Slide 1: Autoroutes du Sud de la France Analyst day
Autoroutes du Sud de la France Analyst day July 2007 www.asf.fr

Slide 2: Disclaimer
Disclaimer This presentation contains forward-looking statements which are based on current plans and forecasts of VINCI’s management. Such forward-looking statements are by their nature subject to a number of important risk and uncertainty factors, as those described in the registration document fi

Slide 3: List of participants
List of participants Christian LABEYRIE Executive Vice President of VINCI Vice-President and Chief Financial Officer of VINCI Jacques TAVERNIER Senior Executive Vice President of VINCI Chief Executive Officer of VINCI Concessions Chairman and CEO of ASF Patrick PRIAM Chief Financial Officer of ASF P

Slide 4: Table of contents
Table of contents 1. Business profile Page 5 2. Contractual framework Page 12 3. 2007–2011 Programme Contracts Page 17 4. Financial profile Page 30 5. Operational performance Page 44 6. 2007 outlook Page 54 7. Valuation Page 56 Conclusion Page 62 Appendices Page 65 4

Slide 5: 1. Business Profile
4 @ Autoroutes q| du Sud I, ~) W de la France Asubsidiary of WIN Pa 1. Business Profile

Slide 6: Shareholding structure
Shareholding structure (As of July 2007) VINCI VINCI CONCESSIONS 100% ASF Holding 100% 77%* ASF 23% Escota 1% Local authorities 99% and institutions VINCI Cofiroute 100% ENERGIES 83% EUROVIA VINCI Park 100% 100% VINCI CONSTRUCTION Other transport 100% infrastructure – concessions VINCI * Transfer of

Slide 7: ASF group: the major French toll-road operator
ASF group: the major French toll- toll-road operator ASF + Escota: Escota: # 1 toll- toll-road operator in France and # 2 toll- toll-road operator in Europe Mature and almost completed network: • 3,160 km of conceded network • 3,026 km under operation Strategic location at crossroads of Southern Eur

Slide 8: Strategic location at crossroads of Europe
Strategic location at crossroads of Europe Urban network with strong daily traffic: Lyon, Montpellier, Toulouse, Bordeaux, Nice 3 cross-boarder zones Summer traffic peak: A7-A9: 160,000 vehicles/day Traffic types Tourist and economic flows Daily traffic Significant experience in managing diversified

Slide 9: Overview
Overview Total ASF* Escota ASF Group Company created in 1957 1956 - Network under operation (km) 2,567 459 3,026 Total network conceded (km) 2,701 459 3,160 End of concession 31/12/2032 31/12/2026 - 2006 Number of kilometers travelled 27,039 6,428 33,467 (millions of km) 2006 Annual Average Daily Tr

Slide 10: A strong traffic dynamism
A strong traffic dynamism Established track record of steady traffic growth A diversified user base Km traveled Revenue 35000 2006 figures 2006 millions of km travelled 30000 HV 25000 15% HV 20000 29% 15000 10000 5000 0 LV 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 LV 71% Stable network Netwo

Slide 11: High profitability and increasing positive free cash flow
High profitability and increasing positive free cash flow Revenue EBITDA (Cash flow from operations before tax and financing cost) 3000 1800 1,706 2,625 1,572 2,474 1600 1,520 2500 2,389 2,572 1,418 2,239 1400 in €m 1,310 in €m 2,104 2,427 CAGR: +7% 2,343 2000 2,190 1200 2,053 CAGR: +6% 1000 1500 80

Slide 12: 2. Contractual framework
: W@ Autoroutes NW du Sud ; 7 BID de ia France | - A subsidiary of vinci 2. Contractual framework 12

Slide 13: General framework
General framework French State “the Grantor” Grantor” (Department of Transport “Direction Générale des Routes” Routes”) 5-year Program Contracts Concession Contract “Contrats de Plan” Plan” Caisse Nationale des Autoroutes (CNA)* Financing ASF Group: Construction work Construction EIB Concessionaire

Slide 14: A transparent and protective legal framework
A transparent and protective legal framework Relations with the Grantor are governed by: – 3 Concession Contracts (ASF, Escota, Puymorens Tunnel) and their Amendments which determine general framework – 5-year Programme Contracts (“Contrats de Plan”) can be added to define through the period: The de

