Slide 1: GMR Infrastructure Ltd Investor Presentation
GMR INFRASTRUCTURE LTD Investor Presentation for quarter ended Dec 31, 2013 0
Slide 2: Table of Contents
Table of Contents Industry Updates Part A: Performance Analysis for quarter ended Dec 31, 2013 Consolidated Financial Performance … 5 Airports Sector … 10 Energy Sector … 19 Highways Sector … 23 Part B: Business Overview Group Overview … 28 Airports Sector … 34 Energy Sector … 36 Hig
Slide 3: Industry Updates: Airports and Energy
Industry Updates Airports 1. The City and Industrial Development (CIDCO) floated a global tender for building Navi Mumbai International Airport having a capacity to handle 60 million passengers a year and has invited RFQ’s on February 5, 2014. The qualification process ends on August 5, 2014. (Sourc
Slide 4: Industry Updates: Highways
Industry Updates Highways 1. Central government is planning to revisit the policy that allows highway developers to exit projects through 100% stake divestment. (Source: Indian Infrastructure magazine) 2. The Economic Advisory Council’s committee has finalised the terms & conditions for rescheduling
Slide 5: Performance Analysis
GAR Performance Analysis Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 6: Consolidated Financial Performance
Consolidated Financial Performance 5
Slide 7: Highlights
Highlights GMR continues its efforts to stabilize the operations and it is consistently focusing on revenue growth across the sectors. The Gross Revenue for the quarter ended Dec-13 has grown by 9% over the previous quarter and EBITDA has grown by 24%, which is mainly on account of improved perf
Slide 8: Net Revenue and EBITDA
Key Indicators INR Mn 82,632 Others Inter Segment Net Revenue EPC 781 1,200 (906) Sectorwise Breakup Highways Sector 62,022 62,697 1,453 Net Revenue Airport Sector 11,207 21,231 Energy Sector 19,403 19,560 7,496 Q2-2014 Q3-2014 Q3-2013 9M-2014 9M-2013 FY 2013 Q3-2014 Others Inter EBITDA 24,773 EPC (
Slide 9: Consolidated Profitability Statement
Consolidated Profitability Statement I NR Mn Q2-2014 Q3-2014 Q3-2013 9M-2014 9M-2013 FY 2013 Ai rports 14,750 16,053 15,985 44,749 43,909 61,202 Power 6,636 7,623 5,206 23,580 19,162 24,295 Roads 1,603 1,633 1,238 4,883 3,353 5,174 EPC 799 781 3,404 3,289 12,034 14,537 Others 1,314 1,200 1,534 4,208
Slide 10: Key Balance Sheet Analysis
Key Balance Sheet Analysis Gross Block as on Dec 31, 2013 INR Mn Others Roads 20,964 Total: 64,829 4% 11% 558,106 Airport 166,016 30% Power 306,296 55% INR Mn INR Mn Mar 31, 2013 Dec 31, 2013 Mar 31, 2013 Dec 31, 2013 458,459 109,693 408,249 98,544 391,701 337,170 71,079 66,758 Gross Debt Cash & Cas
Slide 11: Airports Sector
GAR Airports Sector Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 12: Highlights
Highlights The passenger traffic (YTD) registered a 9.3% YOY growth. Cargo and ATM has grown 9.6% and 3.7% respectively YTD. Aero Revenues have grown by 59% and Non-Aero revenues by 18% YTD. Non-Aero revenues have grown by 19% compared to the corresponding quarter buoyed mainly by growth in Re
Slide 13: Airports Sector Consolidated: Financial Performance
Airports Sector Consolidated: Financial Performance INR Mn Q2-2014 Q3-2014 Q3-2013 9M-2014 9M-2013 FY 2013 Aero Revenue 7,979 8,652 6,955 24,755 17,753 27,526 Non Aero Revenue 5,218 5,804 5,448 15,469 15,167 20,112 Cargo 716 717 413 2,142 1,171 2,770 CPD Rentals 256 258 250 766 748 993 Fuel income 5
