Slide 1: 2013 Analyst Conference: Investing Today for a Brighter Tomorrow
2013 Analyst Conference Investing Today for a Brighter Tomorrow March 14, 2013 New York, NY
Slide 2: Safe Harbor Statement/Regulation G Information
Safe Harbor Statement/Regulation G Information Some of the statements contained in today’s presentation with respect to Pepco Holdings, Pepco, Delmarva Power and Atlantic City Electric, including each of their respective subsidiaries, are forward-looking statements within the meaning of the U.S. fed
Slide 3: Investing Today for a Brighter Tomorrow
Investing Today for a Brighter Tomorrow Joe Rigby, Chairman, President & Chief Executive Officer
Slide 4: PHI Overview
PHI Overview Power Delivery Invest in T&D infrastructure Achieve operational excellence, focused on reliability and meeting customer expectations Implement Smart Grid Achieve reasonable regulatory outcomes Pepco Energy Services Maintain profitable business while preserving potential upside as energy
Slide 5: Achievements Since Our Last Meeting
Achievements Since Our Last Meeting Significant improvement in reliability and customer satisfaction Strong restoration performance grades across all service territories after Hurricane Sandy Expanded constructive dialogue with regulators and legislators Solid 2012 financial performance anaged sever
Slide 6: We Are Managing Today's Challenges
We Are Managing Today’s Challenges Reducing Regulatory Lag File and complete rate cases in each jurisdiction Pursue alternative ratemaking mechanisms/approaches Continue outreach to key stakeholders on critical issues Pursue resolution of consolidated tax adjustment issue through generic proceeding
Slide 7: 2013 – Our Priorities Are Clear
2013 – Our Priorities Are Clear Operational/Customer Execute the construction and maintenance plan Complete the deployment of the Smart Grid Make significant progress on new Customer Information System Meet our customers’ expectations Financial Increase rate base Execute the regulatory plan Maintain
Slide 8: Strong T&D Infrastructure Growth
Strong T&D Infrastructure Growth (Billions of Dollars) $14 $12 $10 $8 $6 $4 $2 $- $6.3 ($3.1) 18% 23% 82% $9.7 77% 25% $6.5 24% 75% 76% 2012 Rate Base Estimate Plant Placed In Service Depreciation / Other 2017 Rate Base Projection Transmission Distribution Rate base expected to increase ~ 50% by 201
Slide 9: PHI Value Proposition – Poised for Above Average Total Return
PHI Value Proposition – Poised for Above Average Total Return Key Earnings Drivers Rate base growth - 8% CAGR in rate base through 2017 Regulatory lag reduction Manageable financing requirements Above Average Total Return Attractive Dividend Current yield is 18% higher than the average yield for S&P
Slide 10: Investing Today for a Brighter Tomorrow
Investing Today for a Brighter Tomorrow Joe Rigby, Chairman, President & Chief Executive Officer
Slide 11: Power Delivery Overview
Power Delivery Overview Dave Velazquez, Executive Vice President, Power Delivery
Slide 12: Business Overview – Power Delivery
Business Overview – Power Delivery Electric 793,000 26,006 N/A 640 square miles - District of Columbia, major portions of Prince George’s and Montgomery Counties in Maryland 2.2 Million Electric 503,000 12,641 N/A 5,000 square miles - Delmarva Peninsula 275 square miles - Northern Delaware 1.4 Milli
Slide 13: 2012 Highlights
2012 Highlights Continued executing our reliability enhancement plans in Pepco, Atlantic City Electric and Delmarva Power Completed approximately $1.2 billion in transmission and distribution infrastructure projects Realized 24% reduction in the number of outages and 26% reduction in the average dur
Slide 14: Customer Satisfaction Improvements
Customer Satisfaction Improvements PHI uses an independent firm (Market Strategies, Inc.) to survey its customers on a quarterly basis. Overall satisfaction has increased at all 3 utilities since 2011. PHI’s customer satisfaction score has increased 9 percentage points since fall 2011. Of the key dr
Slide 15: 2012 Reliability Improvements
2012 Reliability Improvements(1)(2) 2011 SAIFI(3) 2012 SAIFI(3) Number of Outages 2011 SAIDI(4) 2012 SAIDI(4) Length of Outages 1.73 1.32 24% 185 124 33% 1.68 1.34 21% 205 163 21% 1.67 1.24 26% 189 141 25% (1)Excluding major event days as defined by Institute of Electrical and Electronics Engineers
