 2023 and all oil assets converted to gas

  78. Slide 78: Alunorte returns and capex

    Slide 78: Alunorte returns and capex

    Returns below the cost of capital reflecting challenging markets, embargo and operational issues during the early years Capital employed in B&A 12 % 9% 24 % 6% 6% 3% 2% ~26 BNOK (31 Dec.22) 2017 2018 2019 2020 2021 2022 Adjusted EBITDA FY 2022 Return requirement 2017-2022 average ARoaCE Capex, BNOK

  79. Slide 79: Energy

    Slide 79: Energy

    nergy

  80. Slide 80: Center of energy excellence in Hydro

    Slide 80: Center of energy excellence in Hydro

    Center of energy excellence in Hydro Bauxite Alumina Primary Extrusion ~25% ~35% ~35% Energy cost 1) ~8% ~50% Energy business area’s • Power sourcing • Power sourcing • Power sourcing and • Power sourcing contribution to Hydro production • Fuel switch project (LNG) • Gas sourcing • Gas sourcing • En

  81. Slide 81: Energy portfolio across the aluminium value chain

    Slide 81: Energy portfolio across the aluminium value chain

    Spanning the entire aluminium value chain, all global regions and energy carriers Hydro’s total energy portfolio amounts to ~210 million GJ per year based on ownership equity Europe Power 18.3 TWh North America Natural gas 4.5 million MMBtu Power Natural gas Power 2.2 TWh Power Natural Natural gas 6

  82. Slide 82: Power sourcing and revenue in Norway

    Slide 82: Power sourcing and revenue in Norway

    Based on external price references Sourcing side Revenue side TWh TWh Spot price 0-3 3) • Long-term contract 1 9.4 (7-11) 1) • Market pricing • Fixed annual Regulated pricing price adjustments • Market pricing 16-182) • Duration varies • Different Mainly Back-to-back 8-104) indexation parameters Nor

  83. Slide 83: Energy adjusted EBITDA and NO2 spot price

    Slide 83: Energy adjusted EBITDA and NO2 spot price

    Adjusted EBITDA and NO2 spot price • Production and market prices strongly linked to hydrological NOK million NOK/MWh conditions 5 500 2500 5 000 4 500 • Seasonal market variations in demand and supply. Gains or losses 2000 4 000 3 500 1500 may occur from delink between area prices arising due to 3

  84. Slide 84: Realizing value in Batteries, Hydro Rein and Hydro Havrand

    Slide 84: Realizing value in Batteries, Hydro Rein and Hydro Havrand

    Realizing value potential in Batteries, Hydro Rein & Hydro Havrand 2020: Hydro 2025 Strategy 1905 1991 2016 - 2019 2017 2021 Wind power PPAs First battery investment Latest growth asset Energy markets operations Hydro Rein Batteries unit established Hydro Havrand established 2021 Developer, owner an

  85. Slide 85: Hydropower operations and power market player

    Slide 85: Hydropower operations and power market player

    Excellent hydropower operations & growth projects Leading power market player 14.0 TWh NOK 1 billion 200 GWh Operations of power Potential Hydro Potential increased Top 5 in Europe Among the top 10% assets in Norway. Market analysis, market largest energy trading investments in Lyse production in Fo

  86. Slide 86: Energy strategy: commercialize positions and decarbonize

    Slide 86: Energy strategy: commercialize positions and decarbonize

    Operations and projects: HSE excellence, Decarbonizing Hydro operating 40 power plants across Norway • Power sourcing, managing and matching profiles and (hydropower and wind). Large scale project execution consumptions across new units and Hydro • Hydro Rein offering renewable power and energy solu

  87. Slide 87: Renewable energy producer, market player and offtaker

    Slide 87: Renewable energy producer, market player and offtaker

    Major renewable energy producer, market player and offtaker In Operation Offtake Aluminium Metal Hydropower in Norway (equity): 9.4 TWh Norwegian smelters: 17 TWh Hydropower in Norway (operator): 13 TWh Wind power in Norway (operator): 0.7 TWh Offtake Extrusions Selected Extrusion plants: 0.1 TWh So

  88. Slide 88: Hydro Rein progress last 24 months

    Slide 88: Hydro Rein progress last 24 months

    Significant progress last 24 months Hydro Rein EBITDA estimates 2026/27. CAPEX 21-26 3.6 TWh NOK 2.5 billion signed under long-term USD 2.7 billion Remaining capex for contracted revenues projects in construction, EUR & USD PPAs incl. 2.1 BNOK in 2023 20 1.7 GW 30 gross capacity in numbers of renewa