Slide 14: Delhi International Airport: Operational Performance
Delhi International Airport: Operational Performance Passenger (Mn) ATM ('000) 300.92 Domestic International Total Domestic International Total 34.37 220.32 76.49 80.58 74.70 80.60 57.10 60.36 53.30 19.40 20.22 21.41 22.80 Q2-2014 Q3-2014 Q3-2013 FY 2013 546.31 Cargo ('000) Domestic International To
Slide 15: Delhi International Airport: Financial Performance
Delhi International Airport: Financial Performance INR Mn Particulars Q2-2014 Q3-2014 Q3-2013 9M-2014 9M-2013 FY 2013 Aero Revenue 6,315 6,937 5,302 19,827 12,491 21,307 Non Aero Revenue 2,461 2,707 2,280 7,580 6,406 9,101 Cargo Revenue share 352 347 335 1,049 955 1,294 CPD Rentals 235 235 222 701 6
Slide 16: Delhi International Airport: Revenue Analysis
Delhi International Airport: Revenue Analysis (INR per pax) Other Revenue Total: 62 1,080 6% Non Aero Revenue 285 UDF 26% 498 46% Other Aero Revenue 235 22% Q3-2014 Other Revenue Total: 63 948 7% Non Aero Revenue UDF 265 395 28% 41% Other Aero Revenue 225 24% FY-2013 15
Slide 17: Hyderabad International Airport: Operational Performance
Hyderabad International Airport: Operational Performance Passengers (Mn) ATM ('000) 90.65 Domestic International Total Domestic International Total 8.38 75.28 6.29 21.51 22.43 22.19 17.31 18.14 18.18 15.36 4.20 4.29 4.01 Q2-2014 Q3-2014 Q3-2013 FY 2013 Cargo ('000) 83.99 Domestic International Total
Slide 18: Hyderabad International Airport: Financial Performance
Hyderabad International Airport: Financial Performance INR Mn Q2-2014 Q3-2014 Q3-2013 9M-2014 9M-2013 FY 2013 Aero Revenue 1,050 1,036 819 3,149 2,532 4,233 Non Aero Revenue 710 745 651 2,140 1,895 2,671 Cargo Revenue Share 30 30 26 90 79 107 Gross Revenue 1,790 1,811 1,496 5,378 4,506 7,011 Less: R
Slide 19: Hyderabad International Airport: Revenue Analysis
Hyderabad International Airport: Revenue Analysis (INR per pax) Other Revenue Total: 14 827 2% UDF Non Aero 348 Revenue 42% 340 41% Other Aero Revenue PSF 88 37 11% 4% Q3-2014 Other Revenue Total: 13 837 1% Non Aero UDF Revenue 376 319 45% 38% PSF Other Aero 39 Revenue 5% 91 11% FY-2013 18
Slide 20: Energy Sector
GAR Energy Sector Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 21: Highlights
Highlights EMCO & Kamalanga power plants have contributed revenues of Rs 5,775 mn during the current financial year. Past dues in TNEB has reduced substantially with receipt of around Rs 12,190 mn during the current year. TNEB has invited GPCPL for negotiation for extension of period of power supply
Slide 22: Energy Sector Consolidated: Financial Performance
Energy Sector Consolidated: Financial Performance INR Mn Q2-2014 Q3-2014 Q3-2013 9M-2014 9M-2013 FY 2013 Power Generation 4,301 5,023 2,593 15,594 10,254 13,162 Coal Revenue 1,821 1,564 2,090 4,896 6,376 7,797 Power Trading and others 514 1,036 523 3,089 2,532 3,292 Gross Revenue 6,635 7,623 5,206 2
Slide 23: Energy Sector - Power Generation: Operational Performance
Energy Sector - Power Generation: Operational Performance PLF (%) Q2-2014 Q3-2014 Q3-2013 FY 2013 65% 52% 53% 38% 39% 35% 36% 32% 26% 19% 20% 19% 19% 18% 13% 15% 0% 0% 0% 0% 0% 0% 0% 0% GEL GPCL VPGL EMCO* GKEL** Solar Net Generation (MU) 700.0 600.0 500.0 400.0 300.0 200.0 100.0 0.0 GEL GPCL VPGL E
Slide 24: Highways Sector
GAR Highways Sector Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 25: Highlights