Slide 16: Reliability Performance – Pepco's MD Jurisdiction
Reliability Performance – Pepco’s MD Jurisdiction Pepco-MD Performance vs. RM43 Standard SAIFI Component (COMAR Exclusion) SAIFI 2.4 2.1 1.8 1.5 1.2 0.9 0.6 0.3 0.0 1.99 1.95 1.81 1.61 1.36 1.49 2012 SAIFI is 32% lower than in 2011 2011 2012 2013 2014 2015 Actual Performance Mandated Yearly SAIFI Pe
Slide 17: Reliability Performance – DPL's MD Jurisdiction
Reliability Performance – DPL’s MD Jurisdiction Delmarva-MD Performance vs. RM43 Standard SAIFI Component (COMAR Exclusion) 2012 SAIFI is 30% lower than in 2011 SAIFI 2.4 2.1 1.8 1.5 1.2 0.9 0.6 0.3 0.0 2.42 1.77 1.69 1.65 1.55 1.46 2011 2012 2013 2014 2015 Actual Performance Mandated Yearly SAIFI D
Slide 18: Storm Response – Derecho and Hurricane
Storm Response – Derecho and Hurricane “Few people realize the effort it took to restore power to the region after powerful storms” 7.8.12 “This was pretty good compared to previous Storm. I want to personally thank Pepco. They brought in a large number of crews. I’ve criticized them in the past and
Slide 19: 2013 Focus – Continuing to Build on 2012 Progress
2013 Focus – Continuing to Build on 2012 Progress Improving reliability and customer service Investing in transmission and distribution infrastructure Implementing Smart Grid Continue deployment and activation of smart meters in the Pepco and Delmarva Power regions Continue rolling out first phase o
Slide 20: PHI Service Territory
PHI Service Territory Customer Diversity, 2012 Electric Sales Residential 36% Government 10% Industrial 7% Commercial 47% Regulatory Diversity, 2012 Revenues NJ 14% MD 35% DE 17% FERC 14% DC 20% Near Term Economic Outlook is Mixed Pepco Least affected by recession and tracking national employment tr
Slide 21: Sales and Customer Growth
Sales and Customer Growth Sales (GWh) Forecasted Compound Annual Growth Rate Sales Customer 2011 2012 2013 2012 - 2013 2013 - 2017 2012 - 2013 2013 - 2017 Actual* Actual* Projected Pepco 26,622 26,021 26,376 1.4% 0.5% 1.3% 0.8% Delmarva Power 12,586 12,732 12,852 0.9% 1.8% 1.0% 1.1% Atlantic City El
Slide 22: Operation and Maintenance (O&M) Expense
Operation and Maintenance (O&M) Expense 2011 Actual 2012 Actual 2013 Forecast (M illions of Dollars) Utility O&M $ 767 $ 796 $750 - $780 Major Storms (Incremental Costs)(1) 16 1 - Environmental Remediation 2 - - Sub-Total $ 785 $ 797 $750 - $780 Reimbursable/Recoverable(2) 99 104 100 Total O&M $ 884
Slide 23: 2012 Operation and Maintenance Expense
2012 Operation and Maintenance Expense Reimbursable/ Recoverable 12% Operations 26% Administration & Support 20% Major Storms* 0% Customer Care 24% Tree Trimming 6% Maintenance 12% 2012 Actual (Millions of Dollars) Operations $ 245 Customer Care 213 Maintenance 104 Tree Trimming 55 Major Storms * 1
Slide 24: Forecast Construction Expenditures – 2013 - 2017
Forecast Construction Expenditures – 2013 - 2017 (Millions of Dollars) Advanced Metering Infrastructure $92 Transmission $1,340 Other $670 Distribution $3,797 Distribution Transmission Total = $5,899 (Millions of Dollars) $0 $500 $1,000 $1,500 $1,198 $1,210 $1,194 $1,111 $1,186 2013 2014 2015 2016 2
Slide 25: Distribution Construction Expenditures – 2013 - 2017
Distribution Construction Expenditures – 2013 - 2017 (Millions of Dollars) Advanced Metering Infrastructure $92 Transmission $1,340 Other $670 Distribution $3,797 Reliability and Aging Infrastructure ($2,552M) – planned investment is expected to enable us to meet reliability standards in our jurisdi
Slide 26: Pepco Undergrounding Status – Maryland
Pepco Undergrounding Status – Maryland The Maryland rate case filed in December 2012 outlined a plan to underground certain distribution feeders: Immediate recommendation to underground 6 distribution feeders (3 each in Montgomery and Prince George’s counties) Selection based on the 3 feeders in eac
Slide 27: Pepco Undergrounding Status – District of Columbia