Slide 15: A transparent and protective legal framework
A transparent and protective legal framework Early termination of the concession for default – The concession contract may be terminated by decision of the Grantor approved by decree of the Conseil d'Etat (the equivalent of the French Supreme Court), should any major contractual breaches not be reme

Slide 16: Clear contract awarding procedures
Clear contract awarding procedures Conditions of awarding contracts for civil works and all supply or services have been clearly set by the Grantor: – Public tender is required for all civil works contracts above € 2,000,000 and all supply or services contracts above €240,000 – A “Commission Consult

Slide 17: 3. 2007–2011 Programme Contracts
3. 2007– 2007–2011 Programme Contracts “Contrats de plan” plan” 17

Slide 18: A clear tariff policy
A clear tariff policy Tariffs (applicable to class 1 vehicles*) 2007 2008 to 2011 ASF 85% CPI 85% CPI +1.0925 % + 0.825 % Escota 85% CPI + 0.9 % CPI, Consumer Price Index: French inflation index excluding tobacco * Class 1 vehicles = light vehicles (see page 19) As a result of the formula here above

Slide 19: New tariffs coefficients
New tariffs coefficients Tariff coefficients ASF Escota Class 1 Light vehicles 1x 1x Class 2 Light vehicles 1.55 x 1.51 x Class 3 Heavy vehicles Evolutive Evolutive See here below Class 4 Heavy vehicles Evolutive Evolutive See here below Class 5 Light vehicles 0.60 x 0.62 x Tariff coefficients for h

Slide 20: Capital expenditures
Capital expenditures 2007- 2007-11 Programme Contract: total CAPEX over the period * In constant 2006 € ASF Construction of new sections €1,317m of which Lyon-Balbigny (A89) €950m Supplementary investments in motorways in service (“ICAS”) €1,315m of which road widening € 694m safety investments €150

Slide 21: Capital expenditures – ASF Group
Capital expenditures – ASF Group (ASF + Escota) Escota) 1200 1000 in current €m 800 600 400 200 0 2007 2008 2009 2010 2011 Ne w se c t i o n s (e xc l u d i ng Bal b i g n y- L yo n ) Bal b i g n y- L yo n I CAS O t he r i nve st me nt s (I E AS) & c ap i t al i se d b o r r o wi n g c o st s ICAS:

Slide 22: Capital expenditures - ASF
Capital expenditures - ASF 1000 800 in current €m 600 400 200 0 2007 2008 2009 2010 2011 Ne w se c t i o n s (e xc l u d i ng Bal b i g n y- L yo n ) Bal b i g ny- L yo n I CAS O t h e r i n ve st me n t s (I E AS) & c ap i t al i se d b o r r o wi ng c o st s ICAS: Complementary investments in exis

Slide 23: Capital expenditures - Escota
Capital expenditures - Escota 250 200 in current €m 150 100 50 0 2007 2008 2009 2010 2011 ICA S Other inve stments (IEA S) & capitalised bo rrowing costs ICAS: Complementary investments in existing motorways IEAS: Operating investments in existing motorways 23 See definitions on slide 76

Slide 24: Capital expenditures - new sections
Capital expenditures - new sections Scheduled in constant Nb of km Opening date 2006 €m Completion of the A89 Mid-2008 22 km 130 (Bordeaux/Clermont-Ferrand) Completion of the A87 Mid-2008 23 km 150 (Angers/La Roche-sur-Yon) A89 - Balbigny/Lyon End of 2012 53 km 950 A75/A9 Beziers East bypass Q1 2010

Slide 25: New sections: A89 – Balbigny/Lyon
New sections: A89 – Balbigny/Lyon Balbigny/Lyon Key figures Length: 53 km 7 interchanges 7 viaducts 3 tunnels for a total length of 6 km Construction cost: €1.4bn (in current euros) Opening in Dec. 2012 Link between major East-West highway 89 Bordeaux/Clermont-Ferrand to Lyon’s conurbation Decongest

Slide 26: Investments on motorways in service (ICAS): ASF
Capital expenditures - Investments on motorways in service (“ (“ICAS” ICAS”): ASF Scheduled in constant Nb of km opening date 2006 €m A9 widening* in Montpellier April 2013 19 km 278 A63 Biriatou/Ondres widening* Mid- 2014 40 km 330 A9 Perpignan Nord/Sud widening* Mid-2013 14 km 86 Safety, environme

