    Disclaimer Statement This Presentation contains certain statements that are, or may be deemed to be, “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. All statements other than

  3. Slide 3: Recent Developments and Key Highlights: Commissioning and Start-Up Timeline

    Phase Recent1 Developments Expected Commissioning and Start-Up Timeline and Key Highlights 4Q 2026 Expected first gas into the Rio Grande LNG Facility 2Q 2027 Expected first LNG production from Train 1 3Q 2027 Expected Substantial Completion of Train 1, one quarter ahead of guaranteed schedule ~1 Qu

  4. Slide 4: Recent Developments: Unsold Production Volumes Provide Market Exposure

    Projected Unsold Production Recent Developments and KeyVolumes Provide Valuable Market Exposure Highlights TTF Calendar Pricing 2027-2030 >$6/MMBtu Volume-weighted average implied $/MMBtu October 2025 v. October 2026 market margins during ramp-up $27.50 period (~2027–2Q 2031) $22.50 October 2025 Oct

  5. Slide 5: Construction Continues Safely, on Budget, and Ahead of Schedule

    Construction Continues Safely, on Budget, and Ahead of Schedule Progressing toward expected Train 1 LNG production in 2Q 2027 and Substantial Completion in 3Q 2027 Recent Construction Highlights Construction Progress as of September 2026 Liquefaction Trains 79.7% • Train 1 electrical, mechanical, an

  6. Slide 6: Meaningful Regulatory Progress During 3Q 2026

    Meaningful Regulatory Progress During 3Q 2026 Trains 1-5 • FERC approved uprate for Trains 1 through 5, increasing authorized liquefaction capacity to 30.15 MTPA, in line with expected production Train 6 • FERC released schedule of environmental review for Train 6 in July 2026, final Environmental I

  7. Slide 7: Continuing to Execute Project-Level Balance Sheet Strategy

    Continuing to Execute Project-Level Balance Sheet Strategy • Strong progress on project-level balance sheet strategy of terming out bank facilities via debt capital markets transactions • Robust demand and attractive pricing across transactions • Over 60% of initial capacity under Phase 1 bank facil

  8. Slide 8: NextDecade Level Debt Target Update

    NextDecade Level Debt Target Update • NextDecade level debt target ~$2.0–$2.25B NextDecade Consolidated Financial Statements at beginning of five-train steady state operations based on base case guidance NextDecade NextDecade Corporation level debt • Unchanged target leverage supported by cash flows

  9. Slide 9: NextDecade Investment Highlights

    NextDecade Investment Highlights 8

  10. Slide 10: Providing the World Access to Lower-Carbon Energy

    Providing the World Access to Lower-Carbon Energy Maximizing shareholder value by safely and efficiently delivering lower-carbon energy through LNG infrastructure Rio Grande LNG Facility NextDecade is developing and constructing the Rio Grande LNG Facility, a natural gas liquefaction and export faci

  11. Slide 11: NextDecade Key Investor Highlights

    NextDecade Key Investor Highlights 1 Strong Asset Development Platform at Rio Grande LNG Site 2 Valuable Relationships with High-Quality Counterparties Across the Value Chain 3 Growth Momentum Supported by Robust Market Fundamentals 4 Strong Commitment to Sustainability and Social Responsibility 10

  12. Slide 12: Strong Organic Growth Platform at Site

    NextDecade Key Investor Highlights Construction of Trains 1-5 progressing safely and on budget, Phase 1 tracking ahead of guaranteed schedule 1 First LNG from Train 1 expected 2Q 2027, Trains 1-3 each expected to achieve Substantial Completion approximately one quarter ahead of guaranteed schedule S

  13. Slide 13: Valuable Relationships with High-Quality Counterparties

    NextDecade Key Investor Highlights EPC partner has unmatched track record of liquefaction project deliverability on time and on budget 2 Commercial offtake agreements (LNG SPAs) with creditworthy, leading players in the global LNG market​ Valuable Relationships with Project design utilizes establish

