Petra Diamonds Limited · LSE:PDL
Petra Diamonds — Technical Presentation (February 2017)
48 slides from Petra Diamonds's technical presentation, Feb 4, 2017
Slide 1: Cullinan Site Visit
Cullinan Site Visit 4 February 2017 Photo: Underground at Cullinan: Silo no.2 C-cut project
Slide 2: Important Notice
Important Notice • These Presentation Materials are being supplied to you by Petra Diamonds Limited (the “Company”) solely for your information and use at this presentation. These Presentation Materials may contain information that is confidential, legally privileged or otherwise protected by law. T
Slide 3: Cullinan Site Visit Itinerary
Cullinan Site Visit Itinerary • 08:00 Pick up from Sandton, Johannesburg • 08:15 Pick up from OR Tambo • 09:30 Arrive Cullinan Diamond Mine • 09:45 Overview on Petra, Cullinan & Safety briefing • 11:00 Underground visit 138.57 ct Cullinan white, sold for US$6.5 million FY 2017 • 13:00 New plant visi
Slide 4: About Petra
© — Ss o (aL, = > fe) Xe) <x
Slide 5: Discover Petra…
Discover Petra… Revenue Adjusted EBITDA …a leading independent diamond miner with a US$m US$m diversified portfolio and high quality team 600 200 188 472 431 164 425 392 128 139 400 317 Petra expansion plans expected to: 277 100 90 116 200 • Improve grades 154 49 0 0 • Improve product mix FY12 FY13
Slide 6: H1 FY 2017 – driving forward to FY 2019
H1 FY 2017 – driving forward to FY 2019 H1 FY 2017 FY 2019 21% 51% 5% 41% 40% Production 1% by mine Finsch 22% Cullinan 11% Williamson 2% 6% Koffiefontein 20% Kimberley Ekapa 33% Revenue 43% Mining 36% by mine 14% 11% 12% 17% 6% 8% Unit H1 FY 2017 H1 FY 2016 Variance FY 20161 SALES Revenue US$m 228.
Slide 7: Moving to Undiluted Ore
Moving to Undiluted Ore • Caving is a safe and proven mechanised mining method; provides access to higher volumes of ore than other methods • Current underground mining taking place in diluted, mature caves nearing end of lives • Expansion programmes to take next ‘cut’ by deepening and establishing
Slide 8: Growth and Margin Expansion
Growth and Margin Expansion Adjusted EBITDA margin expected to rise from ca. 38% in FY 2016 to +50% by FY 2019 • Increase in ROM grades and increase in tonnage throughput (mainly due to Kimberley Mines transaction) to lead to ca. 43% growth in production • Lower value tailings carat production to re
Slide 9: Growth and Margin Expansion
Growth and Margin Expansion Petra to maintain a fairly flat tonnage profile from FY 2017 onwards, but the replacement of poor quality tonnes with better quality tonnes will significantly grow production and increase the average value per carat FY 2019 production target of ca. 5.3 Mcts; revenue of ca
Slide 10: Cullinan Overview
V4 Cullinan Overview
Slide 11: Cullinan Diamond Mine (“CDM”) Overview
Cullinan Diamond Mine (“CDM”) Overview 1902 1903 1905 1930 1932 1945 1997 2008 2009 Cullinan Open pit Recovery of De Beers Mine closed Mine Premier Mine acquired Petra kimberlite pipe mining the 3,106 acquired due to reopened and (Transvaal) by Petra increased its originally commenced at carat Culli
Slide 12: Iconic Diamonds of Cullinan
Iconic Diamonds of Cullinan • Petra’s Exceptional Diamonds (+$5 million stones) contributed on average $23 million p.a. from FY 2009 to FY 2016 • A 121 carat white diamond, recovered at Cullinan in June 2016, was sold for US$6 million in July • A 138.57 carat white stone from Cullinan sold for US$6.