Pepco Undergrounding Status – District of Columbia The District of Columbia Power Line Undergrounding Task Force, which started in August 2012, continues its work The Technical Committee of the Task Force has recommended that the option that best balances cost and reliability improvement is to under
Slide 28: Smart Grid Activities
Smart Grid Activities Advanced Metering Infrastructure (AMI) –includes smart meters and communication and data infrastructure Customer applications – empowering customers Distribution automation – enables quicker power restoration Advanced transmission – includes synchrophasors Replacement of our le
Slide 29: Advanced Metering Infrastructure (AMI) Status
Advanced Metering Infrastructure (AMI) – Underway in Delaware, Maryland, and the District of Columbia Pepco Delmarva Power DC MD MD DE Electric meter installation* 98% complete; to be completed 1Q2013 Regulatory asset approved 83% complete; to be completed 2Q2013 Regulatory asset approved Approved b
Slide 30: Other Significant Construction Expenditures – 2013 - 2017
Other Significant Construction Expenditures – 2013 - 2017 (Millions of Dollars) Advance Metering Infrastructure $92 Transmission $1,340 Other $670 Distribution $3,797 Category $ Activity Gas Delivery $140 Improvements associated with FERC gas transmission line regulations and replacement of aging in
Slide 31: Transmission Construction Expenditures – 2013 - 2017
Transmission Construction Expenditures – 2013 - 2017 (Millions of Dollars) Transmission $1,340 Advanced Metering Infrastructure $92 Other $670 Distribution $3,797 Total 2013 - 2017 Forecast Customer Driven $ 22 Reliability 536 Load 194 PJM / RTEP N-1-1 and Major Transmission Lines 220 Transmission L
Slide 32: Power Delivery Business Outlook
Power Delivery Business Outlook Continued improvement in operating performance – safety, reliability, storm response Leveraging technology to enhance customer service Over $5.9 billion in planned infrastructure investment during the next five years Revenue growth through achieving reasonable regulat
Slide 33: Power Delivery Overview
Power Delivery Overview Dave Velazquez, Executive Vice President, Power Delivery
Slide 34: Appendix
Appendix
Slide 35: Construction Expenditure Forecast
Construction Expenditure Forecast (Millions of Dollars) 2013 2014 2015 2016 2017 Total Distribution: Customer Driven (new service connections, meter installations, highway relocations) $ 116 $ 128 $ 131 $ 127 $ 131 $ 633 Reliability and Aging Infrastructure (facility replacements/upgrades for system
Slide 36: Construction Expenditure Forecast by Utility
Construction Expenditure Forecast (Millions of Dollars) 2013 2014 2015 2016 2017 Total Potomac Electric Power Company Distribution $ 409 $ 511 $ 497 $ 472 $ 443 $ 2,332 Distribution – Advanced Metering 8 - - - - 8 Transmission 103 76 88 58 83 408 Other 57 59 38 34 29 217 Less: DOE Capital Reimbursem
Slide 37: Forecast Construction Comparison
Forecast Construction Comparison (Millions of Dollars) 2013 2014 2015 2016 2017 November 2011 * $ 1,044 $ 1,082 $ 1,023 $ 1,327 N/A October 2012 * $ 1,198 $ 1,210 $ 1,194 $ 1,111 $ 1,186 Change $ 154 $ 128 $ 171 $ (216) N/A Change in Construction Forecast 2013-2016 Key Drivers of Change: Distributio
Slide 38: AMI and Demand Response and Energy Efficiency Cost Forecast
AMI and Demand Response and Energy Efficiency Cost Forecast Advanced Metering Infrastructure (AMI) (Millions of Dollars) 2013 2014 2015 2016 2017 Total Construction Cost Atlantic City Electric (1) $ - $ - $ - $ 8 $ 45 $ 53 Delmarva Power 32 1 - - - 33 Pepco 6 - - - - 6 AMI System Improvements 3 - -
Slide 39: Electric Distribution Projected Sales
Electric Distribution Projected Sales (Sales in GWh) 2011 2012 2013 2014 2015 2016 2017 Actual* Actual* Projected Projected Projected Projected Projected Potomac Electric Power Company Residential 7,923 7,780 7,496 7,470 7,525 7,534 7,530 Commercial 18,539 18,082 18,716 18,721 18,917 19,110 19,237 I
Slide 40: Residential Electric Distribution Projected Customers
Residential Electric Distribution Projected Customers Electric Customers* 2011 2012 2013 2014 2015 2016 2017 Actual Actual Projected Projected Projected Projected Projected Potomac Electric Power Company Residential 714,442 719,701 728,512 735,962 743,424 749,680 754,435 Annual Increase 0.7% 1.2% 1.