  14. Slide 14: Growth Momentum Supported by Robust Market Fundamentals

    NextDecade Key Investor Highlights Demand for incremental LNG expected to continue to grow in coming years due to strong global growth in total gas demand, combined with constraints in natural gas and LNG 3 production and transportation in various parts of the world Since Iran conflict began Februar

  15. Slide 15: Strong Commitment to Sustainability and Social Responsibility

    NextDecade Key Investor Highlights NextDecade seeks to deliver secure, affordable, and cleaner energy through the safe and efficient development and operation of liquefaction capacity at Rio Grande LNG 4 LNG displaces coal and other solid fuels in developing Strong Commitment countries, providing en

  16. Slide 16: 2026 Priorities

    2026 Priorities 15

  17. Slide 17: Progress on Key 2026 Priorities

    Progress on Key 2026 Priorities NextDecade 2026 Priorities Year-to-Date Progress  Phase 1 continues to progress ahead of guaranteed Progress construction of Trains 1-5 safely, on schedule, within budget, and safely budget, and ahead of schedule  Commissioning activities for Train 1 and across site

  18. Slide 18: LNG Market Dynamics

    LNG Market Dynamics 17

  19. Slide 19: Robust Global Gas Demand Growth Calls for Incremental LNG Supply

    Robust Global Gas Demand Growth Calls for Incremental LNG Supply bcm 6,000 • Expect growth in global gas demand to LNG Pipeline Gas remain strong into 2030s and beyond 5,000 - Economic growth and electrification driving demand in developing countries 4,000 - Increased focus on energy security across

  20. Slide 20: Middle East Conflict Has Dramatically Altered “Third Wave” Dynamic

    Middle East Conflict Has Dramatically Altered “Third Wave” Dynamic Uncertain timing of return of existing Middle East LNG supply and delays to expansion projects have removed material amounts of LNG supply from the global market through 2030+ (MTPA) Historical and Projected LNG Supply Prior to Middl

  21. Slide 21: Recent Events Underscore Attractiveness of Long-Term U.S. LNG Supplies

    Recent Events Underscore Attractiveness of Long-Term U.S. LNG Supplies Short-Term LNG Market Price vs. Estimated U.S. LNG SPA Delivered Price to Asia1 2021 – Present Stable Henry-Hub linked $30 pricing serves as buffer Average Average against market price shocks 2021-Present 2023-Present and tight m

  22. Slide 22: Low Storage Levels and Elevated Prices Leave Europe’s Gas Market Exposed

    Low Storage Levels and Elevated Prices Leave Europe’s Gas Market Exposed TTF and Henry Hub Calendar Pricing 2027-2030 Europe natural gas storage (% full) 100% $/MMBtu 90% $30 80% $25 TTF 70% Henry Hub 60% $20 50% $15 40% $10 30% 20% $5 10% 2026 2022 2021 5-year average 5-year range $- 0% 2027 2028 2

  23. Slide 23: Rio Grande LNG Facility

    Rio Grande LNG Facility 22

  24. Slide 24: Site in Great Location for Liquefaction Development

    Rio Grande LNG Site in Great Location for Liquefaction Development Access to uncongested port Strong geotechnical conditions and waterway requiring less piling Area historically subject to Proximity to prolific natural fewer named storms than gas resources in Permian and other areas of U.S. Gulf Coa

  25. Slide 25: Developing and Advancing Trains 6-8 on the Path to Doubling Capacity

    Developing and Advancing Trains 6-8 on the Path to Doubling Capacity Train 6 • Submitted formal FERC application for Train 6 and a third berth in 2Q 2026 • FERC issued schedule of environmental review in July, final Environmental Impact Statement expected in June 2027 • Progressing discussions with

