Critical Mineral Resources Plc · LSE:CMRS
Critical Mineral Resources — Investor Presentation (June 2026)
22 slides from Critical Mineral Resources's investor presentation, June 2026
Slide 1: Critical Mineral Resources Plc Corporate Presentation Q2 2026
CRITICAL MINERAL RESOURCES PLC Corporate Presentation – Q2 2026
Slide 2: Disclaimer
2 DISCLAIMER The sole purpose of this investor presentation, talks given by presenters, the information communicated during any delivery of the presentation and any question and answer session and any document or material distributed at or in connection with the presentation (together, the “Presenta
Slide 3: Board of Directors
3 BOARD OF DIRECTORS GÉRAUD CHARLES NOUREDDINE RUSSELL RUSSELL MOUSARRIE LONG SABRAOUI THOMSON TUCKER CHAIRMAN CEO COO NED NED Géraud has extensive Charlie is a mining Noureddine is an Russell Thomson is an Russell Tucker brings accountant with over over 10 years of resources experience specialist w
Slide 4: Investment Case
4 INVESTMENT CASE 01 04 Strategy to become a mid-sized north African copper Internal resource model based on 50 x 100m drilling and base metals producer underpins Initial Mine development First asset is copper–silver discovery* at Agadir-Melloul Aiming for 2027 construction 02 05 Earning 60% through
Slide 5: Morocco's Strong Copper Outlook
5 WORLD COPPER MINE SUPPLY (Mt) MOROCCO’S STRONG 37 COPPER OUTLOOK POSSIBLE PROBABLE COMMITTED AFTER DISRUPTION ALLOWANCE • Favourable jurisdiction – No.2 in Africa (Fraser Institute) 32 FORECAST MINE SUPPLY • Presence of large-scale copper deposits confirmed ACTUAL/REQUIRED MINE SUPPLY (Tizert: 130
Slide 6: Agadir Melloul Introduction
6 AGADIR MELLOUL INTRODUCTION
Slide 7: Agadir-Melloul Location and Regional Context
7 Company making sedimentary COMPANY MAKING copper deposit SEDIMENTARY COPPER DEPOSIT AGADIR-MELLOUL AGADIR TIZERT ZGOUNDER / AYA GOLD & SILVER OTHER MINES 50 100km
Slide 8: Internal Resource Based on 7 Months Drilling
8 INTERNAL RESOURCE BASED ON 7 MONTHS DRILLING - EXCELLENT ROI
Slide 9: Drill Results: Copper-Silver, All Mineralisation Near Surface
9 DRILL RESULTS: COPPER - SILVER ALL MINERALISATION NEAR SURFACE No. Length (m) Cu (%) Ag (g/t) No. Length (m) Cu (%) Ag (g/t) BH01 5.8 1.12 19.0 BHR09 10.0 1.10 20.0 BH04 2.5 0.85 4.0 BHR10 3.0 0.82 12.0 BH06 2.0 1.30 - BH100 5.0 1.20 1.42 BH07 1.3 0.98 - Inc. 3.0 1.64 1.85 BH09 3.0 0.75 - BH107 3.
