Avista Corporation · NYSE:AVA

Avista — Technical Presentation (May 2024)

37 slides from Avista's technical presentation, May 21, 2024

  1. Slide 1: 2025 Electric IRP TAC Meeting No. 7 Agenda

    2025 Electric Integrated Resource Plan Technical Advisory Committee Meeting No. 7 Agenda Tuesday, May 21, 2024 Virtual Meeting – 8:30 am to 10:00 am PTZ Topic Staff Introductions John Lyons Variable Energy Resource Study Clint Kalich Portfolio/Market Scenarios James Gall ____________________________

  2. Slide 2: 2025 IRP TAC 7 Introductions

    2025 IRP TAC 7 Introductions John Lyons, Ph.D. Technical Advisory Committee Meeting No. 7 May 21, 2024

  3. Slide 3: Today's Agenda

    Today’s Agenda Introductions, John Lyons Variable Energy Resource Study, Clint Kalich Portfolio/Market Scenarios, James Gall 2

  4. Slide 4: Remaining 2025 Electric IRP TAC Schedule

    Remaining 2025 Electric IRP TAC Schedule • TAC 8: June 4, 2024: 8:30 to 10:00 (PTZ) o Load & Resource Balance and Methodology o Loss of Load Probability Study o New Resources Options Costs and Assumptions • TAC 9: June 18, 2024: 8:30 to 10:00 (PTZ) o IRP Generation Option Transmission Planning Studi

  5. Slide 5: Remaining 2025 Electric IRP TAC Schedule

    Remaining 2025 Electric IRP TAC Schedule • TAC 11: July 30, 2024: 8:30 to 10:00 (PTZ) o Preferred Resource Strategy Results o Portfolio Scenario Analysis o LOLP Study Results • TAC 12: August 13, 2024: 8:30 to 10:00 (PTZ) o Preferred Resource Strategy Results (continued) o Portfolio Scenario Analysi

  6. Slide 6: Avista Variable Energy Resource Integration Study Update

    Avista Variable Energy Resource Integration Study Update Clint Kalich Technical Advisory Committee Meeting No. 7 May 21, 2024

  7. Slide 7: Table 18: Integration Costs for Base Scenarios

    Table 18: Integration Costs for Base Scenarios Wind Wind System Forecast Cost Cost Te ~ ‘Columbia Basin 100 MW o% 1% ($275 5.0% Wind's Natura SSS es Diversified Mix 400 MW 20% em 665 12.1% B ] e Diversified Mix 600 MW 30% &% 16.1% Table 24: Effect on Integration Cost of Short-Term Liquid Markets 10-

  8. Slide 8: Differences Between Traditional Resources and VERs

    Differences Between Traditional Resources and VERs Traditional Resources Variable Energy Resources • Gas, coal, hydro, and biomass • Fuel supply subject to the weather • Reliable and known fuel supply • Geographical dispersion may help *** • Responsive to operator direction • Wind fuel supply issues

  9. Slide 9: Loading Profiles (as % of Daily Maximum Loading)

    Loading Profiles (as % of Daily Maximum Loading) January 1, 2024 (5-Minute Data) 4

  10. Slide 10: Comparing Predictability of Load, Wind, and Solar

    Comparing Predictability of Load, Wind, and Solar January 1, 2023, through April 30, 2024 (Hourly T-1 vs. Actual Data) 5

  11. Slide 11: Ancillary Services

    Ancillary Services • What are ancillary services? – capacity services matching real-time variance between load & generation • Why do we need ancillary services? – customer load variation – VER forecast error – forced outages • How do we supply ancillary services? – (generally) “hold back” generator

  12. Slide 12: Ancillaries as They Pertain to VERs (Solar, Wind)

    Ancillaries as They Pertain to VERs (Solar, Wind) various  Spinning Reserves are procured to cover NW reserve-sharing agreement for load and forced outages Also carry operating reserves (spin/non-spin)! 7

  13. Slide 13: Ancillaries as They Pertain to VERs (Solar, Wind)

    Ancillaries as They Pertain to VERs (Solar, Wind) Key Concepts • Integration costs are driven primarily by the need to hold higher levels of reserves • Higher reserve levels are needed because of large variability and uncertainty of VER production • Higher reserve levels means de-optimizing system o

  14. Slide 14: VER Integration Study Scope

    VER Integration Study Scope Purpose and Overview • What’s included in the study? – consumptive capacity and its costs – impacts of EIM (”fast”) markets – potential future portfolio VER buildouts – sensitivity scenarios • What’s not included in the study? – alternative capacity resources (e.g., batte

  15. Slide 15: VER Integration Study

    VER Integration Study Purpose and Overview • Consistent application supporting varying analyses – Integrated Resource Planning – resource acquisition processes (e.g., RFP) – transmission rates – PURPA avoided cost calculations • Define “Consumptive Capacity” associated with incremental variable ener

  16. Slide 16: VER Integration Study Timeline

    VER Integration Study Timeline Timelines have slipped a bit X X * ancillary services covered in later slide ** excludes variation from forced outages that affect all resources 11 *** but estimating this savings is difficult given varying methods employed

  17. Slide 17: VER Buildout Scenarios

    VER Buildout Scenarios Locations Based on Past Proposals • Three VER portfolios • Solar, Wind, 50/50* • Four VER penetrations • 400, 800, 1500, 2500 MW * 50/50 mix created based on nameplate capacity (e.g., 200 MW solar, 200 MW wind) 12