Slide 41: 2012 Financial Performance – Power Delivery
2012 Financial Performance – Power Delivery Earnings Per Share $0.93 $0.12 $0.07 -$0.03 $0.02 -$0.02 -$0.02 -$0.02 -$0.03 -$0.03 -$0.03 $1.02 2011 GAAP Dist Rate Increases Network Transmission Revenue Micellaneous Distribution Revenue Tax Adjustments ACE/BGS Dilution Distribution Revenue Weather O&M
Slide 42: Regulatory Overview
Regulatory Overview Fred Boyle, Senior Vice President & Chief Financial Officer
Slide 43: Executing Our Regulatory Strategy
Executing Our Regulatory Strategy Continuing our work to improve customer service and reliability Continuing our focus on achieving timely recovery and fair returns Filing rate cases every 9 - 12 months in each jurisdiction Pursuing alternative ratemaking mechanisms/approaches Educating the regulato
Slide 44: Accomplishments Since Our Last Analyst Conference
Accomplishments Since Our Last Analyst Conference Five distribution base rate case decisions received in 2012 authorizing a total annual increase of $104 million Four active cases filed with two additional cases to be filed by end of March Annual transmission rate updated resulting in a total annual
Slide 45: Regulatory Environment
Regulatory Environment Positives Regulators have been supportive of cost recovery for AMI, energy efficiency and demand response initiatives Reliability expectations have re-opened the discussions for alternative ratemaking mechanisms Formula rates in place at FERC Challenges Regulatory lag in distr
Slide 46: Rate Base Summary
Rate Base Summary 2012 Estimated Year-End Rate Base by Company (Millions of Dollars) Transmission Pepco $ 641 Delmarva Power 507 Atlantic City 395 Total - Transmission $ 1,543 Distribution Pepco - Electric $ 2,485 Delmarva Power - Electric 1,138 Delmarva Power - Gas 251 Atlantic City - Electric 1,07
Slide 47: Regulatory Distribution Returns on Equity
Regulatory Distribution Returns on Equity Jurisdiction/Company Test Period Estimated Rate Base in Current Rate Case Cycle (Millions of Dollars) Estimated Per Books Return on Equity Estimated Return on Equity with Annualized 2012 Rate Orders* Authorized Return on Equity MD – Pepco 12/31/12 Avg. $1,16
Slide 48: Our Strategy for Reducing Regulatory Lag
Our Strategy for Reducing Regulatory Lag Frequent Rate Case Filings Maryland: Statute – 7 months District of Columbia: No statute, PSC target to complete cases within 9 months of filing Delaware: Statute – 7 months New Jersey: Statute – 9 months; Extensions granted Reduce Regulatory Lag Initiatives
Slide 49: Distribution Rate Cases – The Current Cycle
Distribution Rate Cases – The Current Cycle We are filing distribution base rate cases in each of our jurisdictions between November 2012 and March 2013 In the four active rate case filings, we have requested an annual increase in revenue of $196 million in total: (Millions of Dollars) Jurisdiction/
Slide 50: Distribution Rate Cases – Drivers of Requested Revenue Increase
Distribution Rate Cases – Drivers of Requested Revenue Increase We are currently under-earning our authorized ROE in all jurisdictions Breakdown of requested rate increases: Rate base growth, including reliability investments Increase in operating expenses, including customer service enhancements Re
Slide 51: Regulatory Information by Commission
Regulatory Information by Commission Rate Cases District of Columbia Maryland Delaware New Jersey Permitted to file partially forecasted test year? Yes Yes Yes Yes Required to update test year data to actual? No (1) Yes No Yes Timing for rate implementation No statute; target to complete cases withi
Slide 52: Distribution Rate Cases – Focus on Reducing Regulatory Lag
Distribution Rate Cases – Focus on Reducing Regulatory Lag Advancing mechanisms to reduce regulatory lag include: Test periods adjusted to recover additional reliability plant additions for future periods Grid Resiliency Charge proposed in MD Multi-year rate plan under discussion in DE Rate cases wi
Slide 53: Distribution Rate Cases – Pending Pepco – Maryland
Distribution Rate Cases – Pending Pepco – Maryland Pepco - MD Case No. 9311 (Millions of Dollars) Test Period 6 mos. actual 6 mos. forecast ending 12/31/12 Adjusted Rate Base $1,296.1 Equity Ratio 49.5% Return on Equity (ROE) 10.25% Revenue Requirement Increase $60.8 (1)(2) Residential Total Bill %
Slide 54: Distribution Rate Cases – Pending Delmarva Power – Delaware Gas