  89. Slide 89: Portfolio of complementary inside-the-fence projects

    Slide 89: Portfolio of complementary inside-the-fence projects

    Sørlige Nordsjø II, offshore wind, phase I: 1,500 MW Focus on early phase opportunities Stor-Skälsjön, wind: 260 MW Southern Sweden, 9 early wind development projects: 672 MW Development model based on strategic partnerships with Jylland in Denmark, 2 solar relevant stakeholders, from landowners to

  90. Slide 90: Strategic growth in battery value chain

    Slide 90: Strategic growth in battery value chain

    S T R AT E G I C G R O W T H Anode materials Circular solutions Battery materials Vianode targeting substantial market Hydrovolt targeting 25% market share Selectively explore share for synthetic graphite in Europe within EV battery recycling in Europe. and North America Work to integrate downstream

  91. Slide 91: Vianode synthetic graphite capacity and emissions

    Slide 91: Vianode synthetic graphite capacity and emissions

    Description Status Capacity • All process steps • Small size industrial Emissions reduction compared to the production process in today’s market equipment R&D In operation • Located in Kristiansand, Samples Norway • All process steps Renewable power • Industrial environment In operation Customer • N

  92. Slide 92: Batteries progress last 24 months

    Slide 92: Batteries progress last 24 months

    Significant progress last 24 months Key capabilities 10,000 20,000 2x EVs with Vianode Value uplift on equity EV batteries secured by Raw materialsScaling capability, energy expertise graphite from plant invested Hydrovolt and automotive experience under construction 90% NOK 3 billion NOK 0.9 billio

  93. Slide 93: Hydrogen: first mover position from industrial consumption

    Slide 93: Hydrogen: first mover position from industrial consumption

    First mover position from industrial consumption in Hydro Strategic approach and overview Establishing as a developer, owner and operator of Multi-GW 30% 70+ green hydrogen production facilities. potential internal Hydro reduction of Hydro potential Hydro offtake emissions by 2030 locations worldwid

  94. Slide 94: Expanded footprint in the Nordics

    Slide 94: Expanded footprint in the Nordics

    Expanded footprint in the Nordics in terms of 1 power and market operations, projects and sourcing 2 Sourcing and management of power and fuels for Hydro operating assets across geographies Hydro Rein successfully established as separate 3 company with external capital and partners Hydro Havrand dev

  95. Slide 95: Energy returns and capex

    Slide 95: Energy returns and capex

    Returns above the cost of capital reflecting the depreciated asset base Capital employed in Energy 30 % 25 % 9% 18 % 19 % 13 % ~10 BNOK 9% 6-7% (31 Dec.22) 2017 2018 2019 2020 2021 2022 Adjusted EBITDA FY 2022 Return requirement 2017-2022 ~19% average ARoaCE Capex, BNOK Lower realized unit 4.0 Selec

  96. Slide 96: Aluminium Metal

    Slide 96: Aluminium Metal

    Aluminium Metal

  97. Slide 97: Aluminium Metal and Metal Markets production sites

    Slide 97: Aluminium Metal and Metal Markets production sites

    Aluminium Metal and Metal Markets Norway, 1 155 000 tonnes 50% • Sunndal (100%): 425,000 tonnes • Årdal (100%): 200,000 tonnes • Karmøy (100%): 270,000 tonnes • Høyanger (100%): 65,000 tonnes • Husnes (100%): 195,000 tonnes Slovakia, 175 000 tonnes 8% • Slovalco (100%): 175,000 tonnes • Hydro owns 5

  98. Slide 98: Emissions and energy consumption in Hydro smelters

    Slide 98: Emissions and energy consumption in Hydro smelters

    Total emissions, in tonne CO2/t al Energy consumption in Hydro smelters1), kwh/kg al 18 17.5 18 16 16 15.0 14.8 14.4 14.1 14 13.9 13.5 14 12.5 12.3 12 11.5-11.8 12 10.0 10 10 8 8 6 6 4 4 2 2 0 0 Hydro Karmøy Hydro Hydro Hydro Hydro Hydro HAL300HAL4E HAL4e HAL4e Hydro 1967 1993 1998 2003 2018 2020 20