Slide 27: Investments on motorways in service (ICAS): Escota
Capital expenditures - Investments on motorways in service (“ (“ICAS” ICAS”): Escota in constant Opening date Nb of km 2006 €m Investments in tunnel safety (19 tunnels) - 13.4 264 A8 widening* Mid-2010 30.5 138 (Châteauneuf-le –Rouge / Saint Maximin & Saint Augustin / Saint Isidore) A50-52 widening*

Slide 28: New safety and quality of service requirements
New safety and quality of service requirements Main innovations of the new Programme Contract: Toll collection – Increased automation of the tolls – Tariff adjustment on traffic fluidity under study, restricted to specific purposes (e.g. environment, holidays departures) Traffic fluidity – Speed con

Slide 29: New safety and quality of service requirements
New safety and quality of service requirements Safety – More developed communication and prevention – Implementation of a Security Programme (protection of construction sites, prevention of driving into head-on traffic) Services to heavy vehicles – Creation of 1,500 additional heavy vehicle park spa

Slide 30: 4. Financial profile
4 @ Autoroutes q| du Sud I, ~) W de la France Asubsidiary of WIN Pa 4. Financial profile 30

Slide 31: Toll revenues on ASF network
Toll revenues on ASF network Total ASF 2006 / 2005 ASF Escota group Traffic on stable network +2.1% +2.5% +2.2% New sections +0.5% - +0.4% Effect of traffic +2.6% +2.5% +2.6% Effect of increased toll prices +3.6% +2.5% +3.4% Total toll receipts +6.2% +5.0% +6.0% - light vehicles +5.5% +4.8% +5.3% -

Slide 32: Key figures
Key figures in € million 2005 2006 ∆06/05 Revenue 2,474 2,625 +6.1% of which toll revenues 2,427 2,572 +6.0% EBITDA (Cash flow from operations) 1,572 1,706 +8.5% as % of revenue 63.5% 65,0% Net profit 435 475 +9.3% as % of revenue 17.6% 18.0% Net financial debt 7,627 7,355 Adjusted net financial deb

Slide 33: 2006 consolidated P&L (1/2)
2006 consolidated P&L (1/2) in € million 2005 2006 ∆ 06/05 Revenue 2,474 2,625 +6.1% Purchases & external charges (232) (226) Taxes (excluding corporate income taxes) (360) (370) Payroll costs (323) (329) Miscellaneous 12 6 EBITDA 1,572 1,706 +8.5% as % of revenue 63.5% 65,0% Depreciation & amortiza

Slide 34: 2006 consolidated P&L (2/2)
2006 consolidated P&L (2/2) in € million 2005 2006 ∆ 06/05 Revenue 2,474 2,625 +6.1% Operating profit 1,068 1,150 +7.7% as % of revenue 43.1% 43.8% Financial expense (400) (406) Income tax expense (232) (265) Effective tax rate 34.6% 35.7% Share losses of associates and minority interest (1) (4) Net

Slide 35: 2006 consolidated financial expenses
2006 consolidated financial expenses in € million 2005 2006 ∆ 06/05 Cost of net financial debt (420) (410) +10 Cost of gross financial debt (435) (431) +4 Financial income from cash investments 15 21 +6 Other financial income/(expenses) 20 4 (16) Capitalized borrowing costs 17 7 (10) Dividend receiv

Slide 36: 2006 consolidated cash flow statement
2006 consolidated cash flow statement in € million 2005 2006 EBITDA* 1,572 1,706 Change in working capital requirement (4) (6) Net interest paid (437) (315) Income taxes (207) (264) Net cash flows from operating activities 924 1,121 New concessions fixed assets (478) (466) Other cash flows related t

Slide 37: 2006 consolidated balance sheet
2006 consolidated balance sheet in € million 2005 2006 ASSETS Non-current intangible assets 11,725 11,661 Other non-current assets 169 159 Trade receivables and other current assets 266 296 Fair value of derivative financial instruments (a) 182 39 Cash and other financial assets (b) 818 700 Total as

Slide 38: Financial policy
Financial policy Main objectives: – Lengthen average debt maturity to match cash flow generation profile – Maintain a financing strategy based on a non-recourse basis – Diversify sources of financing – Limit interest rate exposure by maintaining a conservative hedging policy 38

Slide 39: Financial policy
Financial policy ASF Group (ASF+Escota (ASF+Escota): ASF+Escota): an optimised indebtedness – ASF has no capacity for further extraordinary dividend (no available reserves) – A 100% pay-out policy will be implemented as from 2007 – Commitment to comply with the CNA financial covenants: Net debt / EB

