  1. Slide 1: Annual General Meeting

    Annual General Meeting 06 August 2020

  2. Slide 2: Contents

    Contents • Corporate Overview • Objectives Talisman Project • Health and Safety • General progress update • Next Steps 2 © New Talisman Gold Mines Ltd – Company Update, 5 September 2017

  3. Slide 3: Corporate Overview

    Corporate Overview Capital Structure 1 Board Shares on issue Market capitalisation 2 Charbel Nader Non-Executive Chairman 2,792m NZ$22.36m Matthew Hill Managing Director and CEO Options Cash Debt Murray Stevens Non-Executive Director Listed Unlisted Tony Haworth Non-Executive Director NZ$2.2m Nil Ja

  4. Slide 4: Gold Price – NZD

    GOLD PRICE – NZD © New Talisman Gold Mines Ltd – Company Update, 5 September 2017

  5. Slide 5: Talisman Gold Project - Health and Safety

    Talisman Gold Project - Health and Safety • The Health and Safety of our workers and all operations on the Talisman Gold Project is critical to the Company. • Site hazards and underground activities are actively managed. • Since establishment on site in June 2017 there have been no LTI’s or medical

  6. Slide 6: Recap on last year

    Recap on last year • Mobilised in June 2017 • Established site and rehabilitated over 700m on No 8 Level • No reportable safety incidents • Services extended into Dubbo and Mystery • Fan in Place; • First blast in Mystery • Commission Vent Fan; • Utilise mobile equipment to clean Dubbo and Mystery;

  7. Slide 7: Developing a processing route

    Developing a processing route Objectives of testwork were to verify precious metal recovery and verify quality of tailings for use in industrial applications. TESTWORK RESULTS • Achieved the desired grind size with 98% of the ore less than 100µm and 96.1% less than 75µm ; • Primary Concentration (Ce

  8. Slide 8: Dubbo

    Dubbo • Cleaning the Dubbo rise started in December 2018; • Approximately 250 tonne of rock removed; • Significant geotechnical hazards encountered 8 © New Talisman Gold Mines Ltd – Company Update, 5 September 2017

  9. Slide 9: Dubbo

    Dubbo • The rise is significantly longer than records indicate; • Likely holed through into an unrecorded excavation above; • Winze of unknown length present below 8 Level • In very poor condition presenting a number of ? hazards 9 © New Talisman Gold Mines Ltd – Company Update, 5 September 2017

  10. Slide 10: Mystery

    Mystery • Pleasing increase in resource grade to approx. 25g/t; • Presents a significant opportunity to increase resource quantum; 10 © New Talisman Gold Mines Ltd – Company Update, 5 September 2017

  11. Slide 11: Consultation and stakeholder engagement

    Consultation and stakeholder engagement Iwi • Have developed a very positive relationship with Ngati Tara Tokanui • Continued engagement and site visits • Other groups largely unresponsive Community • Have continued the strategy of face to face engagement • Several site visits by locals, including M

  12. Slide 12: Rahu

    Rahu • Access is problematic • NZPAM directed activities in the northern area of the permit which is DOC land • Application for activities on the DOC land was unable to be attained • Engaging with DOC, Iwi and NZP&M has failed to find a resolution and with the decline by NZPAM to change the permit c