  99. Slide 99: Primary aluminium cash cost 2022

    Slide 99: Primary aluminium cash cost 2022

    • Primary aluminium cash cost 2022 Liquid aluminium cash cost 20223) • All-in implied primary aluminium cash cost1,2) USD 2 375 per mt • LME implied primary aluminium cash cost1,3) USD 1 575 per mt • Alumina • Purchases based on alumina index ~93% 6% • Purchased based on LME link ~7% (only for Qatal

  100. Slide 100: Annual EBITDA sensitivities for aluminium

    Slide 100: Annual EBITDA sensitivities for aluminium

    Annual sensitivities on adjusted EBITDA if +10% in price Revenue impact NOK million • Realized price lags LME spot by ~1-2 months • Realized premium lags market premium by ~2-3 months 3 130 Cost impact 530 Alumina • ~1.9 tonnes per tonne aluminium • ~ 2-3 months lag (580) (230) • Mainly priced on Pl

  101. Slide 101: HalZero on track for first metal by 2025

    Slide 101: HalZero on track for first metal by 2025

    On track to deliver first metal by 2025 and industrial scale pilot volumes by 2030 Promising technology basis confirmed Funding received Norwegian Research Council and Gassnova Test site chosen Hydro Porsgrunn Technology Center Final engineering of test facility close to completion Construction plan

  102. Slide 102: Carbon capture on track for first metal by 2025

    Slide 102: Carbon capture on track for first metal by 2025

    On track to deliver first metal by 2025 and industrial scale pilot volumes by 2030 Successfully completed first test at the Sunndal smelter Further testing in progress for 2023 Second test planned for early 2023, received funding from Gassnova Location of industrial scale pilot to be decided Verdox

  103. Slide 103: Sorting technology and casthouse decarbonization

    Slide 103: Sorting technology and casthouse decarbonization

    Advanced sorting technology ready. Progress on casthouse decarbonization technology HySort technology ready for industrialization Program to test viable technologies in progress Enabling further growth in Hydro CIRCAL and scaling Green hydrogen test pilot by Hydro Havrand to be built at production o

  104. Slide 104: Aluminium Metal returns and capex

    Slide 104: Aluminium Metal returns and capex

    Investments in recycling capacity to support growth Capital employed in AM (MM) 35 % 28 % 13 % 5% 3% ~44 (4) -3 % BNOK 2017 2018 2019 2020 2021 2022 (31 Dec.22) Adjusted EBITDA FY 2022 4% Return requirement 40 % 2017-2022 average ARoaCE Capex, BNOK 5.0 4.0 Sustain and Investments in 3.0 improve1) re

  105. Slide 105: Metal Markets

    Slide 105: Metal Markets

    f v Metal Markets

  106. Slide 106: Value-added casthouse products and flexible sourcing

    Slide 106: Value-added casthouse products and flexible sourcing

    • Capitalizing on value-added casthouse Leading global position products portfolio Extrusion ingot Unique primary and • Extensive multi-sourcing system 1.6 million mt recycling capacity network including fully- and part-owned primary casthouses and stand-alone remelters Leading global position Found

  107. Slide 107: Pricing of value-added products by region

    Slide 107: Pricing of value-added products by region

    Smelter Intermediate product Casthouse Aluminium Standard ingot Value added products Extrusion ingot Foundry alloy Sheet ingot Wire rod Traded on LME • US Midwest - 1020 • Extrusion Ingot – Priced above standard ingot • Foundry Alloy – Priced above standard ingot US (in cent per pound) • Sheet ingot

  108. Slide 108: Metal Markets earnings drivers

    Slide 108: Metal Markets earnings drivers

    • Recyclers Adjusted EBITDA excluding currency effects and inventory valuation effect, • Revenue impact – volume and product premiums NOK million1) above LME 800 • Cost impact 700 • Scrap and standard ingot premiums above LME • Raw material mix 600 • Freight cost – proximity to market 500 • Energy c

  109. Slide 109: Recycling investments, PCS usage and EBITDA uplift

    Slide 109: Recycling investments, PCS usage and EBITDA uplift

    Key investment decisions made PCS usage and ambition 620-770 Tonnes (‘000) 520-670 100 150 +300-450 80 120 40 280 2) 2020 2022 Creep Growth/ Alumetal 2025 new Growth 2027 other EBITDA uplift NOK million 3.1-3.5 2.6-3.0 0.5 0.4 3.0 -2.8 0.4 0.4 0.2 +1.5-1.9 0.8 1.4 2020 2022 2022 market Creep Growth/