  26. Slide 26: Potential to Be One of World’s Largest LNG Production and Export Sites

    Potential to Be One of World’s Largest LNG Production and Export Sites MTPA 12 MTPA 60 MTPA 60 50 18 MTPA 40 30 MTPA 30 ~48 MTPA 20 currently under construction or 10 in development 0 Trains 1-5 under Trains 6-8 in Potential incremental LNG Total potential LNG construction development production cap

  27. Slide 27: Trains 1–5 Facility Site Plan

    Trains 1–5 Rio Grande LNG Facility Site Plan World class ~1,000-acre site in south Texas with 15,000 feet of frontage on the Brownsville Ship Channel, advantaged by proximity to abundant Permian and Eagle Ford gas resources and uncongested port Texas State Pipeline Highway 48 interconnects Material

  28. Slide 28: Valuable Relationships with High-Quality Counterparties Across Value Chain

    Valuable Relationships with High-Quality Counterparties Across Value Chain LNG Customers Equity Partners Technology EPC Pipeline 27

  29. Slide 29: Partnering with Preeminent Global LNG EPC Contractor Bechtel

    Partnering with Preeminent Global LNG EPC Contractor Bechtel Construction of the Rio Grande LNG Facility is de-risked by Bechtel’s track record of successful LNG completions and by fully-wrapped, lump-sum, turnkey EPC contracts Project Scope Trains 1-5 • 5 liquefaction trains with expected productio

  30. Slide 30: Facility Construction Schedule

    Rio Grande LNG Facility PhaseGuaranteed Construction 1 Construction Schedule Progress Update 2023 2024 2025 2026 2027 2028 2029 2030 2031 Train 1 3Q 2027 4Q 2027 Train 2 2Q 2028 3Q 2028 Train 3 4Q 2028 1Q 2029 Train 4 3Q 2030 Train 5 2Q 2031 Guaranteed Construction Timeline Guaranteed Substantial Co

  31. Slide 31: Phase 1 Construction Progress Update: Trains 1-3

    Rio Grande LNG Facility PhaseConstruction 1 Construction Progress Progress Update Train 1, September 2026 Train 2, September 2026 Train 3, September 2026 30

  32. Slide 32: Construction Progress Update: Trains 4 and 5

    Rio Grande LNG Facility PhaseConstruction 1 Construction Progress Progress Update Train 4, September 2026 Train 5, September 2026 31

  33. Slide 33: Feed Gas Sourcing and Transportation Strategy

    Rio Grande LNG Facility Feed Gas Sourcing and Transportation Strategy Executing a diversified gas sourcing and transportation strategy to capitalize on proximity to sources that are expected to produce significant quantities of low-cost natural gas for decades • Diversified sourcing across suppliers

  34. Slide 34: Long-Term LNG Sale and Purchase Agreements Overview

    Long-Term LNG Sale and Purchase Agreements Overview Phase 1 Train 4 Train 5 Counterparties 93% FOB SPA Type 100% FOB 100% FOB 7% DES Average Term 19.2 years 20 years 20 years 91% HH Index 100% HH 100% HH 9% Brent SPA volume (MTPA)1 16.2 4.6 4.5 % Capacity Contracted ~90%2 ~77% ~75% ~85% of five-trai

  35. Slide 35: ~$32 billion of Fully Funded Liquefaction Infrastructure

    Rio Grande LNG Trains 1-5 Funding Summary • Financed ~66% debt / ~34% equity at FID Phase 1 • $6.2 billion total equity commitments1 from NextDecade, Global Infrastructure Partners (GIP), GIC, $18.0 billion Mubadala, and TotalEnergies estimated total • $1.0 billion equity from RGLNG HoldCo Borrower2

  36. Slide 36: Facility Equity Partners

    Rio Grande LNG Facility Equity Partners Financial Investors Total Commitments $2.7 Billion Total Commitments $7.5 Billion Total Commitments $1.3 Billion • Phase 1 • Phase 1 • Phase 1 - ~$0.3 billion commitment completed - ~$4.8 billion total commitments - ~$1.0 billion commitment - Up to 20.8% econo