Distribution Rate Cases – Pending Delmarva Power – Delaware Gas Delmarva Power - DE Gas Docket No. 12-546 (Millions of Dollars) Initial Filing Date 12/7/12 Test Period 6 mos. actual 6 mos. forecast ending 12/31/12 Adjusted Rate Base $273.2 Equity Ratio 48.8% Return on Equity (ROE) 10.25% Revenue Req
Slide 55: Distribution Rate Cases – Pending Atlantic City Electric – New Jersey
Distribution Rate Cases – Pending Atlantic City Electric – New Jersey Atlantic City Electric Docket No. ER12121071 (Millions of Dollars) Filed Position 1/4/13 12 Test Period mos. actual data ending 9/30/12 Adjusted Rate Base $1,198.9 Equity Ratio 49.0% Return on Equity (ROE) 10.25% Net Revenue Requi
Slide 56: Distribution Rate Cases – Pending Pepco – District of Columbia
Distribution Rate Cases – Pending Pepco – District of Columbia Pepco - District of Columbia FC No. 1103 (Millions of Dollars) Filed Position 3/8/13 12 Test Period mos. actual data ending 12/31/12 Adjusted Rate Base $1,371.1 Equity Ratio 49.8% Return on Equity (ROE) 10.25% Net Revenue Requirement Inc
Slide 57: FERC-Regulated Transmission Business
FERC-Regulated Transmission Business (Millions of Dollars) Pepco Delmarva Power Atlantic City Electric Total 2011 Actual Year-End Rate Base $544 $422 $370 $1,336 2012 Estimated Year-End Rate Base (1)(2) Base Amount - 11.3% $514 $406 $347 $1,267 Incentive Amount - 12.8% MAPP Related 45 35 - 80 Incent
Slide 58: FERC Filing Challenging Our Transmission Rates
FERC Filing Challenging Our Transmission Rates On February 27, 2013, the public utilities commissions and public advocates in all four of our jurisdictions made a Section 206 filing at FERC challenging the transmission rates of each of the Company’s three utilities Two primary issues included in the
Slide 59: MAPP Abandoned Cost Recovery
MAPP Abandoned Cost Recovry FERC order issued on F ebruary 28, 2013 FERC concluded that the MAPP project was canceled for reasons beyond the Company’s control and granted recovery of prudently incurred costs Key elements of the Order: Established a hearing to review the prudence of the $87.5 million
Slide 60: Decoupling Status
Decoupling Status Jurisdiction Pepco/Delmarva Power – MD Pepco – DC Delmarva Power – DE ACE – NJ Status Implemented June 2007 Implemented November 2009 Filed, requires PSC approval Request deferred Forecasted 2013 % Regulated Distribution Revenue 40% 24% 64% 14% 22% Decoupling provides benefits to b
Slide 61: Regulatory Summary
Regulatory Summary Highly experienced regulatory team, supplemented with strong new players Committed to filing rate cases every 9 - 12 months in each jurisdiction to reduce regulatory lag while simultaneously pursuing alternative ratemaking mechanisms PHI strategy is well aligned with the energy ef
Slide 62: Regulatory Overview
Regulatory Overview Fred Boyle, Senior Vice President & Chief Financial Officer
Slide 63: Appendix
Appendix
Slide 64: Distribution Base Rate Case Outcomes
Distribution Base Rate Case Outcomes Revenue Return on Equity Ratio Increase Equity (Millions of Dollars) 2008 Pepco - DC$28.310.00%46.55% 2009 DPL - MD$7.510.00%49.87% 2010 Pepco - DC$20.3 (1)9.63%46.18% 2010 ACE - NJ$20.010.30%49.10% 2010 Pepco - MD$7.89.83%48.87% 2011 DPL Electric - DE$16.410.00%
Slide 65: Transmission Formula Rate Process
Transmission Formula Rate Process Formula Rate Components • Debt % in Capital Structure x Debt Rate x Total Rate Base • Equity % in Capital Structure x 11.3% ROE x Base Rate Base • Equity % in Capital Structure x 12.8% ROE x Incentive Rate Base • Operation and Maintenance • Depreciation and Amortiza
Slide 66: Default Service Auction/Bidding Process
Default Service Auction/Bidding Process Maryland (Pepco/Delmarva Power) District of Columbia (Pepco) Delaware (Delmarva Power) New Jersey (Atlantic City Electric) Transition to Competitive Market July 2004 February 2005 May 2006 August 2003 Procurement Public Service Commission approves and monitors
Slide 67: Default Service Procurement – Auction Description for Load Bid 2013/14
Default Service Procurement – Auction Description for Load Bid 2013/14 Maryland - Pepco/Delmarva Power District of Columbia - Pepco Delaware - Delmarva Power New Jersey - Atlantic City Electric Supply Period6/1/13 to 5/31/146/1/13 to 5/31/146/1/13 to 5/31/146/1/13 to 5/31/14 Load Bid50% (2)(5) 37.2%
Slide 68: Methods of Cost Recovery Outside of Base Rate Case Process
Methods of Cost Recovery Outside of Base Rate Case Process MD DC DE NJ Transmission rate recovery via FERC formula rates - adjusted annually; retail rate reflects FERC formula rate Procurement cost adjustment mechanisms - reconciles purchased power costs AMI Costs - deferred as a regulatory asset fo
