  1. Slide 1: Expert Working Group

    Expert Working Group Nov 17th, 2014

  2. Slide 2: Agenda

    Agenda • Product design principles SDR from DSO-grid (14:00-14:15) • Submetering (14:15-14:30) • Baselining (14:30-15:15) Break (15:15-15:30) • Prequalification (15:30-16:00) • Contract DSO- SDR DSO provider (16:00-16:15) • R3DP 2016 (16:15: 16:30) • STS R3DP (16:30-16:45) • Conclusion & Next steps

  3. Slide 3: Product Design principles SDR from DSO-grid

    Product Design principles SDR from DSO-grid Key questions:  As explained in previous sessions (Experts WG & TFiSR): o design questions related to SDR will mainly be discussed in TF iSR o in order to reduce complexity Elia aims at keeping differences between SDR-DSO and SDR-TSO to a minimum. Ex: sam

  4. Slide 4: Product Design principles SDR from DSO-grid: Shedding modalities

    Product Design principles SDR from DSO-grid Shedding modalities:  During Last task Force Elia proposed to make SDR evolve from “DROP TO” also to “DROP BY” and offer the possibility to SDR candidates to choose between two options: DROP TO a fixed Shedding Limit DROP BY a fixed Power (deltaP) Target

  5. Slide 5: Product Design principles SDR from DSO-grid: Impact on BRPs perimeter

    Product Design principles SDR from DSO-grid Impact on BRPs perimeter in case of activation:  When using flexibility provided by decentralized resources and parties that are not BRP, the impact on supplier and BRP have to be handled:  Several models have been discussed for a few years within Elia a

  6. Slide 6: Submetering

    Submetering  Improves accuracy of determination activated flexibility service/volume  Provides extra liquidity by allowing diversification in offered flexibility services at 1 customer site Expert WG 14/10/2014 Rapport Forbeg dd. 3/2/2014  Use: subject to product design,  Important principles :

  7. Slide 7: R3DP 2016 SDR DSO 2015-2016

    R3DP 2016 SDR DSO 2015-2016 Expert WG ELIA 17/11/2014

  8. Slide 8: Sub-meter

    Sub-meter  DSO understands the potential need of sub-meter  When a sub-meter is needed for the market processes, the DSO (as neutral party) must  Place, collect and validate sub-metering data  Calculate flexibility data : cf. base-lining  Facilitate the Settlement: sum of flexibility data per E

  9. Slide 9: Content

    Content 1. What is a baseline and for which purpose will it be used for ? 2. Many baseline methods 3. What‘s the best baseline ? 4. Baseline process - Roles & Responsabilities (to define) 5. Proposal of planning and next steps Expert Working Group – 1711/2014 9

  10. Slide 10: What is a baseline and why is it needed?

    What is a baseline and why is it needed ? • A baseline is an estimate of the electricity that would have been consumed/produced by a customer in the absence of a demand response event. Event duration effectively activated energy volume Consumption P [kW] Fixed shedding limit 1/4h • Control of activa

  11. Slide 11: What baseline(s)?

    What baseline(s) ? • Not necessary to “reinvent the wheel” : several baseline methods exist already ! • Methods based on historical measured data: averaging methods (X of Y), regression methods, meter before/after, … with or without adjustements • Already used baselines: - R3DP : static baseline sha

  12. Slide 12: What's the best baseline?

    What’s the best baseline ? Fundamentals • Getting everyone to agree on one (or several) baseline(s) • Must be in line with the goals and interests of all stakeholders Acceptance • Estimation of the effectively activated energy Accuracy volume within a (statistical) confidence interval Precision • Fi

  13. Slide 13: Baseline process

    Baseline process General principles (proposal) Starting phase Validation Activation Verification phase control phase • No or limited experience  learning process • Consultation process • Publication of validated baseline methodologie(s) Expert Working Group – 1711/2014 13

  14. Slide 14: Baseline process: Roles & Responsibilities

    Baseline process Roles & Responsibilities to define … Starting phase Planning ? • Baseline methods proposed by aggregators ? • One or several methodologies ? • Baseline / EAN • Need to validate ? Activation control Verification phase • Part of the functioning rules • Part of the contract When ? Why

  15. Slide 15: Baselining – how to get to a baseline

    Baselining – how to get to a baseline… Final GO Deadline Informative Planning as agreed with Minister Call for Results implementation ≥Jul CREG & DSOs <15 Jan tender 30 Oct Jan 2014 Jul Sep Nov 2015 Mar May Jul Sep 2015 Today Input from FOD/SPF < 15/10 Tendering SoS analysis <15/11 Volumes FOD/SPF a

  16. Slide 16: Independent Aggregator POV

    Elia Expert WG 17/11/14 Independent Aggregator POV This document is strictly confidential. Any use of the information contained herein for purposes other than those mentioned, is prohibited. Unauthorized distribution is prohibited.