Slide 13: Safety Performance
Safety Performance Highest LTIFR/nr = 2001: 0.80 / (19) 2001 = Previous time that development was done U/G 2010 – current = Increase in activities, employees and projects both Lowest LTIFT/nr = 2008&9: 0.13 (2) underground and surface plant *LTIFR = Nr of lost time injuries x 200,000 hrs / hrs worke
Slide 14: Major Diamond Resources
Major Diamond Resources Gross (June 2016) Contained Tonnes Grade Diamonds Category (millions) (cpht) (Mcts) Reserves Proved - - - Probable 47.8 45.1 21.6 Sub-total 47.8 45.1 21.6 Resources Measured - - - Indicated 251.5 70.3 176.9 Inferred 171.2 10.1 17.3 Sub-total 422.7 45.9 194.2 • Resource bottom
Slide 15: ROM Grade Improvement
ROM Grade Improvement 45 40 39.9 38.9 35 36.6 34.5 33.3 30 30.7 30.3 27.8 Grade (cpht) 25 25.7 24.4 20 Declining ROM grade as result of maturing of cave (waste ingress), exacerbated Turnaround in ROM grade as a 15 by high level of development waste in FY 2014 and FY 2015 from host rock that result o
Slide 16: Cullinan – Progress and the Road Ahead
Cullinan – Progress and the Road Ahead FY FY FY FY FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Development programme 2011 2012 2013 2014 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 Development of Declines & Access Tunnels Blasting of Under Cut at 824L New Production levels at 839L Development of Shaft #1 to 943L Prod
Slide 17: Mining Overview
V4 Mining Overview
Slide 18: Cullinan – High Level Development Programme
Cullinan – High Level Development Programme Expansion Plan FY 2016 Development: Waste: 1,911 metres; Raiseboring: 838 metres; Kimberlite: 2,837 metres • Expansion plan to take production to ca. 2.2 Mcts by FY 2019 (2.0 ROM & 0.2 tailings) • C-Cut Phase 1: new block cave being established on the west
Slide 19: Block Caving Schematic
Block Caving Schematic Undercut tunnel is made through the orebody and Undercut material is broken up Production level is created below; draw points are set Draw bells / Draw points up and a fan is drilled above each one; ore starts to ‘cave’ Production level under its own weight and is removed from
Slide 20: Plan View of Cullinan Mining Areas
Plan View of Cullinan Mining Areas Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 20
Slide 21: C-Cut Phase 1 Expansion Programme
C-Cut Phase 1 Expansion Programme
Slide 22: C-Cut Under Cut Level
C-Cut Under Cut Level Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 22
Slide 23: C-Cut Production Level
C-Cut Production Level Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 23
Slide 24: C-Cut Under Cut and Extraction Overlay (Dec’16)
C-Cut Under Cut and Extraction Overlay (Dec’16) Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 24
Slide 25: C-Cut Phase 1
C-Cut Phase 1 C-Cut Phase 1 was 86% complete as at 31 December 2016 Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 25
Slide 26: Cullinan Development Snapshot
Cullinan Development Snapshot Rock breaker south extraction Long hole drilling draw point North production conveyor 2 Conveyor Planning Crusher installation Silo loading Box Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 26
Slide 27: New Plant
New Plant
Slide 28: New Plant – Significantly Reduced Footprint
New Plant – Significantly Reduced Footprint COMPARISON – CURRENT vs AG MILLING PLANT Current Plants New AG Milling Plant (Main, DTP & OSP) 6.0Mt ROM capacity 2.8 Mt ROM Initial feed: Throughput p.a. 2.5 Mt Tailings 4.0 Mt ROM 2.3 – 2.5 Mt Tailings Total footprint ca. 27 ha ca. 4 ha MAJOR EQUIPMENT I
Slide 29: New Plant – Simplified Process Flow Diagram
New Plant – Simplified Process Flow Diagram The New Mill Plant was 87% complete as at 31 December 2016 Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 29
Slide 30: New Plant Construction Snapshot
New Plant Construction Snapshot Mill 1 Feed – Fully Autogenous Milling, inter- HPGR motor side, Inter-particle crushing, XRL BV X-Ray Machine, X-Ray particle grinding Luminescence. 12-25mm & 25-75mm DTP BV X-Ray Machine, 6mm to 12mm . Mill 1 Discharge, Split 75-150, 12-75, 1-12mm 7 Dam Pumps, simpli
Slide 31: New Plant Construction Snapshot
