  3. Slide 3: Company Overview

    COMPANY OVERVIEW  Private Energy Company 1.292 MW active power capacity (Natural gas, Hydro and wind) 198 MW hydro at development stage 904 MW CCGT launched in 2014  Role in Market • Established in 1989, one of the largest and most experienced players in the market. • Single-handedly produces 1% o

  4. Slide 4: Strong Shareholder Synergy

    STRONG SHAREHOLDER SYNERGY AKKÖK GROUP CEZ GROUP One of the biggest industrial groups in Turkey CEZ is the largest Czech corporation, and the largest corporation among 10 new EU member states Active in several sectors with main focus on Chemicals,Energy,Real Estate,Port Operations,IT and Insuranc

  5. Slide 5: Akenerji Highlights

    AKENERJI HIGHLIGHTS  Diversified and flexible portfolio mix  Giant base load capacity increase through Egemer by 2014  Experienced trading staff  Profitability Margins are effected positively because of renewables in the portfolio  The total capacity of 388 MW renewable portfolio enables Akener

  6. Slide 6: Operations and Investments

    OPERATIONS and INVESTMENTS Kemah HPP project , which has 198 MW capacity is in the development phase. Capacity Operational Power Plants Capacity [MW] Diversification by 2015 Egemer CCGT 904 Ayyıldız WPP 15 Akocak HPP 81 Bulam HPP 7 Uluabat HPP 100 Burç HPP 28 Feke I HES 30 Feke II HPP 70 Himmetli HP

  7. Slide 7: Sales & Pricing Assumptions

    SALES & PRICING ASSUMPTIONS Akenerji has 3 main types of customers: eligibles, wholesale customers, and DUY system. ELIGIBLE SALES DUY SALES Tariff for Eligible customers is set as a function of the In the DUY Market, since the price is set by the generation company government’s tariff. Akenerji a

  8. Slide 8: Capacity & Sales Development

    CAPACITY & SALES DEVELOPMENT  With the completion of Egemer project, Akenerji’s power generation capacity has increased to 1.292 MW.  In 2013 (an average year in terms of precipitation), average capacity utilisation rate calculated as 32 % for hydro, 35% for wind power plants.  Egemer will start

  9. Slide 9: Egemer Highlights

    EGEMER HIGHLIGHTS Egemer is a 904 MW, natural gas Combined Cycle Power Plant The projects is the largest investment of Akenerji One of the most efficient projects in Turkey with a desirable coastal location, located in Erzin/Hatay, in the south of the country The project has been operational in

  10. Slide 10: Trends & Expectations in Energy Market

    TRENDS & EXPECTATIONS IN ENERGY MARKET 10

  11. Slide 11: Demand for Energy Is Driven by Emerging Markets

    DEMAND FOR ENERGY IS DRIVEN BY EMERGING MARKETS  According to IEA World energy Outlook Report-2011, world primary energy demand will increase by one-third b/w 2010 and 2035.  90% of the projected growth comes from non-OECD  It is forecasted that the increased need in baseload economies; capacity

  12. Slide 12: Demand Growth & Potential

    DEMAND GROWTH & POTENTIAL Electricity consumption is mainly effected by GDP, population growth, urbanization, climate change and efficiency applications. GDP 2011 2012 2013 (1) Turkey 8.8% 2.2% 4.0% EU 1.6% -0.7% -0.4 % Source: IMF, OECD, WB Increasing electricity demand and growth rates tends to

  13. Slide 13: Consumption Dynamics

    CONSUMPTION DYNAMICS Electricity Consumption Trend 14% In the last 20 years, electricity consumption increased 12% remarkably with 6% CAGR. 10% TEIAS forecasts average annual consumption growth of 5,5 % 8% per year for 2010 to 2019. The consumption growth may be shifted due to the global crises bu

  14. Slide 14: Yearly & Monthly Growth Trends

    YEARLY & MONTHLY GROWTH TRENDS In 2014, consumption inreased yoy by 4,3% and has been 256 TWh in Turkey. Monthly Electricity Demand in Turkey (TWh) TWh 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 First two months results of 2015 represents 3,1% increase in Turkey 128

