British Land Company PLC · LSE:BLND

British Land — Corporate Update (February 2023)

16 slides from British Land's corporate update, Feb 2, 2023

  1. Slide 1: Canada Water Development Construction Liaison Forum

    Canada Water Development Construction Liaison Forum Plots A1 & A2 (and surrounding area) 2nd February 2023

  2. Slide 2: Overview of tonight's presentation

    • Introductions and meeting terms of reference • Canada Water development • Construction management • Updates from contractors • Construction of Plot A1 (Wates) Overview of • Construction of Plot A2 (Mace) tonight’s • Canada Dock (Galldris) presentation • Former Dock Offices • Q&A

  3. Slide 3: Our presenters

    Our presenters SARAH WARD JAMES TURLEY Construction Neighbour British Land Liaison Manager DOVILE CATTERICK DARREN MADIGAN DANIEL BOULTON DAVID WAKE Contractor, Wates Contractor, Wates Contractor, Mace Contractor, Galldris Construction of Construction of Construction of Canada Dock Plot A1 Plot A1 P

  4. Slide 4: Plots A1 & A2

    Plots A1 & A2 • Plot A1 is a 35-storey building providing 186 new homes in The Founding (including intermediate affordable homes), as well as office space and shops and restaurants at ground floor level. • Plot A2 is up to six storeys in height, providing new office space, as well as shops and place

  5. Slide 5: Wider Canada Water development works

    Wider Canada Water development works

  6. Slide 6: Site layout and vehicle access

    Site layout and vehicle access • The haul road, by the former Rotherhithe Police Station, is shared between Plots A1 and A2 and controlled by Alandale Group. • The entrance to the haul road is on Lower Road. Traffic marshals are located on Lower Road to ensure there is no traffic build up and to ens

  7. Slide 7: Common working practices

    Common working practices Standard construction working hours: Noise, dust and vibration monitoring and reporting • Monday – Friday: 8am - 6pm • In line with industry standards and the Construction Management Plans for each development site, environmental • Saturday: 8am - 2pm (no noisy works before

  8. Slide 8: Plot A1

    q im Ime Lt 7] hun i}

  9. Slide 9: Plot A1 – Current site activity

    Plot A1 – Current site activity • Completed work: • Piling • Bulk excavation • Ground floor slab • Current work: • Construction of reinforced concrete structure • Cladding • Mechanical and electrical plant rooms • Upcoming Events: • Tower crane extensions • 18th/19th February (8am-6pm, 9am-6pm) • 18

  10. Slide 10: Plot A1 – Indicative timeline

    Plot A1 – Indicative timeline

  11. Slide 11: Plot A2

    liimace

  12. Slide 12: Plot A2 – Current site activity

    Plot A2 – Current site activity • Completed work: Basement box, and ground floor slab for swimming pools in the leisure centre • Building cores completed and temporary propping has now been removed • Current work: Installation of the steel frame and precast slab continues. Scheduled for completion i

  13. Slide 13: Plot A2 – Indicative timeline

    Plot A2 – Indicative timeline

  14. Slide 14: Canada Dock

    Canada Dock

  15. Slide 15: Canada Dock – site activity

    Canada Dock – site activity • Enabling works beginning next month: • Ground works, earth moving and piling works • Reducing water level to enable full access • Spring 2023: • Works on southern dockside take place • Access between The Range and the dock will be temporarily reduced • Summer 2023: • La

  16. Slide 16: Q&A Contact us

    Q&A Contact us Tel: 0800 470 4593 (freephone) Email: [email protected] Website: www.canadawater.co.uk

British Land — Corporate Update (February 2023) on 6ix