Slide 69: Pepco Energy Services Overview
Pepco Energy Services Overview John Huffman, President and CEO, Pepco Energy Services
Slide 70: Pepco Energy Services – Overview
Pepco Energy Services – Overview ESCO business: Provides government and institutional customers with competitive energy efficiency services Energy Efficiency • Designs, builds, and operates energy efficiency projects • Since 1995, completed over $1 billion of projects Combined Heat and Power (CHP) •
Slide 71: ESCO Market - Challenged
ESCO Market - Challenged The ESCO market experienced a significant downturn in 2012 driven by a decrease in the energy efficiency business; particularly in the state and local government market segments PES signed $9 million of energy efficiency projects in 2012, well below its recent pace, while it
Slide 72: 2013 Outlook
2013 Outlook PES expects the energy efficiency markets will remain soft in 2013 In the second half of 2012, PES responded to market conditions: •Reduced ongoing costs by approximately $8 million (after-tax) •Incurred a one-time charge of $1.4 million (after-tax) for severance PES expects to earn app
Slide 73: Energy Efficiency Market – Looking Forward
Energy Efficiency Market – Looking Forward State and local government markets are expected to rebound as the economy improves Federal government market activity is picking up: •Prior presidential executive orders and agency directives have recently increased Request for Proposal (RFP) activity •PES’
Slide 74: Combined Heat and Power (CHP)
Combined Heat and Power (CHP) Building off its recent DC Water CHP contract, PES is developing opportunities targeting federal government and other customers CHP opportunities are expected to grow: •Natural gas prices are forecasted to remain low •CHP plants are efficient – capturing up to 80% of a
Slide 75: Underground Transmission and Distribution Business
Underground Transmission and Distribution Business W.A. Chester is an industry leader in the installation and maintenance of underground high voltage transmission cable and distribution infrastructure for electric utilities Chester’s earnings have been growing 10% annually in the last 3 years as the
Slide 76: Retail Energy Supply Wind-Down
Retail Energy Supply Wind-Down The bulk of the retail energy supply contracts have rolled off - remaining contracts roll off in mid-2014 PES is considering alternatives to accelerate the completion of the wind-down into 2013 • Either sell retail contracts to other marketers or terminate them with re
Slide 77: Summary
Summary The long-term fundamentals of the energy efficiency business remain strong - PES is well positioned to grow as the state and local government markets rebound and the federal government market expands Reliability initiatives in the utility industry are expected to increase long-term demand fo
Slide 78: Pepco Energy Services Overview
Pepco Energy Services Overview John Huffman, President and CEO, Pepco Energy Services
Slide 79: Appendix
Appendix
Slide 80: Contract Backlog Data
Contract Backlog Data ESCO Construction: Energy Services and Combined Heat and Power Operations and maintenance contracts related to energy efficiency and CHP projects; 3 - 15 year contracts Gross Margin $7 million Contract Backlog 9-month remaining weighted average $38 million Contract Backlog 12-y
Slide 81: Key Features of Typical Projects
Key Features of Typical Projects Energy Efficiency Projects Combined Heat & Power W.A. Chester Typical construction contract size $2 - $30 million $10 - $75 million $1 - $30 million Operation and maintenance Related to ~20% of projects; 2 – 15 year term Typically all projects; 15 – 20 year term N/A
Slide 82: Reconciliation of GAAP Earnings to Adjusted Earnings
Reconciliation of GAAP Earnings to Adjusted Earnings ($ in millions) Energy Services PES Overhead 2012 Retail Energy Supply(1) Total Energy Services PES Overhead 2011 Retail Energy Supply(1) Total Reported Earnings (GAAP) $ - $ (5) $ 23 $ 18 $ 20 $ (5) $ 9 $ 24 Adjustments (After-tax)(2) Mark-to-Mar
Slide 83: Financial Overview
Financial Overview Fred Boyle, Senior Vice President & Chief Financial Officer
Slide 84: Financial Objectives
Financial Objectives Achieve long-term earnings and dividend growth by: Investment in infrastructure Reduction of regulatory lag Maintain solid investment grade credit ratings by sustaining: Solid credit metrics Ample liquidity Strong cash flow Low business risk profile Our regulated business model
Slide 85: Projected Capital Expenditures – 2013 - 2017