  110. Slide 110: Post-consumer scrap availability and price spread

    Slide 110: Post-consumer scrap availability and price spread

    Global estimated recovery from Price spread LME vs. complex Large scrap volumes leaving Europe, ~1 post-consumer scrap collected increases post-consumer scrap increased million tons – an untapped potential Million tons USD/tonne 3800 70 Forecast 3300 60 2800 50 2300 40 1800 30 1300 AM Recycling inde

  111. Slide 111: Scrap sourcing, sorting and recycling portfolio

    Slide 111: Scrap sourcing, sorting and recycling portfolio

    Scrap sourcing Scrap shredding Large Recycling Multiple product Product and market Meeting customer and partnering and sorting asset base segments development needs - partnerships Market scrap – Scrap conversion for Primary Customer increased share of customers ingots scrap complex PCS Extrusion Ing

  112. Slide 112: Combined asset base in Europe and North America

    Slide 112: Combined asset base in Europe and North America

    Utilizing our combined competencies, strong asset base, market position and value chain Europe Aluminium Metal 5 Primary smelters 5 Extrusions 10 North America Aluminium Metal 3 Extrusions 9 112

  113. Slide 113: Extrusions

    Slide 113: Extrusions

    Extrusions

  114. Slide 114: Extrusions at a glance

    Slide 114: Extrusions at a glance

    Present in ~40 countries ~ 21 400 people 1) 1.3 Million mt sales2) 1) Permanent employees as of end-2022 2) Total sales in 2022 114

  115. Slide 115: Unrivalled position as #1 extrusions provider globally

    Slide 115: Unrivalled position as #1 extrusions provider globally

    Unrivalled position as #1 extrusions Four distinct Business Units, all with strong segment presence provider globally Total volume 2022: 1.3 million tonnes Extrusion sales volume (2022), tonnes (000s) 1500 Building 7% Systems Distribution 11% Precision 9% Tubing 1000 Automotive 16% Extrusion Transpo

  116. Slide 116: Extrusions business units

    Slide 116: Extrusions business units

    21,400 highly competent people across the world, total turnover of BNOK 91 Extrusion Europe Extrusion North America Precision Tubing Building Systems • Market leader focusing on • Uniquely positioned as the only • Global Technology market leader in • Leading European player with value-added products

  117. Slide 117: Extrusions contract structure and earnings per tonne

    Slide 117: Extrusions contract structure and earnings per tonne

    Adjusted EBITDA per tonne1), NOK • Contract structure 8 000 • Margin business based on conversion price • LME element passed on to customers 7 000 • Mostly short-term contract, typically ranging from spot to 12 months, few 6 000 longer term contracts with floating price or hedging in place 5 000 • H

  118. Slide 118: Building Systems and Precision Tubing growth opportunities

    Slide 118: Building Systems and Precision Tubing growth opportunities

    Building Systems and Precision Tubing offering unique value added and specialty solutions growth opportunities • Increased penetration in E-mobility supported by substitution Extrusion Europe • Recycling capacity to facilitate increased PCS usage • Grow in automotive and commercial transport Extrusi

  119. Slide 119: Competitive cost base and targeted capacity expansion

    Slide 119: Competitive cost base and targeted capacity expansion

    More competitive cost base, stronger customer interaction, targeted capacity expansion and sustainability agenda provide for business resilience going forward • Strong focus on selected segments where Extrusions has competitive advantage Portfolio restructuring • Exited non-attractive operations and

  120. Slide 120: Extrusions EBITDA and margin by unit

    Slide 120: Extrusions EBITDA and margin by unit

    Extrusions EBITDA EBITDA-margin per unit in Hydro Extrusion (%) NOK billions 0.6 2022 YTD Sep >5% 2018 YTD Sep 2.0 5.7 -1.3 0-5% 0.3 <0% 4.1 Adj. EBITDA Underlying Core Commercial Inflation and Actual 2021 2018 market improvement ambitions other EBITDA growth levers adjustments Total Hydro Extrusion

  121. Slide 121: Extrusions EBITDA target 2025

    Slide 121: Extrusions EBITDA target 2025

    Extrusions EBITDA NOK billions 0.9 Uplift from projects under execution 0.6 Continued cost reduction 8.0 programs, including 1.3 -1.3 procurement and EBS Customer partnerships and 0.8 Commercial Excellence initiatives 5.7 Actual 2021 EBITDA Underlying market growth Core improvement levers Commercial