Slide 40: Debt push down
Debt push down* Before debt push down After debt push down* Capital increase: €2.5bn Capital increase: €2.5bn Perpetual bond: €0.5bn Perpetual bond: €0.5bn Treasury drawdown: drawdown: €0.55bn VINCI SA Treasury drawdown: drawdown: €3.1bn VINCI SA Acquisition debt brought back to Acquisition debt: de

Slide 41: ASF Group & ASF Holding indebtedness
ASF Group & ASF Holding indebtedness As at June 30, 2007* (provisional accounts) ASF Group ASF Holding TOTAL in € million (ASF + Escota) Escota) Bonds 1,492 1,492 CNA 7,596 7,596 EIB 253 253 Bank term loan 800 1,186 1,986 Bank revolving facility 654 654 Other loans 16 16 Gross debt 10,811 1,186 11,9

Slide 42: Breakdown of debt after hedging
Breakdown of the ASF Group & ASF Holding debt after hedging As at June 30: – 2007, 95% of ASF Group (ASF+Escota) net financial debt is at fixed or capped or inflation-linked rate – 2/3 of ASF Holding financial debt (€ 1.2bn) are optionally hedged until the end of 2013 – ASF Group + ASF Holding avera

Slide 43: Indebtedness profile
ASF Group & ASF Holding indebtedness profile Repayment schedule - ASF Group & ASF Holding gross financial debt as of June 30, 2007* 3000 2000 1040 40 1000 20 30 1518 35 1 278 25 1074 792 821 695 708 687 768 637 651 332 470 18 18 18 18 18 18 0 2007 * 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

Slide 44: 5. Operational performance
5. Operational performance 44

Slide 45: Growth of EBITDA
Growth of EBITDA total revenue €1,930m 1,930m €2,104m 2,104m €2,239m 2,239m €2,389m 2,389m €2,474m 2,474m €2,625m 2,625m 2009 TARGET 13% 14% 13% 14% 14% 14% 12% 14% 13% 8% 15% 13% 10% 9% % of total 13% 11% 10% revenue 12% 60% 62% 63% 64% 64% 65% ≥ 67% 2001 2002 2003 2004 2005 2006 2009 Ebitda Purcha

Slide 46: Improvement in productivity
Improvement in productivity Average annual workforce 7789 7735 7613 7494 8000 7312 1940 1900 1862 1829 1802 Escota 6000 4000 5849 5835 5751 5665 5510 ASF 2000 0 2002 2003 2004 2005 2006 Millions of km travelled per employee 5 4 4,6 4,2 4,4 3 3,9 4,0 2 2002 2003 2004 2005 2006 46

Slide 47: Pursuing the development of automation
Pursuing the development of automation ASF Group - Toll receipts by payment method 2 systems are available: Automatic terminals (payments with credit 100% cards or coins), including 24 hour-a-day or 90% 37% 34% all-night fully automated toll stations 80% 52% 46% 41% 70% 58% Electronic Toll Collectio

Slide 48: Pursuing the development of automation
Pursuing the development of automation Transparency on the level and schedule of automation Pace of automation determined by retirements and natural turnover of employees – Principle of non compensated departures, unless strictly necessary Commitments: – No layoff or compulsory change of job – Stron

Slide 49: A peaceful social climate
A peaceful social climate 5 internal agreements have been signed with unions on: – Continuous professional training (“formation professionnelle”) – Early-retirement for posted workers – Jobs and competency management (“Gestion Prévisionnelle des Emplois et des Compétences”) – Toll collection organiz

Slide 50: Positive effects of ASF integration within VINCI Concessions
Positive effects of ASF integration within VINCI Concessions General expenses: – Rationalisation of head offices – Shrinkage of the number of districts for Escota (from 6 to 4) Purchasing costs: – ASF benefits from master agreements signed by VINCI with selected suppliers – Scale effect on common pu

Slide 51: Positive effects of ASF integration within VINCI Concessions
Positive effects of ASF integration within VINCI Concessions Business synergies – Cross-divisional changes in top management between ASF and VINCI – Benchmark & best practices on operations – Revenue synergies: Optimised value of optical fibre networks towards communication operators Global manageme