  18. Slide 18: VER Profiles and Forecasts

    VER Profiles and Forecasts Dee dddddddddddddddddddddddddd 13

  19. Slide 19: Reserve Calculations

    14 Reserve Calculations * Reserve levels are determined by taking a statistical confidence interval of “errors” that represent unanticipated variability or uncertainty contributed to the system by VERs * Reserve calculations identify the MW level of reserves required to 95-99% of variability and unc

  20. Slide 20: EIM and Reserves

    EIM and Reserves * The Western EIM facilitates procurement of flexible ramping capacity to address variability that may occur in real-time dispatch “+ The application of flexible ramping capacity serves to reduce the level of Load Following and Forecast Error reserves held within the Avista BAA foot

  21. Slide 21: EIM and Reserves

    EIM and Reserves Dee • For the VER integration study, we reduced consultant-calculated load following and forecast error reserves by 50% to reflect benefits of EIM diversity 16

  22. Slide 22: Study Methodology

    Study Methodology • 2021 actual system conditions with ADSS software – Hydro conditions, outages, fuel prices • Run Avista system portfolio with and without VER – 2 VER condition scenarios: without new VER, with new VER – 5 VER addition scenarios: 400, 800,1500, 2500 MW – 3 VER mix scenarios: all so

  23. Slide 23: Removing Commodity Energy Value from Study

    Removing Commodity Energy Value from Study Two cases include the same energy amounts to avoid biasing results • “Without VER” scenarios – input monthly 12x24 energy shape – no incremental reserves – emulates a firm contract delivery of same energy quantity as With VER • “With VER” scenarios – input

  24. Slide 24: Preliminary Study Results – Average Costs

    Preliminary Study Results – Average Costs Integration Cost ($/kW-mo) Integration Cost ($/MWh) Changeset Base High Low Base High Low Existing 0.16 0.23 0.11 0.78 1.11 0.53 5050 400 0.05 0.15 0.03 0.20 0.66 0.11 5050 800 0.12 0.24 0.08 0.50 1.00 0.34 5050 1500 0.33 0.64 0.21 1.53 3.00 1.00 5050 2500 0

  25. Slide 25: Preliminary Study Results – Marginal Costs

    Preliminary Study Results – Marginal Costs Integration Cost ($/kW-mo) Integration Cost ($/MWh) Changeset Base High Low Base High Low Existing - - - - - - 5050 400 (0.03) 0.10 (0.03) (0.13) 0.39 (0.13) 5050 800 0.11 0.24 0.07 0.42 0.97 0.28 5050 1500 0.36 0.72 0.23 1.66 3.33 1.08 5050 2500 0.62 0.91

  26. Slide 26: Next Steps

    Next Steps • Finalize study results • Generate final study report • Use in future IRPs/RFPs/transmission tariff 21

  27. Slide 27: VER Study Uses in the 2025 IRP

    VER Study Uses in the 2025 IRP • Integration Cost ($/kW-month) included as a resource cost (slide 18) • Reliability modeling will include a “Flex Ramp” adjusted for EIM benefits reserve determined by this study (slide 15) • Capacity expansion modeling will include a small incremental flexible capaci

  28. Slide 28: Questions?

    Questions? 23

  29. Slide 29: 2025 IRP Market Scenario Update (DRAFT)

    2025 IRP Market Scenario Update (DRAFT) James Gall Technical Advisory Committee Meeting No. 7 May 21, 2024

  30. Slide 30: Market Scenario Update

    Market Scenario Update • Expected Case (Deterministic/Stochastic) • Low Natural Gas Prices • High Natural Gas Prices • No Washington Climate Commitment Act 2

  31. Slide 31: Henry Hub Natural Gas Prices

    Henry Hub Natural Gas Prices $14.00 Expected Case Uses 95th percentile of stochastic study $12.00 Low Natural Gas Price Scenario High Natural Gas Price Scenario $10.00 $7.20/dth $ Per Dekatherm $8.00 $5.01/dth $6.00 $3.86/dth $4.00 Uses 25th percentile of stochastic study $2.00 $0.00 2026 2027 2028

  32. Slide 32: Electric Price Forecast – Mid-Columbia (Washington Delivery)

    Electric Price Forecast Mid-Columbia (Washington Delivery) $80.00 $70.00 $60.00 $50.00 $ per MWh $40.00 $30.00 Deterministic ($45.45) Low NG Prices ($41.52) $20.00 High NG Prices ($52.89) $10.00 No CCA ($40.85) $0.00 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 204

  33. Slide 33: Electric Price Forecast – Mid-Columbia (Non-Washington Delivery)

    Electric Price Forecast Mid-Columbia (Non-Washington Delivery) $80.00 $70.00 $60.00 $50.00 $ per MWh $40.00 $30.00 Deterministic ($44.37) $20.00 Low NG Prices ($40.41) High NG Prices ($51.86) $10.00 No CCA ($40.26) $0.00 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041

  34. Slide 34: 2025 IRP Load Forecast

    2025 IRP Load Forecast

  35. Slide 35: System End Use Changes in Load Forecast

    System End Use Changes in Load Forecast Annual Average Load Growth/Decay Rate Annual Average Load Change Between 2045 and 2024 Between 2045 and 2024 Process -1.03% Lighting -22 Lighting -0.93% Generation -11 Motors -0.73% Motors -8 Ventilation -0.72% Ventilation -8 Water Heating -0.47% Water Heating

  36. Slide 36: Energy Forecast

    Energy Forecast 0.81% AAGR 1.08% AAGR 0.31% AAGR 8

  37. Slide 37: Peak Forecast (Forecast is 1-in-2 Weather Event)

    Peak Forecast (Forecast is 1-in-2 Weather Event) 1.02% Winter AAGR 1.10% Summer AAGR 9

Avista — Technical Presentation (May 2024) on 6ix