Vale S.a. · BMFBOVESPA:VALE3

Vale — Corporate Update (November 2015)

62 slides from Vale's corporate update, November 2015

  1. Slide 1: Update on the S11D project

    Update on the S11D project Analyst Tour Pará, November 2015

  2. Slide 2: Disclaimer

    isclaime “This presentation may include forward-looking statements, including statements that present Vale's plans, strategies and expectations about future events or results. These forward-looking statements, involve various risks and uncertainties. Vale cannot guarantee that such statements will p

  3. Slide 3: Agenda

    genda 1. Project Overview 2. Project Status 3. Preparation for Operations

  4. Slide 4: Project Overview

    Project Overview

  5. Slide 5: The opening of the South Range is a landmark in Vale's history

    5 The opening of the South Range is a landmark in Vale’s history • South Range has an extension North Range of 120 km and an area of 48,000 ha • S11D has an extension of 9.5 km and an area of 1,400 ha • S11D will have a mine life of 30 years at 90 Mtpy • S11D has a strip ratio of 0.38 Carajás Nation

  6. Slide 6: The South Range contributes significantly to Vale's Northern System reserves

    6 The South Range contributes significantly to Vale’s Northern System reserves Billion Metric Tons Fe Content, % 66.7 66.7 65.4 306 2.535 7.081 4.240 South Range (S11) North Range East Range Total Source: 20F, 2014

  7. Slide 7: The S11D project encompasses a new Mine, Railway and Port

    7 The S11D project encompasses the development of a new Mine and Railway and Port structures Mine and Plant Railway Port  Mine capacity of 90 Mtpy  Construction of 101 km  Construction of a new with a truckless mining railway spur, linking the onshore infrastructure, system S11D ore body to the m

  8. Slide 8: The S11D project is expected to be delivered on time and below the original budget

    8 The S11D project is expected to be delivered on time and below the original budget US$ billion Logistics Mine and Plant Mine, Plant and Logistics 19.7 90% of future expenditure in S11D is BRL 14.4 9.4 denominated 11.6 7.9 2.6 8.1 6.5 1.6 0.6 0.2 Original Total Cumulative 2016 2017 2018 2019 Budget

  9. Slide 9: Project Status

    9 Project Status

  10. Slide 10: The S11D project is progressing according to plan

    10 The S11D project is progressing according to plan As of September 2015 Mine and Plant Railway Port  Physical Progress of  Physical Progress:  Physical Progress: 75% - Railway spur 72% - Onshore 66% - Railway duplication 34% - Offshore 64% with 6 segments and 7 semi-segments out of 48 segments

  11. Slide 11: The S11D project is progressing according to plan

    11 The S11D project is progressing according to plan As of September 2015 Mine and Plant Railway Port  Physical Progress of  Physical Progress :  Physical Progress: 75% - Railway spur 72% - Onshore 66% - Railway duplication 34% - Offshore 64% with 6 segments and 7 semi-segments out of 48 segments

  12. Slide 12: Mine and Plant Highlights

    12 Mine and Plant Highlights • Plant equipment with 36 screens, 18 cone crushers, 7 stackers and 7 reclaimers, 2 train load-out terminals. Additional Capacity of 90 • Three buffer stockyards with 1 Mt of capacity and four product stockyards with 3.4 Mt of Mt with truckless capacity mining system and

  13. Slide 13: The S11D mine will apply a truckless mining system

    13 The S11D mine will apply a truckless mining system Portable Modular Conveyor Mobile Sizing Rig

  14. Slide 14: Dry screening process avoids the need for tailing dams

    14 The project will apply a dry screening process and avoid the need for tailing dams Screening Process Process Highlights • High grade ore avoiding washing and concentration processes • Highly homogeneous ore body enabling the dry processing of the ore • 18,000 MWh of electricity saved every year (

  15. Slide 15: Significant progress at the S11D Mine and Plant

    15 Significant progress has been achieved at the S11D Mine and Plant Mine and Plant Status • Physical progress of 75% in September • Civil works on the main substation on the mine concluded • 74% of overall civil works concluded • 100% of the 109 modules positioned at site • 91% of earthworks conclu

  16. Slide 16: Overview of the Mine and Plant area

    16 Overview of the Mine and Plant area Mine

  17. Slide 17: Mine overview

    17 Mine overview S2 S3 S4 S1 Aug-11-2015

  18. Slide 18: Mine – East Sector

    18 Mine – East Sector S4 West Wing TS01 East Wing S3 Oct-25-2015

  19. Slide 19: Mining System

    19 Mining System 3 S4 S3 Oct-28-2015

  20. Slide 20: Mine Conveyor Systems

    20 Mine Conveyor Systems Mine Substation TS01 West Wing East Wing Mine Buffer Stockpile Mine Construction Site TS02 Aug-11-2015