  15. Slide 15: Generation Characteristics

    GENERATION CHARACTERISTICS Turkey's Installed Capacity by Generation Companies (MW) 80.000 BO-BOT-TOR and others 70.000 Private Generation Co. 60.000 Public Generation Co. %13 Fuel Sources 50.000 of electricity 40.000 generation %51 2014 30.000 20.000 %37 10.000 0 2000 2001 2002 1990 1991 1992 1993

  16. Slide 16: Market Mechanism

    MARKET MECHANISM TRY/MWh  The official electricity tariff (for residential /commercial/industrial use) is set by the government every 3 months. Most of the consumption can be contracted outside of the official markets based on the DUY ** prices different from the tariffs.  NG tariffs are determine

  17. Slide 17: Market Liberalization Schedule

    MARKET LIBERALIZATION SCHEDULE Turkish Energy Market deregulation is developed after the UK Model and has been proceeding as per below schedule. Privatization & Liberalization should be expected to start to help create a transparent & competitive market environment. Liberalization NG Market The priv

  18. Slide 18: Current Privatization Overview

    CURRENT PRIVATIZATION OVERVIEW The aim of the GenCo privatizations is to increase the efficiency in the market and provide cheap electricity to the end-user. GenCO DisCO  37% of Turkey’s capacity should be offered to the private sector.  Privatization of 21 DisCos were completed.  The Goverment i

  19. Slide 19: Akenerji Financial Information

    AKENERJI FINANCIAL INFORMATION 19

  20. Slide 20: Financial Performance

    FINANCIAL PERFORMANCE * (*) As Kemalpasa plant has been shut down due to the market conditions, the provision for impairment is booked in 2013. TRY 35,5 mio is added to above calculations to better reveal operational performance. 20

  21. Slide 21: Profitability Performance

    PROFITABILITY PERFORMANCE  In the last three years, Akenerji incurred min 2% and max 22% Ebitda Margin with its diversified portfolio. In 2014, Egemer started its operations and the drought in Turkey effected EBITDA margins negatively. (3) :Impairment losses (Provision the potential value differenc

  22. Slide 22: Consolidated Balance Sheet

    CONSOLIDATED BALANCE SHEET Debt Structure (mio USD) 2010 2011 2012 2013 2014 Cash 26 45 97 114 35 Short-term Financial Debt 227 249 128 97 213 Long-term Financial Debt 372 496 691 865 854 Net Debt (573) (700) (721) (848) (1.032) Key Ratios 2010 2011 2012 2013 2014 Current Ratio 0,6 0,3 1,1 1,0 0,5 L

  23. Slide 23: Stock Performance

    STOCK PERFORMANCE 700% - Partnership with CEZ -Egemer and SEDAS acquisition Electricity Prices/Natural Gas Prices 600% ° —— Stock Performance —— |IMkKB 9 500% DUY market —Energy introduction 400% 300% 200% 100% ve & & & em © SS eee LS eS x A | * AKKOK

  24. Slide 24: Stock Performance vs DUY Prices

    STOCK PERFORMANCE vs DUY PRICES 24

  25. Slide 25: Abbreviations

    ABBREVIATIONS MW : Megawatt TWh : Terawatt hours NG : Natural Gas GDP : Gross Domestic Product CAGR : Compound Annual Growth Rate DUY : Electricity Market Balancing and Settlement Regulation System DISCO : Distribution Companies TRT : Turkish Radio - Television Corporation HPP : Hydroelectric Power

  26. Slide 26: Akenerji Investor Relations

    AKENERJI INVESTOR RELATIONS Akenerji Elektrik Üretim A.Ş. Miralay Şefik Bey Sok. Nilüfer AYDOĞAN No:15 Akhan +90 212 249 82 82 (ext:21130) 34437 Gümüşsuyu +90 212 393 50 18 İstanbul [email protected] Turkey [email protected] This presentation contains information and analysis on financia