Ptr Minerals Limited · ASX:PTR

Ptr Minerals — Petratherm — South Australia's Future Energy Conference 2009

18 slides from Ptr Minerals's conference presentation, Aug 18, 2009

  1. Slide 1: South Australia's Future Energy

    South Australia’s Future Energy “Building a portfolio of quality geothermal energy projects - Australia and Overseas” 18 August 2009 Presented by Terry Kallis (Managing Director) Explorer and Developer of Geothermal Energy

  2. Slide 2: Disclaimer

    Disclaimer This presentation has been prepared by Petratherm Limited (Petratherm). The information contained in this presentation is a professional opinion only and is given in good faith. Certain information in this document has been derived from third parties and though Petratherm has no reason to

  3. Slide 3: Presentation Outline

    Presentation Outline • Corporate DVD (8 minutes) • Corporate Overview • Geothermal Energy Technology • Paralana Project – Overview – JV arrangements – Drilling program and fracture stimulation • Key Points of Differentiation • Outlook for Calendar 2009 petratherm

  4. Slide 4: Corporate Overview (PTR.AX)

    Corporate Overview (PTR.AX) China – Exclusive Key Statistics Madrid & Barcelona – exploration ¾ Current shares on issue – 92 m direct use heat, agreement ¾ Market capitalization - $28.5m (at share EGS and price of $0.30) hydrothermal ¾ Cash – June 30 $13 m ¾ Grants - GDP $7.0m ¾ Grant Application –

  5. Slide 5: Corporate Mission & Business Model

    Corporate Mission & Business Model Mission “to explore for and develop, emission free, geothermal energy projects that are commercially sustainable” Business Model “to develop a portfolio of quality geothermal energy projects conventional and EGS – for power and/or heat – where there is a favourable

  6. Slide 6: Petratherm Board

    Petratherm Board Highly experienced Board with combination of commercial and technical skills including: • Corporate governance • Financial management • Legal DerekCarter Derek Carter Simon O’Loughlin Richard Hillis Chairman Chairman Director Director • Marketing • Project Management • Exploration a

  7. Slide 7: Corporate Overview – Skills & Capabilities

    Corporate Overview – Skills & Capabilities Combined skills and experience of the Board Management, Partners and Consultants capable of delivering successful geothermal energy projects – from underground resource through to market Beach Petroleum - Subsurface – well design, drilling and fracture stim

  8. Slide 8: Geothermal Energy Technology - Project Portfolio

    Geothermal Energy Technology - Project Portfolio TAG – thermally anomalous granite EGS technology – hot rocks Large systems – low enthalpy TAG Abundant resource Requires large commercial demonstration Paralana – EGS – power production East Gippsland – Hot sedimentary aquifer Tenerife and Gran Canari

  9. Slide 9: Paralana Project - Overview

    Paralana Project - Overview ¾ Uniquely positioned to be potentially commercially viable at all Stages! 9 High heat flow rate (128mW/m²) and predicted Temperature of 200˚C at a depth of 3600 metres 9 Stable geological formation and expect no overpressures – suggests good drilling conditions 9 Very cl

  10. Slide 10: Paralana Project Joint Venture

    Paralana Project Joint Venture ¾Beach Petroleum Farmin (Jan 2007) for up to $30M for 36% ƒ $5M first well and stimulation ƒ $5M second well and stimulation – earns 21% ƒ After HEWI - Option to earn a further 15% for $20M ƒ Plus equity share of project costs at every stage ¾TRUenergy Farmin (Aug 2008

  11. Slide 11: Paralana Project

    Paralana Project 109oC • Heat flow of 128 mWm-2 petratherm • Modeled 200oc at 3.6km (Seismic Line 84 SPG)

  12. Slide 12: Paralana 2 - Development Path to date

    Paralana 2 - Development Path to date • 2D Reflection Seismic and MT Surveys • Installed Passive Seismic Array (IESE) • Cleared 1km x 2km development site • Casing and well head ordered • Camp Established and Crew Trained • Drilling rig arrived, transported, assembled and drilling at a depth of ???

  13. Slide 13: Paralana 2009 Development Plan

    Paralana 2009 Development Plan • June 2009 First Deep Well to ~ 4 Kms • Well testing and stimulation program • First half 2010 Second Deep Well Heat Exchanger Within Insulator (HEWI) Model petratherm

  14. Slide 14: Paralana 2 Well Drilling

    Paralana 2 Well Drilling • Contract 2000 HP Drilling Rig # 828 from Weatherford International Drilling arrived in Port Pirie in May 2009 - Le Tourneau – “ Lightning Rig” built in Dubai • Paralana 2 well spud in late June 2009 • Well Testing and Stimulation Program to follow after well completion • P

  15. Slide 15: Paralana Drilling Rig and Camp Site

    Paralana Drilling Rig and Camp Site

  16. Slide 16: Petratherm Key Points of Differentiation

    Petratherm Key Points of Differentiation • Unique approach to “exploration for heat” and its commercial assessment of projects - “location, location, location” – resource, market, permits/stakeholders • HEWI model approach to resource exploitation process for EGS/hot rock that aims reduce costs and

  17. Slide 17: Petratherm Outlook for Calendar 2009

    Petratherm Outlook for Calendar 2009 • Finalize the $57M TRUenergy Farm-in 9 January • Secure $7M GDP funding for drilling 9 April • Spud Paralana 2 deep well (4kms) 9 June • Drill/complete well (around 3 to 4 months) followed by , testing logging, fracturing and stimulation program in second half o

  18. Slide 18: Thank You

    ASX code: PTR Thank You petratherm www.petratherm.com.au

Petratherm — South Australia's Future Energy Conference 2009 on 6ix