  21. Slide 21: Transfer Station 1

    21 Transfer Station 1 Mine Buffer Stockpile Mine Substation East Wing West Wing TS01 Oct-25-2015 Oct-25-2015 04-jun-2015

  22. Slide 22: Main Mine Substation (230kV)

    22 Main Mine Substation (230kV) Oct-25-2015

  23. Slide 23: Mine – Buffer Stockpile and Long Distance Belt Conveyor

    23 Mine – Buffer Stockpile and Long Distance Belt Conveyor TS01 Mine Buffer Stockpile TS02 Oct-25-2015

  24. Slide 24: Mine Buffer Stockpile

    24 Mine Buffer Stockpile Out-25-2015

  25. Slide 25: Overview of Mine and Plant area

    25 Overview of Mine and Plant area Long Distance Belt Conveyor

  26. Slide 26: LDBC (Long Distance Belt Conveyor)

    26 LDBC (Long Distance Belt Conveyor) TS06 LDBC Access 2B Access 7 TS02 Aug-11-2015

  27. Slide 27: LDBC (Long Distance Belt Conveyor)

    27 LDBC (Long Distance Belt Conveyor) LDBC Access 7 Access 2 Aug-11-2015

  28. Slide 28: LDBC (Long Distance Belt Conveyor)

    28 LDBC (Long Distance Belt Conveyor) TS07 Oct-25-2015

  29. Slide 29: LDBC (Long Distance Belt Conveyor)

    29 LDBC (Long Distance Belt Conveyor) BC09 Oct-25-2015

  30. Slide 30: Overview of Mine and Plant area: Plant

    30 Overview of Mine and Plant area Plant

  31. Slide 31: Secondary and Tertiary Crushing Plants

    31 Secondary and Tertiary Crushing Plants BC10 TS08 Oct-25-2015 Oct-25-2015

  32. Slide 32: Plant Overview

    32 Plant Overview Buffer Product Stockyard Stockyard Secondary Tertiary Crushing Crushing Plant Plant Loading Line Secondary Screening Plant Oct-25-2015

  33. Slide 33: Secondary Crushing Plant

    33 Secondary Crushing Plant Oct-25-2015

  34. Slide 34: Secondary Screening Plant

    34 Secondary Screening Plant Oct-25-2015

  35. Slide 35: Loading Line

    35 Loading Line Railway Loop Train Loading System Oct-25-2015

  36. Slide 36: The S11D project is progressing according to plan

    36 The S11D project is progressing according to plan As of September 2016 Mine and Plant Railway Port  Physical Progress of 75%  Physical Progress:  Physical Progress: - Railway spur 72% - Onshore 66% - Railway duplication 34% - Offshore 64% with 6 segments and 7 semi-segments out of 48 segments

  37. Slide 37: Railway Highlights

    37 Railway Highlights • Duplication of the railway (EEFC): − 48 railway sections (570 km) Implementation duplicated of the logistics of − 55 railway sections (220 km) the Northern remodeled System to • Construction of a railway spur: transport 230 − 101 km of railway Mtpy by 2H17 − 4 bridges − 4 tun

  38. Slide 38: Railway segments being duplicated and spur being built

    38 48 segments of the railway are being duplicated and a greenfield railway spur is being built Railway Spur – Assembly of 1st AMV Status • Construction of the railway spur: ‒ 72% of physical progress ‒ 89% of earthworks completed ‒ Civil works in 3 of 4 tunnels completed ‒ 88% of physical progress

  39. Slide 39: Railway Spur – Tunnel 1 North

    39 Railway Spur – Tunnel 1 North 06-jan-2015 05-mar-2015 11-ago-2015 Oct-01-2015 09-out-2014

  40. Slide 40: Railway Spur – Bridge over the Parauapebas river

    40 Railway Spur – Bridge over the Parauapebas river 06-jan-2015 05-mar-2015 Oct-25-2015 11-ago-2015 09-out-2014

  41. Slide 41: Railway Spur – Bridge over the Verde river

    41 Railway Spur – Bridge over the Verde river Oct-27-2015

  42. Slide 42: Railway – Bridge over the Pindaré river

    42 Railway – Bridge over the Pindaré river Oct-26-2015

  43. Slide 43: Railway Duplication – Bridge over the Cajuapara river

    43 Railway Duplication – Bridge over the Cajuapara river Oct-01-2015 09-out-2014

  44. Slide 44: Railway Duplication – Segment 15-16

    44 Railway Duplication – Segment 15-16 Oct-26-2015

  45. Slide 45: Railway Duplication – Segment 15-16

    45 Railway Duplication – Segment 15-16 Oct-01-2015

  46. Slide 46: Railway Duplication – Segment 48-49

    46 Railway Duplication – Segment 48-49 Oct-21-2015

  47. Slide 47: Overpass – Km 88

    47 Overpass – Km 88 Oct-06-2015

  48. Slide 48: The S11D project is progressing according to plan

    48 The S11D project is progressing according to plan As of September 2015 Mine and Plant Railway Port  Physical Progress of 75%  Physical Progress:  Physical Progress:  Railway spur 72% - Onshore 66%  Railway duplication 34% with - Offshore 64% 6 segments and 7 semi- segments of 48 segments del