Projected Capital Expenditures – 2013 - 2017 (Millions of Dollars) $1,400 $1,200 $1,000 $800 $600 $400 $200 $0 $1,207 $1,218 $1,203 $1,197 $1,122 2013 2014 2015 2016 2017 Distribution Transmission PES/Other 2013 2014 2015 2016 2017 Distribution $ 932 $ 956 $ 914 $ 869 $ 888 Transmission 266 254 280
Slide 86: Infrastructure Investment – The Driver of Growth
Infrastructure Investment – The Driver of Growth (Millions of Dollars) $12,000 $10,000 $8,000 $6,000 $4,000 $2,000 $0 Year-End Rate Base 8 % CAGR 2012 - 2017) $9,215 $9,700$8,570 $7,958 $2,439 $2,292 $7,315 $2,111 $6,489 $1,888 $277 $273 $1,764 $268 $5,702 $263 $5,108 $1,543 $255 $1,336 $251 $1,192
Slide 87: Credit Profile
Credit Profile PHI Credit Metrics 2012 Actual* Long-Term Target Metrics FFO Interest Coverage 3.5X 3.5X Debt/Capitalization 58% ~55% Debt/Capitalization will be strengthened by the February 2013 settlement of the equity forward transaction ($312 million) Targeted debt to capitalization ratio at the
Slide 88: Liquidity Position
Liquidity Position At March 5, 2013 PHI Consolidated Credit Facility (Total Capacity) $650 $850 $1,500 Letters of Credit Issued (2) - (2) Commercial Paper Outstanding (208) (480) (688) Remaining Credit Facility Available $440 $370 $810 Cash Invested in Money Market Funds - 3 3 Total Cash and Credit
Slide 89: 2013 Financing Activity
2013 Financing Activity Debt Issuance Utility long-term debt issuance of $750 - $850 million* Pepco ~$400 million ($200 million maturing) Delmarva Power ~$300 million ($250 million maturing) Atlantic City Electric ~$100 million ($69 million maturing) Equity Issuance Equity forward transaction entere
Slide 90: Manageable Debt Maturity Schedule
Manageable Debt Maturity Schedule (Millions of Dollars) $700 $600 $500 $400 $300 $200 $100 $0 Long-Term Debt Maturities December 31, 2012* 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Pepco Holdings Inc Atlantic City Electric Delmarva Power & Light Potomac Capital Invt Corp Potomac Electric Pow
Slide 91: 2013 Estimated Sources & Uses of Cash
2013 Estimated Sources & Uses of Cash (Millions of Dollars) Principal Sources of Cash: Cash Flow from Operations (1) $ 925 Equity Forward Settlement (2) 312 Dividend Reinvestment Plan/Employee Savings Plan 42 New Debt Issue: Long-term - Utilities (3) 280 Short-term 378 Total Sources of Cash $ 1,937
Slide 92: Pension and OPEB Impacts
Pension and OPEB Impacts Net Pension & OPEB Pre-Tax Expense (O&M) (Millions of Dollars) $90 $80 $70 $60 $50 $40 $30 $20 $10 $0 $77 $69 Pension & OPEB 2012A 2013E Pension Cash Contributions (Millions of Dollars) $300 $250 $200 $150 $100 $50 $0 $200 $60 Pension 2012A 2013A Key Metrics – Pension and OP
Slide 93: Cash Tax Summary
Cash Tax Summary PHI remains in a Net Operating Loss (NOL) position after the tax adjustment associated with the cross-border energy lease portfolio 2013 50% Bonus Depreciation Expense – approximately $400 million NOL expected to be fully utilized in 2014, assuming no extension of bonus depreciation
Slide 94: Cross-Border Energy Leases
Cross-Border Energy Leases In January 2013, an appellate court issued an opinion in a Consolidated Edison case that disallowed tax benefits associated with certain cross-border energy lease transactions After updating our assessment of PHI’s cross-border energy leases, we expect to record an estimat
Slide 95: Secure Dividend, Attractive Yield
Secure Dividend, Attractive Yield Indicated annual dividend of $1.08 per share supported by regulated utility earnings Current dividend yield is 18% higher than the average dividend yield for companies in the S&P 500 Electric Utilities Dividend Yield 6.0% 5.0% 4.0% 3.0% 2.0% 1.0% 0.0% 5.3% 4.5% PHI
Slide 96: 2013 Earnings Guidance
2013 Earnings Guidance Earnings Per Share $1.40 $1.20 $1.00 $0.80 $0.60 $0.40 $0.20 $0.00 $1.21 $1.05 - $1.20 2012 Adjusted* 2013E Guidance The guidance range excludes: The results of discontinued operations and the impact of any special, unusual or extraordinary items All earnings or losses associa
Slide 97: 2013 Earnings Guidance (continued)
2013 Earnings Guidance (continued) Earnings Per Share – 2012 Adjusted vs. 2013 Guidance* $1.60 $1.40 $1.20 $1.00 $0.80 $0.60 $0.40 $0.20 $0.00 $0.02 ($0.02) $0.03 ($0.03) $0.10 ($0.03) ($0.04) ($0.04) $0.10 ($0.06) $1.21 ($0.09) $1.05 - $1.20 ($0.12) Includes Impact of Regulatory Outcomes 2012 Adjus
Slide 98: 2013 Earnings Guidance Assumptions