  37. Slide 37: Train 4 and 5 Equity Commitments Fully Funded

    NextDecade’s Train 4 and 5 Equity Commitments Fully Funded with No Material Impact to Equity Train 4 and 5 equity funding commitments of ~$2.4 billion fully funded utilizing approach with lowest estimated cost of capital and highest impact to cash flow per share ~$0.2 Billion Cash • Cash committed f

  38. Slide 38: Capital Structure and Financial Guidance

    Capital Structure and Financial Guidance 37

  39. Slide 39: NextDecade Summary Capital Structure

    NextDecade Summary Capital Structure NextDecade NextDecade consolidated NextDecade Corporation level debt financial (NASDAQ: NEXT) statements NextDecade LNG, LLC $175 million1 13.50% senior secured loans due 2030 $100 million1 8.00% senior secured exchangeable Rio Grande LNG Super loans due 2030 Hol

  40. Slide 40: Guidance for Ramp-Up Period from Train 1 Start-Up to Train 5 Completion

    Guidance for Ramp-Up Period from Train 1 Start-Up to Train 5 Completion Robust cash flow projected across range of market margins TBtu 5,000 Projected LNG Production Volumes for Ramp-Up Period Projected NextDecade Share of Rio TBtu Train 1 Start-Up to Train 5 DFCD1 (~2027 – 2Q 2031) Grande LNG Proje

  41. Slide 41: Steady State Annual Financial Guidance Pricing Sensitivities

    Steady State Annual Financial Guidance Pricing Sensitivities Robust cash flow projected across range of market margins Projected NextDecade Annual Steady State Distributable Cash Flow Additional Pricing Sensitivity Reaffirm Existing Guidance (Assumes ~2 MTPA additional SPAs and maximization of proje

  42. Slide 42: NextDecade Capital Priorities

    NextDecade Capital Priorities 1. Protect safe and reliable operations by maintaining high-integrity assets 2. Continue to opportunistically access the debt capital markets to term out Rio Grande LNG project-level debt while maintaining investment grade credit metrics 3. Refinance FinCo and Super Fin

  43. Slide 43: Empowering the Rio Grande Valley Community

    Empowering the Rio Grande Valley Community 42

  44. Slide 44: NextDecade is Committed to the Rio Grande Valley Community

    NextDecade is Committed to the Rio Grande Valley Community Fostering a long-lasting partnership with local stakeholders to create value, provide opportunities, and contribute to a thriving community for all • Continuous engagement with local stakeholders to: - Obtain a greater understanding of commu

  45. Slide 45: NextDecade is Committed to the Rio Grande Valley Community

    NextDecade is Committed to the Rio Grande Valley Community Fostering a long-lasting partnership with local stakeholders to create value, provide opportunities, and contribute to a thriving community for all • NextDecade’s community engagement is founded on four core values: “The Rio Grande LNG proje

  46. Slide 46: Appendix

    Appendix 45

  47. Slide 47: Key Assumptions and Details

    Key Assumptions and Details Steady state period refers to the period beginning when respective trains have been completed and placed in operation and deliveries under each train’s LNG SPAs have commenced. Projected guidance assumes SPA contract price for all contracted volumes and a $3.00/MMBtu or $

  48. Slide 48: Non-GAAP Measures

    Non-GAAP Measures Rio Grande LNG Project-Level Adjusted EBITDA, Rio Grande LNG Project-Level Distributable Cash Flow, NextDecade Share of Rio Grande LNG Project-Level Distributable Cash Flow, and NextDecade Distributable Cash Flow are non-GAAP financial measures that we use to assess operating perfo

  49. Slide 49: Delivering energy for what’s NEXT

    Investor Relations Contacts: Megan Light John Montano Vice President, Investor Relations Senior Analyst, Investor Relations [email protected] [email protected] 832-981-6583 832-397-6140 Delivering energy for what’s NEXT www.next-decade.com

NextDecade — Investor Presentation (October 2026) on 6ix