  49. Slide 49: Additional onshore and offshore infrastructure

    49 The project scope entails additional onshore and offshore infrastructure • Onshore: − 4 stockyards (600,000 t each) − 2 car dumpers (8,000 t/h) − 1 stacker (16,000 t/h) − 2 reclaimers (8,000 t/h) Increase in the − 2 stackers/reclaimers (8,000 t/h) Northern System • Ponta da Madeira Rail Terminal

  50. Slide 50: The port expansion is also progressing according to plan

    50 The port expansion is also progressing according to plan Port Onshore Status • Port onshore: - 66% of physical progress - Civil works ongoing - Assembly of equipment ongoing • Port offshore: - 64% of physical progress - 89% of the foundations completed Port Offshore - 59% of physical progress at

  51. Slide 51: Railway Duplication – Maintenance inspection terminal

    51 Railway Duplication – Maintenance inspection terminal Substation Administrative Exit LIne Building Main Shed Parking Lot and Bus Stops Water Towers Entry Line Sandpit 05-oct-2015

  52. Slide 52: Railway Duplication – Wheelset Change and Wheel Maintenance Centers

    52 Railway Duplication – Wheelset Change (CTR) and Wheel Maintenance Centers (CMR) CMR Main Shed CTR Main Shed Substation Dressing Entry Lines Room and Nursery Admin Building Oct-05-2015

  53. Slide 53: Onshore – Civil Engineering Work on Stockyards O and T

    53 Onshore – Civil Engineering Work on Stockyards O and T O P Stockyard O – East and P Stockyard T – West Oct-07-2015 Oct-23-2015 Stockyard O – West and P Oct-23-2015 Stockyard T – East Oct-07-2015

  54. Slide 54: Onshore – Assembly of Car Dumpers and Reclaimers

    54 Onshore – Assembly of Car Dumpers and Reclaimers Oct-23-2015 Oct-23-2015 Stacker – 05 Reclaimer – 06 Car Dumpers – 07 and 08 Oct-26-2015 General View – Car Dumpers Oct-07-2015

  55. Slide 55: Onshore – Assembly of Belt Conveyors Lines

    55 Onshore – Assembly of Belt Conveyors Lines (TR) Oct-07-2015 Oct-23-2015 TR 311K-13 CT-311K-202 and TR-313k- TR-311K-13 and CT-311K-202 82 Oct-26-2015 Oct-23-2015 TR-313K-82 and CT-311K-202 TR 313K-211

  56. Slide 56: Off shore – Pier 4 North Berth Construction

    56 Off shore – Pier 4 North Berth Construction Auxiliary platform Dolphin D10 Pavement A Dolphin D12 Dolphin D13 Track SL4 Oct-30-2015

  57. Slide 57: Preparation for Operations

    57 Preparation for Operations

  58. Slide 58: Personnel required for start-up already mobilized and being trained

    58 Personnel required for start-up already mobilized and being trained • The S11D project is tracking according to plan and expected to meet the following key milestones still in 2016: − Start-up of the Mine and Plant − Start-up of the Railway Spur − Gradual upgrade of the Estrada de Ferro Carajás (

  59. Slide 59: Personnel required for start-up of Mine and Plant mobilized and trained

    59 Personnel required for start-up of Mine and Plant already mobilized and being trained Pre-Operational Training • More than 800 people already mobilized out of a total of 2,000 • Training programs in partnership with SENAI and other mining companies

  60. Slide 60: The logistics teams are also being trained

    60 The logistics teams are also being trained Pre-Operational Training • 300 trainees already trained out of a total of approximately 500 trainees • Over 200 hours of specific and practical training per person

  61. Slide 61: S11D is already benefiting local communities

    61 S11D is already benefiting local communities Canaã dos Carajás Court House Multisport Complex Investments • 132 projects approved • 104 ongoing with more than 330 thousand people benefited in projects such as:  The Court house in Canaã dos Construction of schools Carajás in partnership with the

  62. Slide 62: For a world with new values.

    W va For a world with new values. 62