Slide 10: Zone 1 North – Shallow, Tabular Copper Mineralisation
10 ZONE 1 NORTH – SHALLOW, TABULAR COPPER MINERALISATION
Slide 11: Initial Portfolio / Zones
11 ZONE 2 INITIAL PORTFOLIO • District scale deposit ZONE 4 • Thus far only drilled 5% of project • All four zones show sedimentary copper mineralisation ZONE 1 over multi kilometre strike lengths • Mineralisation primarily hosted in sedimentary rocks, however copper rhyolite discovery could change
Slide 12: Achievements to Date
12 ACHIEVEMENTS TO DATE • Internal resource at Zone 1 based on only 7 months of drilling • Confirmation that Agadir-Melloul is a direct geological analogue of Tizert (130Mt at 0.9% Cu) • Mineralised rhyolite and gold discovered at Zone 2
Slide 13: 2026 Work Programme, Milestones and Catalysts
13 2026 WORK PROGRAMME, MILESTONES AND CATALYSTS FEB MAR JUN JUL JUL SEP DEC Q1 STARTED MINING INTERNAL PROJECT LARGE MAIDEN FEASIBILITY CONSTRUCTION DIAMOND LICENSE RESOURCE ACQUISITION SCALE RESOURCE1 AND DECISION DRILLING ISSUED MODELLED MET-TEST PERMITTING NEW OWNER’S ZONES ZONE 1 FRONTIER AFRIL
Slide 14: Exploration Target
14 EXPLORATION TARGET AREA (km2 of Adoudounian) % / KM2 MINERALISED CuEQ GRADE (%) Potential Resources Contained copper eq. TARGET 50 10% 5.0 1.2% 25MT 300KT 50 15% 7.5 1.2% 38MT 450KT 300,000 tonnes = c.$3.0 billion NSR 65 10% 6.5 1.1% 33MT 358KT Net Smelter Revenue 65 15% 9.75 1.1% 49MT 536KT $13,
Slide 15: Tizert Analogue
15 55km west of Agadir Melloul TIZERT Tizert started life with 1.1Mt at 2.3% Cu and 65 g/t Ag now 130MT at 0.9% copper + silver credits ANALOGUE Agadir Melloul is starting a similar journey TIZERT JOURNEY: RESOURCE PHASE 1 130 MT RESOURCE GROWTH (17Y) EXPECTED 1.1 MT PLANNED 100MT M&I “VERY OUTPUT R
Slide 16: Continued Drilling
16 FAST-TRACK DEVELOPMENT 600 to 1,000 tpd Initial Mine • Earning-in to 60% through development of modest scale copper flotation plant CONTINUED DRILLING • Production provides path to cashflow within 3.5 years STRATEGIC RESOURCE Targeting a large-scale discovery • Majority of value from Strategic Re
Slide 17: The CMR Vision
17 THE CMR VISION SHALLOW DRILLING FOR FEASIBILITY STUDY TO START RAPID GROWTH OF COPPER IMMEDIATELY WITH MINE EISA • Morocco is an excellent destination for mining RESOURCES ALREADY SUBMITTED • It is geologically well endowed with known but underexplored metallogenic belts • Its mining regulations
Slide 18: Appendix
18 APPENDIX METALLURGY, COMPARATORS, IGNEOUS UPSIDE
Slide 19: Mineralised Rhyolite Discovery
19 MINERALISED RHYOLITE DISCOVERY • At surface rhyolite discovery at Zone 2 • Potential for separate copper – silver, igneous discovery • Some parts of the rhyolite also contain gold • BHR6 1.0m at 4.52g/t gold • BHR7 1.0m at 2.5g/t gold RHYOLITE CORE 6.0m at 1.4% Cu and 30g/t Ag 10m at 1.1% Cu and
Slide 20: Orebody Thickness Analogues
20 OREBODY THICKNESS ANALOGUES KUPFERSCHIEFER / LUBIN / KGHM : OREBODY CuEq GRADE DEPTH Mine Company WIDTH (m) GRADE (at 2.0M) (M) LUBIN KGHM POLSKA MIEDZ S.A 2.8 1.2% 1.2% 350-1000 MANSFELD MKM MANSFELD KUPFER 0.5 3.5% 1.0% 0-1000 AGA-MELLOUL CRITICAL MINERAL RES. 2.0* 1.2%* 1.2% 0-50 * 2.0m and 1.
Slide 21: Metallurgy
21 METALLURGY • Testwork undertaken by Afrilab in Marrakesh (SGS Certified) • Mineralogy and Metallurgy typical of West Anti-Atlas • Sulphide to oxide ratio of approx. 80:20 • Copper and silver sulphides must be recovered at the head of the circuit without sulphidation; oxidized copper is then recov
Slide 22: Contact
CONTACT CEO Charlie Long [email protected] REGISTERED OFFICE Eccleston Yards 25 Eccleston Place London SWIW 9NF
Critical Mineral Resources — Investor Presentation (June 2026) on 6ix