Highlights Divestment of 74% stake in Jadcherla road project completed Divestment of 74% interest in GMR Ulundurpet Road project is in advance stage of closure Toll rates have increased during the year on account of the following inflation adjustments: Asset Inflation Adjustment Date GACEPL 7.35% 01
Slide 26: Highways Consolidated: Financial Performance
Highways Consolidated: Financial Performance INR Mn Q2-2014 Q3-2014 Q3-2013 9M-2014 9M-2013 FY 2013 Annuity Revenue 623 628 628 1,871 1,869 2,485 Toll Revenue 980 1,005 610 3,013 1,485 2,688 Gross Revenue 1,603 1,633 1,238 4,883 3,353 5,174 Less: Revenue Share 170 180 25 531 25 211 Net Revenue 1,433
Slide 27: Highways - Toll Projects: Operational Performance
Highways - Toll Projects: Operational Performance 7.50 Traffic (mn) 18.00 Traffic PCU (mn) 6.00 15.00 12.00 4.50 9.00 3.00 6.00 1.50 3.00 - - GACEPL GUEPL GHVEPL GOHHPL GACEPL GUEPL GHVEPL GOHHPL Q2-2014 2.19 1.93 3.40 1.09 Q2-2014 2.97 4.00 7.67 3.71 Q3-2014 2.29 1.84 3.62 1.11 Q3-2014 3.03 3.65 7.
Slide 28: Business Overview
Business Overview Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 29: Group Overview
Group Overview Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 30: Business Structure
Business Structure Creating successful businesses across the spectrum of infrastructure Airports Energy Highways Urban Infrastrucuture • Delhi : 60 mn pax capacity • Power Generation •Operational • Delhi Airport: 230 acres •Operational: 2136MW •Annuity: 255 kms • Hyderabad: 12 mn pax capacity •Under
Slide 31: Corporate Structure
Corporate Structure The Group has been conferred with the Most Caring Shareholding FIIs 11.8% Company Award-2013 at a ceremony in Mumbai GIL Pattern As on Dec 31 2013 Promoter & Promoter Group 71.7% MF & DIIs 7.5% Others 9.0% 97% * 98% * 100% Airports Energy Roads (GMR Airports Limited) (GMR Energy
Slide 32: Visionary Leadership Building Professional Institution
Visionary Leadership Building Professional Institution THE GROUP HOLDING BOARD THE GMR INFRA LTD. BOARD Executive G M Rao Chairman Managing Kiran Kumar Grandhi Director Srinivas Bommidala Group G B S Raju Directors B V Nageswara Rao O Bangaru Raju Directors K V V Rao N C Sarabeswaran Dr Prakash G Ap
Slide 33: Our demonstrated competencies in the Value Creation Process
Our demonstrated competencies in the Value Creation Process 32
Slide 34: Awards & Recognition
Awards & Recognition •Presented with the prestigious `Most Admired Infrastructure Company – Overall’ at the 5th KPMG Infrastructure Today Awards 2012-13 •The Group has been conferred with the Most Caring Company Award-2013 at a ceremony in Mumbai GIL •Awarded with the globally recognized Airport Car
Slide 35: Airports Sector
GAR Airports Sector Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 36: Airport Asset Details
Airport Asset Details GMR is the largest private developer and operator of Airports in India Annual Passenger Project GMR Stake Traffic in FY 2013 Project Cost Concession Terms Capacity 30 + 30 years concession DIAL 34.37 mn Pax; Rs. 128 bn for Phase I 54% 60 mn 46% Revenue share New Delhi, Indi
Slide 37: Energy Sector
GAR Energy Sector Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 38: Energy Assets