Slide 52: Heavy vehicle discounts - from CAPLIS to TIS
Heavy vehicle discounts - from CAPLIS to TIS Until April 30, 2007: a unique HV subscription system: Caplis May 2007: launch of “TIS PL” (electronic toll collection for HV) in accordance with the “Eurovignette” European Directive which: – Limitation the HV discounts to 13% of revenue – Discount calcu

Slide 53: A strategy focused on the existing concession contracts
A strategy focused on the existing concession contracts ASF Group is exclusively dedicated to running its current concession contracts – ASF Group is now 100% focused on improving its current business growth and profitability ASF Group will develop non-capital intensive service activities only relat

Slide 54: 6. 2007 Outlook
—_—_——_—— 3 qx Auoroutes u Su T 4 : h i) de la France Asubsidiary of WIN Pa 6. 2007 Outlook 54

Slide 55: Revenue – First half 2007
Revenue – First half 2007 Robust figures in the first half of 2007: ASF Escota TOTAL Traffic on stable network +3.5% +2.4% +3.3% New sections +0.1% - +0.1% Effect of increased toll prices +4.3% +3.5% +4.1% Total toll receipts +7.9% +5.9% +7.5% 55

Slide 56: 7. Valuation
=. @ Autoroutes q@ du Sud T 4 ) | de la France Asubsidiary of WENCH Pa 7. Valuation 56

Slide 57: Valuation methodology
Valuation methodology 2 methods: – DCF method with variable wacc – DDM with variable cost of equity 2 scenarios: – Base case scenario: based on the current debt situation, with a wacc calculated on ASF + Escota + ASF Holding consolidated indebtedness – Releveraged scenario: with a wacc calculated on

Slide 58: Valuation: main assumptions
Valuation : main assumptions Assumptions: – For the 2007-2011 period : implications of ASF & Escota Programme Contracts – For the 2012-2032 period : it is supposed there will not be any new Programme Contracts 58

Slide 59: Valuation: main assumptions
Valuation : main assumptions Traffic growth – Constant network (excluding leap year effect): 2007-2011 CAGR: + 2.0% 2012-2026 CAGR: +1.5% 2027-2032 CAGR: +1.0% – Leap year effect: +0.3% Tariffs – Inflation rate: 2% – Tariff growth of existing agreements with the Grantor: As defined by Programme Plan

Slide 60: Valuation: main assumptions
Valuation : main assumptions EBITDA: – 2007-2011 CAGR: c.+ 7.5% – 2012-2026 CAGR: c.+3.5% – 2027-2032 CAGR: c.+2.5% CAPEX – For the 2007-2011 period, CAPEX are defined by ASF & ESCOTA Programme Contracts (cf. slide 19) – For the 2012-2032 period, CAPEX: c. € 5.3bn (in current €) New sections: € 0.7b

Slide 61: Valuation: main assumptions
Valuation : main assumptions Main valuation assumptions: Risk-free rate (15-year OAT) 4.71% Average debt spread : base case scenario 0.83% releverage scenario 0.94% Market risk premium 4.50% Unleveraged beta 0.50 Normative tax rate 34.43% Equivalent to Base case Releverage scenario scenario a DCF va

Slide 62: Conclusion
=. @ Autoroutes q@ du Sud T 4 ) | de la France Asubsidiary of WENCH Pa Conclusion

Slide 63: Conclusion
Conclusion LARGEST AND MOST DIVERSIFIED MOTORWAY NETWORK IN FRANCE: # 2 TOLL TOLL-ROAD OPERATOR IN EUROPE UNIQUE & STRATEGIC GEOGRAPHICAL POSITION MATURE AND ALMOST COMPLETED NETWORK LOW CONSTRUCTION RISK HIGH, RECURRENT AND GROWING CASH FLOWS WITHIN LONG- LONG-TERM CONCESSION CONTRACTS PROTECTIVE C

Slide 64: Autoroutes du Sud de la France Analyst day
Autoroutes du Sud de la France Analyst day July 2007

Slide 65: Appendices
=. @ Autoroutes q@ du Sud T 4 ) | de la France Asubsidiary of WENCH Pa Appendices

Slide 66: ASF: the major French toll-road operator
ASF: the major French toll- toll-road operator Network conceded km ASF 2,695 Escota 459 Puymorens tunnel 6 Total ASF network 3,160 Cofiroute 1,101 Arcour (A19)** 101 SMTPC 3 Total VINCI network 4,365 APRR 1,895 AREA 384 Total APRR 2,279 Viaduc de Millau 3 SANEF 1,393 SAPN 379 Total SANEF 1,772 A’lie