  122. Slide 122: Strengthening flagship plants in the portfolio

    Slide 122: Strengthening flagship plants in the portfolio

    Further strengthening flagship plants in the portfolio, leveraging key trends • Sustainable products with low-carbon Hungary recycling footprint Cressona Bay-Zero The Dalles upgrade • Recyclability and keeping materials “in (recycling upgrade) the loop” Navarra recycling • Greener energy sourcing Sj

  123. Slide 123: Extrusions returns and capex

    Slide 123: Extrusions returns and capex

    Returns in line with the cost of capital reflecting leading market positions in high value segments and portfolio optimization Capital employed in Extrusions 11 % 10 % 7% 7% 6% 6% 23 % ~26 BNOK 2017 2018 2019 2020 2021 2022 (31 Dec.22) Adjusted EBITDA FY 2022 Return requirement 2017-2022 average ARo

  124. Slide 124: Additional information

    Slide 124: Additional information

    ») Hydro Additional information

  125. Slide 125: Adjusted EBITDA Q4 2022 vs Q4 2021

    Slide 125: Adjusted EBITDA Q4 2022 vs Q4 2021

    Q4-2022 vs Q4-2021 9.0 2.7 7.2 3.6 Other & eliminations 0.4 0.3 CO2 compensation Power sales Slovalco, Karmøy & Husnes 1.9 2.0 0.6 0.6 1.7 0.6 Adj. EBITDA Q4 2021 Realized aluminium Raw material cost Downstream margin Downstream volume Fixed cost FX Power sales, CO2 Adj. EBITDA Q4 2022 and alumina p

  126. Slide 126: Adjusted EBITDA FY 2022 vs FY 2021

    Slide 126: Adjusted EBITDA FY 2022 vs FY 2021

    FY 2022 vs FY 2021 Other & eliminations CO2 compensation 5.5 39.7 0.4 Power sales Slovalco, Karmøy & Husnes 2.3 13.6 13.7 2.8 1.5 2.9 3.7 28.0 4.0 Adj. EBITDA 2021 Realized aluminium Raw material cost Downstream Energy price Fixed cost FX Power sales, CO2 Adj. EBITDA 2022 and alumina price margin an

  127. Slide 127: Net cash position and free cash flow 2022

    Slide 127: Net cash position and free cash flow 2022

    Still in a net cash position before adjustments due to strong earnings in 2022 NOK billion Free cash flow NOK 14.0 billion (8.8) (6.1) 39.7 (10.8) Hedging collateral and other Pension assets/(liabilities) (14.7) Other assets/(liabilities) 3.2 (1.2) 1.3 (2.6) (0.3) (4.5) (7.3) (6.0) Net cash adj. EBI

  128. Slide 128: Items excluded from adjusted EBITDA

    Slide 128: Items excluded from adjusted EBITDA

    NOK million (+=loss/()=gain) Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2021 Year 2022 Unrealized derivative effects on raw material contracts Hydro Bauxite & Alumina (27) (84) (143) 113 (376) (173) 157 353 (141) (40) Community contributions Brazil Hydro Bauxite & Alumina -

  129. Slide 129: Adjusted EBIT and adjusted EBITDA by segment

    Slide 129: Adjusted EBIT and adjusted EBITDA by segment

    Adjusted EBIT NOK million Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2020 Year 2021 Year 2022 Hydro Bauxite & Alumina 535 1 047 108 116 556 383 466 1 913 718 484 10 (586) 1 806 3 318 626 Hydro Aluminium Metal 573 (37) (156) 844 1 185 2 246 3

  130. Slide 130: EBIT and EBITDA by segment

    Slide 130: EBIT and EBITDA by segment

    EBIT NOK million Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2020 Year 2021 Year 2022 Hydro Bauxite & Alumina 406 1 047 108 111 583 467 407 1 830 1 094 657 (147) (1 133) 1 672 3 288 471 Hydro Aluminium Metal 784 (777) (93) 880 (171) 325 909 7

  131. Slide 131: Total and external revenue

    Slide 131: Total and external revenue

    Total revenue NOK million Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2020 Year 2021 Year 2022 Hydro Bauxite & Alumina 6 029 6 173 5 334 5 503 6 026 5 976 6 984 8 713 7 901 9 413 8 652 7 986 23 039 27 699 33 951 Hydro Aluminium Metal 9 753 7 7