  17. Slide 17: Baseline design principles

    Baseline design principles = Accuracy >» Providers should receive credit for no more and no less than the curtailment/ enhancement volumes they actually provide = Integrity >» A program should not encourage irregular consumption and irregular consumption should not influence baseline calculations; i

  18. Slide 18: Baseline best practices

    Baseline best practices* = Customer specific baseline rather than a portfolio baseline [simplicity and aligment] = Use Y days as baseline window [accuracy and integrity] = Select X days, where X is less than Y to exclude days with lowest load [accuracy] = Applying high X of Y exclusion rules among “

  19. Slide 19: Proposed baseline based on principles and best practice

    Proposed baseline — based on principles and best practice = Where it increases accuracy at a reasonable cost, the baseline should be based on the sub metering data " To strike the best balance between simplicity and accuracy, the baseline should be based on > 4of5 of the last weekdays if the event i

  20. Slide 20: Baseline methodology choice: Behind the meter generation

    Baseline methodology choice: Behind the meter generation = Emergency gensets > Donotrun on a regular basis (as opposed to CHP) >» Baseline should be 0, i.e. all energy produced by genset during an event should be counted as activated energy > Implicitly covered by general baseline methodology using

  21. Slide 21: Baseline methodology choice: Who does what?

    Baseline methodology choice: Who does what? Vv VvVVWV WwW VvVVV YW > > Role of the aggregator (BSP) Receives head-metering from DGO or TGO Receives sub-metering from sub-metering provider (consumer or other) Calculates baseline based on approved methodology Calculates activated energy based on diffe

  22. Slide 22: Baseline methodology choice: Other considerations

    Baseline methodology choice: Other considerations = Only one baseline therefore no need to choose baseline based on DR type = Accuracy of chosen baseline methodology can be evaluated in the specific Belgian context by the TGO and adapted if needed for SDR 2016-17 > Based on sub-metering data provide

  23. Slide 23: R3DP 2016 SDR DSO 2015-2016

    R3DP 2016 SDR DSO 2015-2016 Expert WG ELIA 17/11/2014

  24. Slide 24: Base-lining

    Base-lining  Existing DSO methods in case of missing values  Explanations foreseen  Interest in methods presented by the market  Portfolio of baselines could be possible  Base-line for a client must be selected “in advance” and based on neutral rules  Calculation should be neutral and based on

  25. Slide 25: BREAK !

    BREAK ! 28/02/2012 Footer 25

  26. Slide 26: R3DP 2016 SDR DSO 2015-2016

    R3DP 2016 SDR DSO 2015-2016 Expert WG ELIA 17/11/2014

  27. Slide 27: Pre-qualification

    Pre-qualification  Concerns SDR 2015/2016 & R3DP2016 ”together”  Clear distinction between the client installation and impact of FSP flexibility on the network (NFS):  Content  Responsibilities  Timing  Process EG ELIA 17/11/2014 27

  28. Slide 28: Pre-qualification: DSO document describing client installation

    Pre-qualification  Proposition of a DSO document (name to be found) describing client installation  Extract of the connection contract  Helps the client to understand the content of his connection contract  Informs the client on what he can offer to an FSP (and what not)  In the context of flex

  29. Slide 29: Pre-qualification: Update of C8-01

    Pre-qualification  Update of C8-01 :  Limitation to NFS process  Independent of the ELIA product (for instance R3DP & SDR)  Timing must be in line with tendering ELIA SDR 2015/2016 EG ELIA 17/11/2014 29

  30. Slide 30: DSO/FSP contract

    DSO/FSP contract  Update of DSO/FSP contract :  Unique contract for the ELIA products, for instance R3DP & SDR  Contracted EAN’s by an FSP for an ELIA contract: living annex  Replaces the existing contracts  Proposition (market consultation and approval by regulators) begin 2015, deadline signa

  31. Slide 31: R3DP 2016

    R3DP 2016 Expert WG 14/10: stakeholders call for stability, i.e. prolongation of existing R3DP 2015 product design while maintaining 100MW (?) volume cap. However, stakeholders require …  transparent and non-discriminatory rules for “partial activation”  @TF Balancing  submetering  @TF Balancing

  32. Slide 32: STS R3DP

    STS R3DP Link to SDR: transition to STS as from 1/1/2016 also favors load to participate to SDR tendering and monthly to R3DP for those months outside of SDR period (Apr – Oct) Bidladder ? ELIA will implement  ELIA is committed to ELIA will focus on STS of R3DP and investigate Bidladder open to i