Slide 67: French toll roads operators: 2006 key figures
French toll roads operators: 2006 key figures Network conceded Km travelled Revenue EBITDA EBITDA (km) (millions of km) (€m) (€m) Margin ASF Group 3,160 33,467 2,625 1,706 65% Cofiroute 1,101 9,895 954 659 69% APRR Group 2,279 20,247 1,670 1,068 64% SANEF Group 1,772 11,589 1,241 779 63% Source: fig

Slide 68: Average daily traffic per main section
Average daily traffic per main section 2006 figures Vehicles / day 68

Slide 69: Traffic growth per main section
Traffic growth per main section 2005/06 growth 69

Slide 70: Established track record of steady traffic growth
Established track record of steady traffic growth ASF + Escota Other French Networks 160 CAGR: +4.5% Km t r avelled (base 100 in 1995) 150 140 CAGR: +3,1% 130 120 110 100 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 Source: AFSA (French Association of Motorway Concessionaires) Including ne

Slide 71: High resilience of traffic to economic context and fuel price increases
High resilience of traffic to economic context and fuel price increases 300 250 100 basis in 1990 200 150 100 50 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 ASF+Escota traffic French GDP (volume) Fuel price (Brent) 71

Slide 72: History: milestones
History: milestones ASF was founded in 1957 by the French State In 1984, ASF bought ACOBA (network in Basque country) At the end of 1994, ASF acquired Escota (network in South East of France) founded in 1956 In 1994, ASF signed the concession agreement for the operation and maintenance of the Tunnel

Slide 73: ASF acquisition and refinancing: key dates
ASF acquisition and refinancing: key dates Date Acquisition Date Financing/refinancing 07/11/05 VINCI submitted firm offer to purchase French government's 05/11/05 Signature of 7-year acquisition loan for €4.2 billion and holding in ASF 20-month bridge to equity loan for €2.3 billion 14/12/05 Govern

Slide 74: 2006 revenue - details
2006 revenue - details 2005 2006 Group ASF Escota Group Revenue – tolls 2,427 2,036 536 2,572 Fees for use of commercial premises 31 34 5 39 Fees for use of fibre optics and telecommunication facilities 16 12 2 14 Revenue 2,474 2,082 543 2,625 74

Slide 75: 2006 Taxes and levies
2006 Taxes and levies (excluding corporate income taxes) in € millions 2005 2006 Dues paid to government estate authorities 58 60 Infrastructure tax (TAT Taxe d’aménagement du territoire) 209 215 Business entity tax 80 83 Other local taxes 3 2 Taxes on wages and salaries 3 5 Other taxes and levies 6

Slide 76: Definitions
Definitions ICAS: Investissement Complémentaire sur IEAS: Investissement d’Exploitation sur Autoroutes en Service (complementary Autoroutes en Service (operating investment investment in existing motorways) in existing motorways) – Examples: – Examples: Road widening Operations equipment (toll equip

Slide 77: 2006 Capital expenditures
2006 Capital expenditures 2005 2006 Type of investment Group ASF Escota Group Construction of new sections 235.9 163.9 2.7 166.6 Supplementary investments on 186.2 98.9 109.5 208.4 motorways in service (« ICAS ») Operating assets (« IEAS ») 54.2 34.8 20.9 55.7 Capitalised production costs 20.9 16.8

Slide 78: First bond issue – EMTN Programme
First bond issue – EMTN Programme Details: – € 1.5bn over 15 years (July 2007 => July 2022) – Baa1/Stable (Moody’s), BBB+/Negative outlook (S&P) – Credit spread: 66 bp – Nominal rate: 5.625%, price: 99.702% – 2.5x over-subscripted (€3.7 bn) 78

Slide 79: Autoroutes du Sud de la France Analyst day
Autoroutes du Sud de la France Analyst day July 2007
Source: Internet Archive copy of vinci.com
More decks from Vinci SA
H1 2026 Earnings Presentation84 slides · Jul 30, 2026
ESG Presentation (March 2026)68 slides · March 2026
FY 2025 Earnings Presentation96 slides · Feb 6, 2026
9M 2025 Earnings Presentation105 slides · Oct 23, 2025
H1 2025 Earnings Presentation106 slides · Jul 31, 2025
FY2024 Earnings Presentation116 slides · Feb 7, 2025