2013 Earnings Guidance Assumptions Power Delivery Normal weather and operating conditions Reasonable regulatory outcomes for pending electric distribution base rate cases Projected 1.2% growth in number of total customers Forecasted sales growth of 1.4% Utility total O&M expense of $850 - $880 mill
Slide 99: 2013 Earnings Guidance Assumptions (continued)
2013 Earnings Guidance Assumptions (continued) Pepco Energy Services After-tax earnings of approximately $5 million Excludes earnings or losses associated with the retail energy supply business, including the after-tax net mark-to-market effects of economic hedging activities PHI Excludes all earnin
Slide 100: Investment Highlights
Investment Highlights Stable Earnings Base – Derived primarily from regulated utility business Long-term Earnings Growth – Driven by T&D utility infrastructure investments and reasonable regulatory outcomes Power Delivery – 8% CAGR of Rate Base (2012 – 2017) Financial Strength – Manageable financing
Slide 101: Financial Overview
Financial Overview Fred Boyle, Senior Vice President & Chief Financial Officer
Slide 102: Appendix
Appendix
Slide 103: Sales and Financial Information – Potomac Electric Power Company
Sales and Financial Information Potomac Electric Power Company (Millions of Dollars, except Sales and Customers) Electric GWh Sales DC Electric Delivered MD Electric Delivered Total Electric Delivered Standard Offer Service Projected 2013 11,772 14,604 26,376 8,495 2014 11,878 14,478 26,356 8,474 20
Slide 104: Sales and Financial Information – Delmarva Power & Light Company
Sales and Financial Information Delmarva Power & Light Company (Millions of Dollars, except Sales and Customers) Electric GWh Sales DE Electric Delivered MD Electric Delivered Total Electric Delivered Standard Offer Service Projected 2013 8,551 4,301 12,852 6,073 2014 8,616 4,345 12,961 6,123 2015 8
Slide 105: Sales and Financial Information – Atlantic City Electric Company
Sales and Financial Information Atlantic City Electric Company (Millions of Dollars, except Sales and Customers) Electric GWh Sales Residential Electric Customers NJ Electric Basic Generation Delivered Service Customers % Change Projected Projected 2013 9,646 5,069 2013 485,126 1.3% 2014 9,698 5,123
Slide 106: Projected Capital Expenditures – 2013 - 2017
Projected Capital Expenditures – 2013 - 2017 (Millions of Dollars) 2013 2014 2015 2016 2017 Total Power Delivery Distribution $ 733 $ 801 $ 784 $ 753 $ 730 $ 3,801 Distribution - Smart Grid 41 1 - 8 45 95 Transmission 266 254 280 242 298 1,340 Gas Delivery 26 28 28 28 30 140 Other 139 126 102 80 83
Slide 107: Projected Rate Base by Utility
Projected Rate Base by Utility 2012 2013 2014 2015 2016 2017 (Millions of Dollars) Estimated Projected Projected Projected Projected Projected Distribution – Electric Pepco $2,485 $2,772 $3,075 $3,289 $3,570 $3,743 Delmarva Power 1,138 1,280 1,381 1,461 1,538 1,618 Atlantic City Electric 1,072 1,244
Slide 108: Calculation of Credit Metrics
Calculation of Credit Metrics 2012 Net Cash Provided by Operating Activities (GAAP Measure) $ 592 Rating Agency Adjustments Less: Changes in Working Capital & Other 12 Less: Securitized Debt Adjustment (39) Plus: Pension & Postretirement Benefit Obligations Adjustment 140 Plus: Operating Lease Adjus
Slide 109: Long-term Debt Maturities
Long-term Debt Maturities Maturity Interest 2013 2014 2015 (Millions of dollars) Date Rate Pepco - Senior Notes 11/15/13 4.95% $200 $ - $ -Pepco - Senior Notes 4/15/14 4.65% - 175 -Delmarva Power - FMB 12/1/13 6.40% 250 - -Delmarva Power - Unsecured Notes 11/15/14 5.00% - 100 -Delmarva Power - Unsec
Slide 110: Pension – Liability-Driven Investment Strategy
Pension – Liability-Driven Investment Strategy Beginning in the second quarter of 2011, PHI initiated a modified pension investment policy Pension Fund to reduce volatility of funded status and Asset Allocation pension costs 12/31/12 • “Return-seeking” (i.e., equity) assets reduced from over 60% to
Slide 111: Our Approach to Earnings Guidance
Our Approach to Earnings Guidance Range provided for ongoing operations (GAAP results excluding special, unusual or extraordinary items) For guidance purposes, the items below will be excluded from results even if not classified as a special item for reporting purposes: • Effect of adopting new
Slide 112: Reconciliation of GAAP EPS to Adjusted EPS
Reconciliation of GAAP EPS to Adjusted EPS Year Ended December 31, 2012 2011 Reported (GAAP) Diluted Earnings per Share from Continuing Operations $ 1.24 $ 1.15 Adjustments (after-tax):* Mark-to-market (gains)/losses from Pepco Energy Services retail energy (0.06) 0.08 economic hedging activities