New Plant Construction Snapshot Run of Mine Silo & Recycle Silo Main Sub Station Recovery & HPGR & XRL Buildings Mill plant, mill basis and DMS feed area Jaw Crusher installation 110 & 210 conveyor to mill Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 31
Slide 32: Costs & Capex
x a) a. © O og & 12) fo) O
Slide 33: Operating Cost History and Make-up
Operating Cost History and Make-up 350 On-mine cash cost per tonne treated 7 Million tonnes treated R/t treated 300 6 250 5 200 4 150 3 Increased unit cost due to the planned reduction in processing of ROM and 100 2 tailings, to focus on grade control (FY 2016) as well as start-up of new plant (FY 2
Slide 34: C-Cut Phase 1 Project: Actual Expenditure compared to Budget
C-Cut – Phase 1 Project: Actual Expenditure compared to Budget 1,200 4,500 4,000 1,000 3,500 800 3,000 Rand (millions) 2,500 600 H1 FY 2016 2,000 YTD Actual - R493m YTD Budget - R490m 400 1,500 1,000 200 500 0 0 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Budget 570 704 842 918 591 291 1
Slide 35: Outlook
Outlook
Slide 36: Cullinan – Production Plan
Cullinan – Production Plan • ROM tonnages to rise 60%, but ROM carat production expected to rise +200%, due to increase in grade as result of mining undiluted C-Cut tonnes Tonnes treated and grades Carat production and average diamond values 7.5 60 3.0 200 New plant fully $/ct cpht Million carats Mi
Slide 37: Cullinan Outlook
Cullinan Outlook • Improving grades – grade to rise gradually from ca. 35 cpht to +50 cpht by FY 2019 • Improving product mix – due to production from undiluted areas and higher proportion of ROM vs tailings • Improving recoveries – new plant to optimise recoveries from Cullinan • Improving mining c
Slide 38: CSR
CSR
Slide 39: Safety, Health & Employee Wellbeing
Safety, Health & Employee Wellbeing • OHSAS 18001:2007 certified • Continued focus on safety • Fatality sustained during H1 FY2017 • Time out sessions to enhance safety culture • Formalized VFL system • Focused audits • Communication • Monthly HSE topics distributed, H&S meetings Cullinan achieve 50
Slide 40: Environmental Management
Environmental Management • ISO 14001 certified; recertification in 2015 • Incidents Management • No major environmental incidents reported • No external community complaint received in FY 2017 • EMP • Environmental Management Programme (EMP) approved in 2012 • Water Use License • Currently operating
Slide 41: Training and Development
Training and Development • Key area of focus – US$5.8m invested throughout the Group in FY 2016 • Leadership Development Programme – helps Petra identify and develop future leaders within the organisation: • 61 employees participated in FY 2016 • 28% of participants were female LDP Graduations • 40
Slide 42: Education Initiatives
Education Initiatives • Technical skills – long-term strategy to address scarcity of skills in the industry • Supporting early learning – Cullinan transformed the Refilwe Early Learning Centre to ensure a conducive learning environment • Careers Day – Cullinan hosted a careers days for 13 schools in
Slide 43: Community Projects
Community Projects • Significant investment – Group social spend of US$1.7 million in FY 2016 (FY 2015: US$1.7 million) • Multi-purpose sports facilities – constructed at 3 local primary schools, labourers from the local community were employed. Project launch date is 3 February 2017 • Expansion of
Slide 44: Appendix
x< = = 5 ioe BS 2]
Slide 45: Location
Location Petra Diamonds Limited: Cullinan Site Visit - 4 February 2017 45
Slide 46: Current Trading – H1 FY 2017 Results
Current Trading – H1 FY 2017 Results Unit H1 FY 2017 H1 FY 2016 Variance FY 2016 Sales Revenue US$m 46.0 25.0 +84% 83.8 Diamonds sold Carats 363,113 227,759 +59% 663,175 Average price per carat US$ 127 110 +16% 1261 ROM Production Tonnes treated Tonnes 1,039,417 1,180,399 -12% 2,302,892 Diamonds pro
Slide 47: Labour Relations – Risk Mitigation
Labour Relations – Risk Mitigation • Labour relations at Cullinan have been stable in FY 2015 and FY 2016 • No migrant labour – 70% of employees come from local/provincial area to Cullinan • Strong focus on internal communications and engagement with employee representatives • Petra concluded 3 year
Slide 48: Thank you
Thank you Further enquiries: Investor Relations [email protected] +44 20 7494 8203 www.petradiamonds.com