Energy Assets 2,136MW in operation and 5,043MW under implementation Presence across the entire value chain covering diverse geographies makes it one of India’s few fully integrated players Alaknanda - BHPGPL Upper Marsyangdi - HHCPL Upper Karnali - GUKHL Bajoli Holi - GBHHPL (300MW / Hydro) (600MW /
Slide 39: Power Assets Portfolio Summary
Power Assets Portfolio Summary Capacity by stage Capacity build-up Operational MW 2,136 9,000 7,179 30% 1,725 7,000 350 480 5,000 2,138 Under 350 Exploration 3,000 2,025 2,136 28% 1,000 Under Construction -1,000 Till date FY14 FY15 FY16 FY17 FY18 FY19 Total 3,018 7,179MW 42% Fuel type split1 MW 9,00
Slide 40: 2,136 MW of Operational Power Generation Capacity
2,136 MW of Operational Power Generation Capacity Project Commencement Capacity GMR Stake Fuel Type Project Cost Power Off-take Additional Information (Capacity MW) of Generation GPCL Rs. 8,250 mn 100% Regulated Tariff 200 MW 51% LSHS1 February 1999 Chennai ($ 138 mn) 15 yrs PPA till 2014 Relo
Slide 41: 2,668 MW of Power Projects under Construction
2,668 MW of Power Projects under Construction Project Project GMR Stake Fuel Type Completion Expected CoD Off take Arrangement Other Information Milestones Achieved (Capacity MW) % GREL High on the gas Rajahmundry Natural Based on Gas 100% - allocation list from KG Andhra Pradesh Gas availability
Slide 42: Power Projects under Exploration
Power Projects under Exploration Talong, Arunachal Pradesh (225MW / Hydro) - GLHPL Alaknanda, Badrinath (300MW / Hydro) - 40 years from CoD BHPGPL 14% power to be supplied as royalty 45 years from Implementation Agreement Environment Study Approved by MOEF 13% free power to State TOR app
Slide 43: Transmission Projects
Transmission Projects Project Expected Project GMR Stake Length Configuration Milestones Achieved Completion % CoD MTSCL Two 400 KV S/C and one 220 Possession of land (61 acres) completed Maru 100% 265 kms 99% FY2014 KV D/C transmission lines Transmission Service Agreement completed Rajasthan
Slide 44: Fuel security: Coal Mining Asset Overview
Fuel security: Coal Mining Asset Overview Rampia Mine Block and Dip side of Rampia, Orissa Golden Energy Mines, Indonesia Blocks jointly allocated to six companies: GMR, Acquired 30% stake in in PT Golden Energy Mines Lanco, Reliance, Navbharat, Arcelor Mittal & TbK (“GEMS”), a Sinar Mas Group c
Slide 45: Highways Sector
GAR Highways Sector Humility | Entrepret ips | Deliverfhe Promise | Learning | Social Re:
Slide 46: Highways Assets
Highways Assets 643 kms in Operation and 29 kms Under Implementation 284 kms Annuity based and 388 kms Toll based Significant scale-up in the Highways business from the under-construction projects Chandigarh-Ambala Highway – GACEPL (35 kms) Tuni-Anakapalli Highway – Adloor-Gundla Pochanpalli GTAEPL
Slide 47: Highways Projects – Annuity (284 kms)
Highways Projects – Annuity (284 kms) Operational (255 kms) Project GMR Stake Road Length Project Cost Scope of Work CoD Concession Period GTAEPL 2 to 4 laning of existing stretch on Rs. 2,950 mn 100% 59 kms NH45 December 2004 17.5 years from May 2002 ($ 49 mn) Tuni – Anakapalli DCDFOM1 of the e
Slide 48: Highways Projects – Toll (388 kms)
Highways Projects – Toll (388 kms) Operational (289 kms) Project GMR Stake Road Length Project Cost Scope of Work CoD Concession Period 2 to 4 laning of stretch on NH21 & GACEPL Rs. 4,993 mn NH22 100% 35 kms November 2008 20 years from May 2006 ($ 83 mn) Maintenance and strengthening of Ambala –
Slide 49: Thank You