Nautilus Minerals — Investor Presentation (April 2014)

11 slides from Nautilus Minerals's investor presentation, Apr 29, 2014

  1. Slide 1: Nautilus Minerals Investor Update

    Nautilus Minerals Investor Update April 29, 2014 1

  2. Slide 2: Disclaimer and Legal Notice

    Disclaimer and Legal g Notice  This Presentation may contain forward-looking statements within the meaning of the United States Securities Exchange Act of 1934 and forward-looking information within the meaning of applicable Canadian securities law.  Material forward-looking statements and forward

  3. Slide 3: Agreement signed with Independent State of Papua New Guinea

    Agreement signed with Independent State of Papua New Guinea (the “State”) State )  The Government of PNG has h approved d th the State’s participation in the j Solwara 1 Project  Under the Agreement, the State shall take an initial 15% interest i t t in i the th P Project j t  Non-refundable depo

  4. Slide 4: The Agreement

    The Agreement g  The State has paid Nautilus a non-refundable deposit for its initial 15% interest of US$7,000,000  The Th remaining i i ffundsd off US$113 US$113,000,000 000 000 tto b be paid id b by th the St State t by 31 July 2014 to be placed in escrow  Bank of South Pacific providing the fi

  5. Slide 5: Immediate Plans

    Immediate Plans  Satisfy Nautilus’ Conditions Precedent under the Agreement  Continue C ti with ith th the b build ild off the th seafloor fl production d ti equipment i t – Assembly of the Bulk Cutter was completed earlier this month – Assembly work on the Auxiliary Cutter and Collecting Machine

  6. Slide 6: Immediate Plans (continued)

    Immediate Plans (continued)  Vessel – remains the critical path for the Project – Looking at securing a suitable vessel arrangement – In discussions with potential vessel building partners – Tender process currently underway with shipyards experienced in building offshore construction vessels – Ves

  7. Slide 7: Production Support Vessel – Key Elements

    Production Support pp Vessel – Key y Elements  Principal Particulars: • Length 227m • Breadth 40m • Depth 18.2m • Ore Storage Capacity 45,000Te • Power Generation 31MW • Complement 180 • Dynamic Positioning DP 2 Ship Yard Base Scope • ABS Class Approved Basic Design Vessel on Delivery Vessel in Ope

  8. Slide 8: Milestones For Next 12 Months

    Milestones For Next 12 Months Milestone Expected Date of Completion Auxiliary Cutter chassis and Collecting June 2014 Machine chassis to arrive at SMD facility to commence assembly Factory Acceptance Testing on Bulk July 2014 Cutter Receive the State’s full capital 31 July 2014 contribution in escro

  9. Slide 9: Other Projects

    Other Projects  Looking to accelerate our impressive pipeline of projects  In discussions with a number of interested parties regarding – seafloor fl massive i sulphides l hid ini other th jjurisdictions i di ti – nodules in the Clarion Clipperton Zone (CCZ) – Equipment partnering/Joint Ventures (

  10. Slide 10: Forward Plan

    Forward Plan  Satisfy Nautilus’ Conditions Precedent  Receive the State’s full capital contribution in escrow by July 31, 2014  Move M forward f d with ith th the Solwara S l 1 Project P j t – Accelerate equipment build – Secure vessel solution – Ensure continued government and community support

  11. Slide 11: Contact

    [email protected] @ www.nautilusminerals.com www.cares.nautilusminerals.com Month 2013 11