  132. Slide 132: Internal revenue and equity accounted profit

    Slide 132: Internal revenue and equity accounted profit

    Internal revenue NOK million Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2020 Year 2021 Year 2022 Hydro Bauxite & Alumina 2 780 2 380 2 168 2 330 2 479 2 438 2 452 3 242 2 848 3 549 3 011 2 895 9 658 10 610 12 303 Hydro Aluminium Metal 7 785 6

  133. Slide 133: Return on average capital employed

    Slide 133: Return on average capital employed

    Return on average capital employed 1) (RoaCE) Reported RoaCE Adjusted RoaCE 2022 2021 2020 2019 2018 2017 2016 2022 2021 2020 2019 2018 2017 2016 Hydro Bauxite & Alumina 1.3% 11.9% 5.4% 1.9% 4.6% 8.5% 2.7% 1.8% 12.0% 5.9% 2.5% 6.0% 8.5% 2.8% Hydro Aluminium Metal 35.1% 21.6% 1.9% (3.9%) 5.6% 11.8% 5

  134. Slide 134: Depreciation, amortization and impairment

    Slide 134: Depreciation, amortization and impairment

    Depreciation, amortization and impairment NOK million Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2020 Year 2021 Year 2022 Hydro Bauxite & Alumina 567 503 470 472 443 472 589 514 553 633 624 687 2 011 2 018 2 496 Hydro Aluminium Metal 655 1 13

  135. Slide 135: Condensed income statement

    Slide 135: Condensed income statement

    NOK million Q4 2022 Q4 2021 Q3 2022 Year 2022 Year 2021 Revenue 44 075 46 433 52 445 207 929 149 654 Share of the profit (loss) in equity accounted investments 131 473 426 1 337 1 340 Other income, net 1 051 942 2 036 4 406 2 219 Total revenue and income 45 256 47 848 54 908 213 672 153 212 Raw mate

  136. Slide 136: Condensed balance sheet

    Slide 136: Condensed balance sheet

    NOK million Dec 31, 2022 Sep 30, 2022 Jun 30, 2022 Mar 31, 2022 Dec 31, 2021 Sep 30, 2021 Jun 30, 2021 Mar 31, 2021 Cash and cash equivalents 29 805 25 852 24 507 21 161 22 923 18 792 20 147 15 011 Short-term investments 4 173 2 511 1 882 8 588 6 763 7 020 3 607 4 348 Trade and other receivables 23

  137. Slide 137: Hydro Bauxite & Alumina key figures

    Slide 137: Hydro Bauxite & Alumina key figures

    Hydro Bauxite & Alumina Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2020 Year 2021 Year 2022 Alumina production (kmt) 1 531 1 442 1 074 1 410 1 540 1 586 1 579 1 600 1 519 1 536 1 579 1 559 5 457 6 305 6 193 Sourced alumina (kmt) 664 667 940 7

  138. Slide 138: Hydro Metal Markets and Extrusions key figures

    Slide 138: Hydro Metal Markets and Extrusions key figures

    Hydro Metal Markets Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022 Q4 2022 Year 2020 Year 2021 Year 2022 Remelt production (1 000 mt) 137 88 124 140 143 154 132 144 151 158 124 115 488 572 548 Third-party sales (1 000 mt) 79 85 85 77 77 78 72 85 72 74 76 81 3

  139. Slide 139: Precision Tubing and Extrusion Europe key figures

    Slide 139: Precision Tubing and Extrusion Europe key figures

    Q1 Q2 Q3 Q4 Year Q1 Q2 Q3 Q4 Year Q1 Q2 Q3 Q4 Year Q1 Q2 Q3 Q4 Year Q1 Q2 Q3 Q4 Year Q1 Q2 Q3 Q4 Year Precision Tubing 2020 2020 2020 2020 2020 2021 2021 2021 2021 2021 2022 2022 2022 2022 2022 Extrusion Europe 2020 2020 2020 2020 2020 2021 2021 2021 2021 2021 2022 2022 2022 2022 2022 Volume (kmt) 2

  140. Slide 140: Next event and contact information

    Slide 140: Next event and contact information

    Next event Line Haugetraa First quarter results t: +47 41406376 e: [email protected] April 28, 2023 Martine Rambøl Hagen For more information see t: +47 91708918 e: [email protected] www.hydro.com/ir Camilla Gihle t: +47 92637820 e: [email protected] 140

  141. Slide 141: Hydro: Industries that matter

    Slide 141: Hydro: Industries that matter

    Hydro Industries that matter

Source: Internet Archive copy of hydro.com

More decks from Norsk Hydro ASA

All 457 Norsk Hydro ASA decks